Surface condition<br />
Floor quality<br />
Description of the fixing<br />
rails and accessories<br />
Cubicle fixing<br />
Take the equipment from the civil<br />
<strong>engineering</strong> package of the switchboard<br />
packaging.<br />
Placing and adjusting on<br />
standard civil <strong>engineering</strong><br />
works<br />
Preparation<br />
Drill holes in the floor and the fixing rails.<br />
Tools<br />
Drill. Socket spanner n. 3.<br />
Placing the fixing rails<br />
Place and fix the rails to the floor using<br />
8 - 07897542EN indice: D0<br />
Floor finishing<br />
and cubicle fastening<br />
The floor surface must be level (no bumps) and such that a 2 meters rule placed on all surfaces<br />
and in every direction shows a clearance of no more than 5mm.<br />
For the rolling of mobile part extraction tools without degrading the floor, it must have a<br />
compression withstand u 33 Mpa.<br />
Standard civil <strong>engineering</strong>:<br />
- fixing rail A (length 2 m),<br />
- 4 expansion pins B,<br />
- 2 fastening shims C.<br />
the supplied expansion pins, screws and<br />
washers.<br />
Cut the last rail to the required length.<br />
Earthquake resistant civil <strong>engineering</strong>:<br />
- 2 fixing rails A (length 2 m),<br />
- 8 expansion pins B,<br />
- 4 fastening shims C.<br />