C. Accountant's Release<br />
Accountant's Release Letter will be required. The responsible accountant must verify the validity of<br />
the applicant’s financial statement. Use the form included on Page 14.<br />
D. Term of Financial Statements<br />
A Contractor's financial information is valid until the date shown is more than one year old.<br />
Statements will be held on file until the financial information is 18 months old. The <strong>District</strong> reserves<br />
the right to reject statements in which the financial information is more than six months old. All<br />
applicable portions of the form should be completed with schedules attached if the space provided<br />
does not suffice.<br />
PUBLIC WORKS REQUIREMENTS<br />
Contractors must have successfully completed at least two public works projects in the State of<br />
California within the past five (5) years. The public works rating will be determined by averaging the<br />
two largest of these construction contracts and adding 33% for inflation.<br />
For example - Project 1 contract value of $1,627,511 plus Project 2 contract value of $1,437,026<br />
equals an average contract value of $1,532,269. Take this value multiply by 1.33 (allowing for a<br />
growth factor) reaches the sum of $2,037,917. This figure is rounded to the nearest $100,000 for a<br />
rating of $2,000,000. This process only obtains the Public Works Rating and does not necessarily set<br />
the final rating.<br />
INSURANCE<br />
A minimum of $2,000,000 Combined Comprehensive Single Limit Liability Insurance for projects<br />
where the engineer’s estimate is at least $1,000,000 or $1,000,000 Combined Comprehensive Single<br />
Limit Liability for projects where the engineer’s estimate is less than $1,000,000 is required.<br />
A Certificate of Insurance must be issued to <strong>Orange</strong> <strong>Unified</strong> <strong>School</strong> <strong>District</strong> which states levels and<br />
dates of coverage.<br />
BONDABILITY<br />
The bonding surety is required to be an admitted surety in the State of California and on the United<br />
States Treasury’s Listing of Approved Sureties .<br />
The surety may be contacted to confirm willingness to bond to a particular limit. It is required that the<br />
<strong>contractor</strong> include a letter of bondability from the surety indicating its support levels.<br />
In the event that the <strong>contractor</strong> is unable to obtain a letter of bondability in the time prescribed by the<br />
<strong>District</strong>, the Contractor may be suspended from the qualified <strong>contractor</strong>s’ list and not be allowed to bid<br />
on <strong>District</strong> projects until proof of bondability is provided.<br />
________________________________________________________________________________________________<br />
ORANGE UNIFIED SCHOOL DISTRICT<br />
PREQUALIFICATION PACKAGE - Instructions<br />
(Rev. 02/09/09)<br />
Page iv