<strong>CIDCO</strong> OF MAHARASHTRA LTD<br />

C.A.No.01/<strong>CIDCO</strong>/SE(KHR)/EE(KHR-I)/2010–11 Pg. No. 385<br />

c) Small linear and incidental labour.<br />

d) The working up or hacking of concrete for the purpose of<br />

providing key to receive further plaster, finishing top surfaces to<br />

falls, roughening to suit other title finishes; finishing smooth and<br />

even with cement mortar (1:3) surfaces with neeru finish which<br />

are not to receive further finishes.<br />

e) All necessary centering and form work for plain and reinforced<br />

concrete.<br />

f) Work whether straight, or curved;<br />

g) Machine mixing of concrete of all RCC work especially controlled<br />

concrete, with weight batching facilities and use of vibrator for<br />

all reinforced and plain concrete work.<br />

h) Tests of materials/ingredients of controlled concrete work as per<br />

IS 456 (latest revision)<br />

i) Cube test for all concrete plain and reinforced at the discretion<br />

of Engineer, for controlled concrete, cube tests as prescribed in<br />

<strong>particular</strong> <strong>specifications</strong> for controlled concrete.<br />

j) Design of mix for controlled concrete work.<br />

k) Concreting the irregular pockets in foundation.<br />

l) Finishing of concrete ceiling and sides underside of beams, RCC<br />

pardis lintels, not in conjunctions with walls with cement plaster<br />

(1:3) not less than 6mm thick.