Tracking No. 00.00.2010

Site Development and Site-Specific

Scope

• Schedule

– The site development schedule

is tied to first nuclear concrete,

usually the placement of the

Nuclear Island Basement

– The duration of site development is

dependent upon specific site conditions, but can be anticipated to

be approximately 24 months

• Major earthwork

– Development of excavation plan

– Site clearing and grubbing

– Site leveling and drainage

– Development of access roads

– Dewatering

– Nuclear Island excavation and backfill

– Foundation preparation for remaining power island block at-grade

structures