<strong>SUNY</strong> <strong>Cobleskill</strong> Facilities Master Plan – Phase 5 Report<br />
November 2011<br />
2B PROVIDE NEW STUDENT & COMMUNITY CENTER<br />
Providing a new student activities building is the highest priority of the final<br />
FMP. The College currently lacks a student center of any kind and is in<br />
need of a space for students and faculty to congregate. The new Student<br />
& Community Center proposed by the FMP creates a natural center for the<br />
campus at the previous location of Beard Wellness Center and Brickyard<br />
Point, replacing the program of both demolished buildings and providing<br />
new space for other functions. While the Student & Community Center<br />
is proposed to be located on the east side of Route 7, it is positioned so<br />
as to be highly visible from both sides of the highway. A new pedestrian<br />
crossing at Route 7 is provided directly in line with the building, helping<br />
to unify the east and west sides of the campus.<br />
The Student & Community Center will require coordination with the<br />
College Crossing at Route 7 (4Ia and 4Ib), the reconfiguration of Albany<br />
Avenue (4X), as well as the Beard Wellness demolition. In particular<br />
the Beard Wellness Center cannot be vacated and demolished until the<br />
Wellness Center is relocated into its new home in the Student & Community<br />
Center.<br />