04.09.2017 Aufrufe

atw 2017-09

Erfolgreiche ePaper selbst erstellen

Machen Sie aus Ihren PDF Publikationen ein blätterbares Flipbook mit unserer einzigartigen Google optimierten e-Paper Software.

<strong>atw</strong> Vol. 62 (<strong>2017</strong>) | Issue 8/9 ı August/September<br />

were suspended in 1990. Similar plans to recommence<br />

­construction have been in development but are less<br />

­advanced.<br />

2016 saw ten units grid connected and three units<br />

closed down (Figure 11). This was the second year that<br />

ten reactors were connected to the grid, a number of grid<br />

­connections not seen since 1990. Reactor connections<br />

­remain lower than their mid-1980s peak, when more than<br />

30 reactors were connected to the grid each year.<br />

Five of the ten reactors connected to the grid in 2016<br />

were constructed in China, with one reactor grid ­connected<br />

in India, South Korea, Pakistan, Russia and USA. Watts Bar<br />

2 first started construction in 1973, but this was suspended<br />

in 1985, before restarting in 2007.<br />

The best performance for construction times for those<br />

reactors grid connected in 2016 are all associated with<br />

China (Figure 12). Five of the six reactors built in the<br />

shortest time were built in China, and the sixth, ­Chashma 3,<br />

is a Chinese-designed reactor, constructed in Pakistan.<br />

The construction time listed for Watts Bar 2 is based on<br />

the restart date for construction, in October 2007.<br />

The median construction time for reactors grid<br />

­connected in 2016 was 73.88 months, higher than for<br />

the five year average in the preceding five years, but little<br />

changed from 2015 (Figure 13). Construction times have<br />

remained below the levels seen prior to 2000.<br />

Conclusions<br />

The global nuclear fleet continued high levels of<br />

­performance in 2016, with an average capacity factor<br />

of 80.5%. The industry has maintained high capacity<br />

­factors of around 80% for the last 20 years, a substantial<br />

increase on capacity factors of around 50% achieved in<br />

the 1970s. Higher capacity factors have been achieved.<br />

In recent years, US reactors have regularly achieved<br />

an ­average capacity factor of around 90 %. However,<br />

­increasing requirements in some countries for nuclear<br />

generation to operate to compensate for intermittent<br />

­renewable generation means that in those countries<br />

­capacity factors will likely be lower despite similarly high<br />

levels of availability.<br />

With ten reactors coming online in each the last two<br />

years the number of reactors being connected to the grid<br />

has been higher than any year since 1990. However, the<br />

number of construction starts has dropped significantly<br />

since 2010, so maintaining this rate of grid connections in<br />

the coming years will be challenging.<br />

The pace of new build will need to accelerate if nuclear<br />

energy is going to make a growing contribution to the<br />

­global electricity generation mix, a requirement of many<br />

projections of future scenarios that aim to meet the<br />

­objective of limiting the rise average temperatures to<br />

­below two degrees Celsius, while at the same time meeting<br />

the growing worldwide demand for electricity.<br />

The global nuclear industry has its own Harmony goal,<br />

setting out the contribution nuclear energy could make to<br />

a sustainable low carbon electricity generation mix. The<br />

Harmony goal is supply 25 % of the world’s electricity by<br />

2050. To achieve this goal it is proposed there should be<br />

1,000 GWe of new nuclear build by 2050, as part of a<br />

­global drive to reduce dependence on polluting fossil fuel<br />

generation while meeting global development needs.<br />

To achieve this aim will require a ramping up of nuclear<br />

construction. About 10 GWe of nuclear capacity needs to<br />

be grid connected each year until 2020. This would require<br />

maintaining the levels of grid connections achieved in<br />

2015 and 2016. An average 25 GWe then needs to be<br />

| | Fig. 11.<br />

Reactor grid connection and shutdown 1980 to 2016.<br />

| | Fig. 12.<br />

Construction times of new unit connected to grid in 2016.<br />

| | Fig. 13.<br />

Median construction times for reactors since 1981 (months).<br />

| | Fig. 14.<br />

Historic construction rates and future requirements for the harmony target.<br />

­connected each year from 2021 to 2025, and an average<br />

33 GWe from 2026 to 2050 (Figure 14).<br />

This is a practical and achievable target, with build<br />

rates similar to those achieved in the mid-1980s. But to<br />

achieve it will require action on three key areas: ­addressing<br />

market failures; building harmonized regulation; and<br />

­creating an effective safety paradigm.<br />

There is not a level playing field in many electricity<br />

­markets. The true cost of air pollution, including carbon<br />

ENERGY POLICY, ECONOMY AND LAW 519<br />

Energy Policy, Economy and Law<br />

World Nuclear Performance Report <strong>2017</strong> ı Jonathan Cobb

Hurra! Ihre Datei wurde hochgeladen und ist bereit für die Veröffentlichung.

Erfolgreich gespeichert!

Leider ist etwas schief gelaufen!