<strong>Northland</strong> in transition from Project to<br />
Operating Company - Operationally derisked<br />
Tapuli pit in<br />
operation<br />
<br />
• Tapuli pit already in operation<br />
• Simple and conventional mining and processing<br />
• Delivering ore tonnage according to mining plan<br />
Processing plant<br />
comissioned<br />
Logistics chain<br />
ramp-up<br />
according to plan<br />
<br />
<br />
• 1 st processing line commissioned according to operational plan<br />
• Approx. 200,000 dmt produced until end-April<br />
• Product quality in line with or exceeding operational targets<br />
• Production increase option identified for additional 600,000 dmtpa production<br />
• All elements of logistics chain tested and operating according to plan<br />
• Some temporary solutions in place, expected to be replaced by permanent<br />
solutions in <strong>2013</strong><br />
• Three shipments of approx. 54,000 wmt each successfully completed<br />
Permits in place<br />
<br />
• All permits in place for Tapuli pit, and both production lines 1 (excluding sulphide flotation) at<br />
Kaunisvaara plant<br />
• Sahavaara environmental permit expected H2 <strong>2013</strong> – required by end-2015<br />
1) Environmental and mining permits in place, but additional mining permit required for Tapuli South from 2017.<br />