3.9.3 Delete Section 3.9.3 and replace with the following:<br />

Owner shall be notified not less than twenty-four (24) hours before any time that superintendent<br />

will not be present at the site for any reason except periodic illness. If the reason is due to<br />

illness, then Owner shall be notified at the beginning of that day. Owner shall be notified of the<br />

identity of the acting superintendent. In the event the superintendent is absent from the site<br />

and notice has not been provided nor has an acting superintendent been assigned to the Work,<br />

the Contractor is subject to being backcharged in the amount of $250 for each day.<br />

3.10.1 Delete Section 3.10.1 in its entirety and replace with following:<br />

The Contractor shall prepare and submit a Contractor's construction schedule for the Work in<br />

accordance with the procedures set forth in Specification Section 01.3216 - Critical Path<br />

Method Schedule and Phasing Plan.<br />

3.10.2 Delete the following from the fourth (and last) sentence of Section 3.10.2:<br />

“increase in Contract Sum or”.<br />

3.10.4 Add new Section 3.10.4 as follows:<br />

The Contractor shall recommend to the Owner and to the Architect a schedule for procurement<br />

of long-lead time items which will constitute part of the Work as required to meet the Project<br />

schedule. If such long-lead time items are procured by the Owner, they shall be procured on<br />

terms and conditions as recommended by the Contractor. Upon the Owner=s acceptance of<br />

the Contractor=s Stipulated Sum Proposal, all contracts previously entered into by Owner shall<br />

be assigned by Owner to the Contractor who shall accept responsibility for such contracts as if<br />

it had initially entered into such contracts. Contractor shall expedite the delivery of long-lead<br />

time items. The Contractor shall receive and protect all Owner supplied material.<br />

3.11.1 Add new Section 3.11.1 as follows:<br />

Contractor shall at all times maintain job records, including, but not limited to, invoices, payment<br />

records, payroll records, daily reports, logs, diaries, and job meeting minutes, applicable to the<br />

Project. Contractor shall make such reports and records available to inspection by the Owner,<br />

Architect, or their respective agents, within five (5) working days of request by Owner, Architect,<br />

or their respective agents.<br />

3.12.11 Add new Section 3.12.11 as follows:<br />

The Architect’s review of Contractor’s submittals will be limited to one examination of an initial<br />

submittal and one (1) examination of a remittal. The Architect’s review of additional submittals<br />

will be made only with the consent of the Owner after notification by the Architect. The Owner<br />

shall be entitled to deduct from the Contract Sum amounts paid to the Architect for evaluation<br />

of such additional remittals.<br />

3.13 Add the following at the end of Section 3.13:<br />

The Contractor shall so conduct its operations as not to unreasonably interfere with traffic on<br />

public thoroughfares adjacent or near to the Project Site.<br />

3.15.1 Delete Section 3.15.1 in its entirety and replace with the following:<br />

The Contractor shall keep the premises and surrounding areas free from accumulation of waste<br />

materials or rubbish caused by operations under the Contract and shall, not less than two times<br />

each week, clean up by removing rubbish, including old and surplus materials. At completion<br />

of the work, the Contractor shall remove from and about the Project waste materials, rubbish,<br />

the Contractor=s tools, construction equipment, machinery and surplus materials, and shall<br />

clean, sweep, mop, brush and polish, as appropriate, the interior of the improvements or<br />

renovated areas, including but not limited to, any floors, carpeting, ducts, fixtures, and<br />

ventilation units operated during construction. Contractor shall clean exterior gutters, drainage,<br />

walkways, driveways and roofs of debris.<br />

Request for Proposals – CMAR Page 39 of 68 Rev 01/22/09<br />