milestone up to a maximum of ten working days. A lump sum of $1000.00<br />
shall be deducted for each working day this work is not successfully<br />
completed after the 270 working day milestone up to a maximum of ten (10 )<br />
working days.<br />
3. Installation of T-1 communications systems.<br />
This item shall be completed 300 working days after authorization to<br />
begin work. Completion shall include installation of all communications<br />
components, testing, making the system operational, and completion of al l<br />
associated clean-up required by the contract specifications is completed .<br />
Installation will not be considered until the entire T-1 communications<br />
system successfully passes all communication tests as outlined in the<br />
General Notes. Upon successful completion of this work within the<br />
specified time frame the contractor shall be paid a lump sum of $1000.00<br />
per working day for each working day the work is completed prior to the<br />
300 working day milestone up to a maximum of ten (10) working days. A<br />
lump sum of $1000.00 shall be deducted for each working day the work is<br />
not completed after the 300 working day milestone up to a maximum of ten<br />
(10) working days.<br />
4. Installation of Closed Circuit Television (CCTV) system.<br />
This item shall be completed 330 working days after authorization to<br />
begin work. Completion of this item of work shall include the complete<br />
installation, testing, synchronization, and making operational a cmplete<br />
CCTV system. Also included is all associated clean-up required by the<br />
contract specifications. Upon successful completion of this work within<br />
the specified time frame, the contractor shall be paid a lump sum of<br />
$1000.00 per working day for each day the work is completed prior to the<br />
330 working day milestone up to a maximum of ten (10) working days. A<br />
lump sum of $1000.00 shall be deducted for each working day the work is<br />
not completed after the 330 working day milestone up to a maximum of ten<br />
(10) working days.<br />
5. Interconnect to Transtar<br />
This item shall be completed 360 working days after authorization to<br />
begin work. Completion shall include successful transmission of video,<br />
voice, and data between the satellite building and Transtar, and all<br />
associated clean-up required by the contract specifications. Upon<br />
successful completion of this work within the specified time frame the<br />
contractor shall be paid a lump sum of $1000.00 per working day for each<br />
working day the work is completed prior to the 360 working day milestone<br />
up to a maximum of ten (10) working days. A lump sum of $1000.00 shall<br />
be deducted for each working day the work is not completed after the 360<br />
working day milestone up to a maximum of ten (10) working days.<br />