<strong>CIDCO</strong> OF MAHARASHTRA LTD<br />

C.A.No.01/<strong>CIDCO</strong>/SE(KHR)/EE(KHR-I)/2010–11 Pg. No. 514<br />

2. Cement Mortar<br />

All cement mortar to be used on this work shall be in<br />

proportion as specified and directed. The ingredient shall be<br />

measured dry, by means of properly made gauge boxes, on a<br />

covered platform and shall be thoroughly mixed dry before<br />

adding water to get the required consistency. Only such<br />

quantity of mortar shall be prepared at a time as can be used<br />

up immediately. Mortar, after it has begun to set, shall not be<br />

allowed to be raked up again, but shall be removed from the<br />

work site immediately. Cement mortar shall be used within<br />

30 minutes after if leaves the mixing board or mill.<br />

3. Workmanship<br />

All stone or brick masonry shall be thoroughly wetted and<br />

joints raked to a depth of 12mm and walls washed.<br />

f) Pointing to Brick Work<br />

The whole of the exposed faces of brick work, cut-stone work and<br />

stone-paving when described as to be pointed are to have the joint<br />

raked out to a depth of a 13mm and pointed with cement and sand<br />

(unless otherwise described) in the proportion of one of cement to<br />

one fine sand flush with the face of the work and out straight,<br />

parallel and of uniform width.