Cubicle coupling<br />
Cubicle configuration:<br />
- gas exhaust,<br />
- AD4, CL4-GL4, TT4, DI4, RD4.<br />
For more details, see drawing<br />
ref. 03833 04N0.<br />
Take out from bolts and screws bag:<br />
- nuts F and I,<br />
- bolts G and H,<br />
- washers L.<br />
Tools<br />
- 2 ratchet spanners n. 3 (A) with the<br />
relevant extension.<br />
<strong>Schneider</strong> <strong>Electric</strong><br />
Installation instructions<br />
- In order to put in place the 2 nd cubicle, operate as for the st cubicle.<br />
- Fasten the two units together (9 fixing points).<br />
- For access to the fixing points, see the chapter “Access to the interior of the cubicles”.<br />
07897542EN indice: D0 - 47