15.02.2014 Aufrufe

Concrete Plant + Precast Technology Betonwerk + Fertigteil-Technik

Concrete Plant + Precast Technology Betonwerk + Fertigteil-Technik

Concrete Plant + Precast Technology Betonwerk + Fertigteil-Technik

MEHR ANZEIGEN
WENIGER ANZEIGEN

Erfolgreiche ePaper selbst erstellen

Machen Sie aus Ihren PDF Publikationen ein blätterbares Flipbook mit unserer einzigartigen Google optimierten e-Paper Software.

Produktion<br />

1<br />

the manhole element design. For this purpose, the<br />

complex control unit transfers the required data to the<br />

saw used. At each saw, the plant operator sees on a<br />

touchscreen which drain element has to be cut from<br />

which basic element type, and the manhole base section<br />

position number to which this individual piece is<br />

to be allocated. A table is used to join the prefabricated<br />

individual pieces and to bond them together using a<br />

glue gun.<br />

This working table has a circle drawn on its surface<br />

that is equivalent to the inside diameter of the base section,<br />

together with a gon scale so that the manufacturing<br />

of the positions of the individual inlets and outlets<br />

can be visually inspected. To check the drain layout, a<br />

laser system has been installed above the table that<br />

projects the center axes of the drains onto the table.<br />

This is just another possibility to monitor the position<br />

of the drains.<br />

In addition, these negative forms are fitted with the<br />

connecting elements, which, in turn, are fitted with appropriate<br />

rubber seals if required. As a result, the final<br />

form can be adapted to any type of connecting pipe<br />

(stoneware, concrete etc.). Each blockout element manufactured<br />

in this process is given the position number<br />

of the relevant manhole, and subsequently kept on<br />

stock in an interim storage area.<br />

Formwork preparation<br />

At the Teising production facility, about 100 steel forms<br />

are available, which are prepared to accommodate the<br />

production of one day (one-shift operation), filled with<br />

concrete and stored for curing. The formwork is<br />

removed from the elements after a storage period of 24<br />

hours, i.e. on the day following production. In theory,<br />

the form could also be removed after about seven or<br />

eight hours, which would enable two-shift operation.<br />

The steel formwork of a manhole base section consists<br />

of two spherical shells mounted on a formwork<br />

platform. The manhole is produced in a position turned<br />

by 180 degrees compared to final assembly, i.e. upsidedown.<br />

The inner core is designed as an expanding element,<br />

and a rubber liner is applied to it in order to<br />

achieve an even better surface quality.<br />

The inner core of the form is cone-shaped, and the<br />

blockout element is cut to size obliquely at the surface<br />

of the final manhole element. This ensures the required<br />

inclination of the base section. The prefabricated blockout<br />

element is mounted on top of the inner core and<br />

held in place by centering pieces.<br />

The joints between the blockout element and the<br />

steel form are also masked off in order to avoid the occurrence<br />

of any unwanted edge during the following<br />

process steps. This would not necessarily be required<br />

but has become a routine procedure at Haba Beton for<br />

quality reasons.<br />

When preparing the formwork, a touchscreen<br />

makes the system easy to control for the operator: The<br />

relevant base section is shown as scheduled in the production<br />

sequence so that any possibility of confusion is<br />

excluded. This step provides an additional opportunity<br />

Fig. 6 Joining the negative form for the drains.<br />

Abb. 6 Zusammensetzen der Gerinne-Negativform.<br />

zur Verfügung; diese werden jeweils in einer Tagesproduktion<br />

(einschichtiger Betrieb) für die Produktion<br />

vorbereitet, dann befüllt und zum Aushärten eingelagert.<br />

Das Entschalen der Elemente erfolgt nach<br />

24 Stunden Lagerung, also am Folgetag. Theoretisch<br />

wäre das Entschalen nach etwa sieben bis acht Stunden<br />

möglich und somit auch ein Zweischichtbetrieb umsetzbar.<br />

Die Stahlschalung eines Schachtunterteils besteht<br />

aus zwei Halbschalen auf einer Schalplattform, die<br />

Fertigung des Schachtes erfolgt um 180° gedreht gegenüber<br />

dem späteren Einbau – also auf dem Kopf. Der<br />

Innenkern der Schalung ist als Spreizschalung ausgeführt<br />

und wird mit einem Gummiüberzug versehen.<br />

Hiermit wird eine noch bessere Oberflächenqualität<br />

geschaffen.<br />

Der Innenkern der Schalung ist dabei kegelförmig<br />

ausgebildet und der Aussparungskörper wird an der<br />

späteren Oberfläche entsprechend schräg zugeschnitten.<br />

So wird das erforderliche Gefälle des Schachtunterteils<br />

hergestellt. Der entsprechend vorbereitete<br />

Aussparungskörper wird auf den Innenkern aufgesetzt,<br />

über Zentrierungen wird er in der richtigen Lage<br />

gehalten.<br />

Die Fugen zwischen dem Aussparungskörper und<br />

der Stahlschalung werden dann zusätzlich abgeklebt,<br />

damit später auch der geringste Grat vermieden wird.<br />

Dies ist nicht zwingend erforderlich, wird bei Haba Beton<br />

aus Qualitätsgründen aber so ausgeführt.<br />

Auch bei der Schalungsvorbereitung ermöglicht<br />

ein Touchscreen dem Mitarbeiter eine einfache Bedie-<br />

5

Hurra! Ihre Datei wurde hochgeladen und ist bereit für die Veröffentlichung.

Erfolgreich gespeichert!

Leider ist etwas schief gelaufen!