Monday Tuesday Wednesday Thursday Friday Saturday Sunday

April 1 2 3 4 5 6 7

Maint.

deBoer, He, R2D2

8 9 10 11 12 13 14

deBoer, He, R2D2

Side Board

Washington

University, 1 week

plus setup, R2D2,

Ni beam?, July -

August

15 16 17 18 19 20 21

Maint.

JLV, H and He

Stech, He

22 23 24 25 26 27 28

Maint.

AMS, Zr

29 30 May 1 2 3 4 5

Maint.

Twinsol


NSL FN Tandem Schedule 2013

Monday Tuesday Wednesday Thursday Friday Saturday Sunday

May 6 7 8 9 10 11 12

Tank Opening to Fix leaky feedthrough

Side Board

Maint.

13 14 15 16 17 18 19

Fermi Lab Setup, WTR

Tank Opening to Fix leaky feedthrough

20 21 22 23 24 25 26

Maint.

Fermi Lab Tests, WTR, H

27 28 29 30 31 Jun 1 2

Maint.

CMU run, R2D2, H

Maint.

3 4 5 6 7 8 9