<strong>CIDCO</strong> OF MAHARASHTRA LTD<br />

C.A.No.01/<strong>CIDCO</strong>/SE(KHR)/EE(KHR-I)/2010–11 Pg. No. 387<br />

v) For exposed cement concrete (plain/reinforced) surfaces, only<br />

surface which are finally required to be maintained exposed as<br />

per Architectural drawings shall be measured and paid for.<br />

However, if one side of a concrete member is partly exposed and<br />

partly unexposed then the whole side will be treated as exposed.<br />

Rate quoted for this item shall be deemed to account for extra<br />

care required for making better shuttering for other unexposed<br />

concrete surfaces contiguous to surfaces required to be kept<br />

exposed.<br />

w) Groves shall be made as per drawing and design or as per<br />

Architect’s instructions in RCC member without any extra<br />

payment. No deduction will be made on concrete quantities for<br />

making such grooves. No extra payment shall also be made.<br />

x) Nothing extra shall be paid on any account for rounding off<br />

corners and ends of concrete members or for making throating<br />

or chamfering or edges where required unless otherwise<br />

specifically included as in item for RCC and shuttering work in<br />

the schedule.<br />

y) Starter column of 100mm in height shall be cast with 12mm<br />

(Maximum size) aggregate and 20% extra cement. No extra<br />

payment for casting of starter column will be made.<br />

z) The rate for PCC/RCC concrete work should also include cost of<br />

procurement and use of plasticizers as approved by Engineer,<br />

for achieving desired workability with w/c ratio and minimum<br />

cement content, slump etc., parameters specified in tender<br />

<strong>specifications</strong> of relevant items of <strong>works</strong> and taking into account<br />

of retardation of setting time if needed to avoid cold joints in<br />

superstructure elements.