<strong>CIDCO</strong> OF MAHARASHTRA LTD<br />

C.A.No.01/<strong>CIDCO</strong>/SE(KHR)/EE(KHR-I)/2010–11 Pg. No. 455<br />

5.0 MEASUREMENT LENGTH OF EXCAVATION<br />

The lengths of excavation for trenches will be measured from and<br />

clear of the settled width allowed for the excavation of trench from<br />

which it starts on which it come into contact and the centre of the<br />

pipe or masonry for which the trench has been excavated shall be<br />

considered as the centre of such trench.<br />

6.0 A GRIP TO BE CUT WHERE PIPE SOCKET OCCURS<br />

Wherever a pipe socket occurs a grip is to be cut in the bottom of the<br />

trench or concrete bed to a depth of atleast 75 mm below the bed of<br />

the pipe so that the pipe may have a fair bearing on its shaft and to<br />

rest upon its socket. Such grip shall be of sufficient size in every<br />

respect to admit the hand all around the socket in order to make the<br />

joint, and the grip shall be maintained clear until the joint has been<br />

passed by the Engineer.<br />

7.0 TRENCHES IN ROCKY GROUNDS<br />

The trenches for pipe drains, if in stony or rocky ground, are to be<br />

excavated all along to the full depth of 75 mm below the intended<br />

level of the bed of the pipes to be laid therein, and layer of soft<br />

clean earth 75 mm thick is to be deposited for the reception of the<br />

pipes and in case where a layer of the concrete and/or precast block<br />

is required to be placed below the pipe line, the bottom of the<br />

excavation shall not be higher at any point than the bottom of the<br />

concrete layer or block.<br />

Wherever excavation is done in rock, the excavated stuff shall be<br />

stacked separately for chiselled rock and blasted rock. The<br />

excavation shall be paid or stack measurement with deduction of<br />

40% for voids to be made from the stack measurement.