• A schedule of the work shall be submitted with the bid. The schedule<br />
shall be of sufficient detail that major work areas and work disciplines<br />
are described. The schedule will be based on work weeks for<br />
submittal purposes. Once the contract is awarded, actual dates can be<br />
applied so that contract progress may be monitored.<br />
• Contractor will be provided a copy of the home inspection report<br />
provide by Accu-Check Home Inspection and a copy of the Lead<br />
report provided by volkmar Consulting Services, LLC.<br />
Exterior Work Items<br />
• Remove and replace existing roof: Remove the existing asphalt<br />
shingle roof in its entirety and dispose offsite. Some roof sheathing is<br />
of suspect quality. For bid purposes, anticipate replacing roof<br />
sheathing equivalent to 3 ea. 4x8’ sheets of plywood. For estimating<br />
purposes, use 5/8” thickness sheathing, however, if it is found not to<br />
match existing sheathing thickness, existing sheathing shall govern.<br />
New rolled building felt is to be installed in accordance with<br />
specification R905 of the International Building Code. . A continuous<br />
ridge vent shall be installed when the roof is replaced. The existing<br />
roof is not cut to accept this system but will have to be done. Asphalt<br />
shingles shall comply with ASTM D225 or D3462 and shall be three<br />
tab attachment features and have a 25 year manufacturers’ warranty.<br />
Fastening shall be per the manufacturer’s recommendations or IBC<br />
provisions, whichever is more stringent. New plumbing boots are to<br />
be supplied and installed and properly tied in along with the new roof<br />
installation. Note that the present “caulking“around the chimney is<br />
cracked and flaking away. Remove the deteriorated portions of this<br />
asphalt material and apply a new asphaltic coating to achieve a<br />
watertight installation. Closed valley type of installation is acceptable.<br />
Work execution, starting with removal up until finishing shall be done<br />
in the shortest time possible. Portions of the roof left unprotected at a<br />
shifts’ end shall be protected by temporary canvases or other<br />
protective means to maintain the integrity of the home interior. Any<br />
flashing materials required shall be per the IBC code section R905.<br />
Total roof area is 19 sq. total vented roof cap is 30lf<br />
Cost to remove and replace existing roof $<br />
Unit cost of sheathing over 3 $<br />
1. The exterior sheathing, including the soffit and fascia are to be<br />
removed and replaced with vinyl siding. New sheathing is to be<br />
2