Erfolgreiche ePaper selbst erstellen
Machen Sie aus Ihren PDF Publikationen ein blätterbares Flipbook mit unserer einzigartigen Google optimierten e-Paper Software.
<strong>atw</strong> Vol. 62 (<strong>2017</strong>) | Issue 8/9 ı August/September<br />
were suspended in 1990. Similar plans to recommence<br />
construction have been in development but are less<br />
advanced.<br />
2016 saw ten units grid connected and three units<br />
closed down (Figure 11). This was the second year that<br />
ten reactors were connected to the grid, a number of grid<br />
connections not seen since 1990. Reactor connections<br />
remain lower than their mid-1980s peak, when more than<br />
30 reactors were connected to the grid each year.<br />
Five of the ten reactors connected to the grid in 2016<br />
were constructed in China, with one reactor grid connected<br />
in India, South Korea, Pakistan, Russia and USA. Watts Bar<br />
2 first started construction in 1973, but this was suspended<br />
in 1985, before restarting in 2007.<br />
The best performance for construction times for those<br />
reactors grid connected in 2016 are all associated with<br />
China (Figure 12). Five of the six reactors built in the<br />
shortest time were built in China, and the sixth, Chashma 3,<br />
is a Chinese-designed reactor, constructed in Pakistan.<br />
The construction time listed for Watts Bar 2 is based on<br />
the restart date for construction, in October 2007.<br />
The median construction time for reactors grid<br />
connected in 2016 was 73.88 months, higher than for<br />
the five year average in the preceding five years, but little<br />
changed from 2015 (Figure 13). Construction times have<br />
remained below the levels seen prior to 2000.<br />
Conclusions<br />
The global nuclear fleet continued high levels of<br />
performance in 2016, with an average capacity factor<br />
of 80.5%. The industry has maintained high capacity<br />
factors of around 80% for the last 20 years, a substantial<br />
increase on capacity factors of around 50% achieved in<br />
the 1970s. Higher capacity factors have been achieved.<br />
In recent years, US reactors have regularly achieved<br />
an average capacity factor of around 90 %. However,<br />
increasing requirements in some countries for nuclear<br />
generation to operate to compensate for intermittent<br />
renewable generation means that in those countries<br />
capacity factors will likely be lower despite similarly high<br />
levels of availability.<br />
With ten reactors coming online in each the last two<br />
years the number of reactors being connected to the grid<br />
has been higher than any year since 1990. However, the<br />
number of construction starts has dropped significantly<br />
since 2010, so maintaining this rate of grid connections in<br />
the coming years will be challenging.<br />
The pace of new build will need to accelerate if nuclear<br />
energy is going to make a growing contribution to the<br />
global electricity generation mix, a requirement of many<br />
projections of future scenarios that aim to meet the<br />
objective of limiting the rise average temperatures to<br />
below two degrees Celsius, while at the same time meeting<br />
the growing worldwide demand for electricity.<br />
The global nuclear industry has its own Harmony goal,<br />
setting out the contribution nuclear energy could make to<br />
a sustainable low carbon electricity generation mix. The<br />
Harmony goal is supply 25 % of the world’s electricity by<br />
2050. To achieve this goal it is proposed there should be<br />
1,000 GWe of new nuclear build by 2050, as part of a<br />
global drive to reduce dependence on polluting fossil fuel<br />
generation while meeting global development needs.<br />
To achieve this aim will require a ramping up of nuclear<br />
construction. About 10 GWe of nuclear capacity needs to<br />
be grid connected each year until 2020. This would require<br />
maintaining the levels of grid connections achieved in<br />
2015 and 2016. An average 25 GWe then needs to be<br />
| | Fig. 11.<br />
Reactor grid connection and shutdown 1980 to 2016.<br />
| | Fig. 12.<br />
Construction times of new unit connected to grid in 2016.<br />
| | Fig. 13.<br />
Median construction times for reactors since 1981 (months).<br />
| | Fig. 14.<br />
Historic construction rates and future requirements for the harmony target.<br />
connected each year from 2021 to 2025, and an average<br />
33 GWe from 2026 to 2050 (Figure 14).<br />
This is a practical and achievable target, with build<br />
rates similar to those achieved in the mid-1980s. But to<br />
achieve it will require action on three key areas: addressing<br />
market failures; building harmonized regulation; and<br />
creating an effective safety paradigm.<br />
There is not a level playing field in many electricity<br />
markets. The true cost of air pollution, including carbon<br />
ENERGY POLICY, ECONOMY AND LAW 519<br />
Energy Policy, Economy and Law<br />
World Nuclear Performance Report <strong>2017</strong> ı Jonathan Cobb