7. PROJECT PROCEDURES<br />
7.1 PLANNING & SCHEDULING<br />
The Establishment is using the primavera system for Scheduling planning<br />
and monitoring for all our projects and the procedure will be as follows:-<br />
7.1.1 An over all detail schedule will be done showing the zones<br />
(location) description of activity, date of early start finish: actual<br />
start actual finish manpower required for every activities material<br />
approval duration, duration of material supplying, the approval<br />
of drawing for that activity and the amount of retention for every<br />
activity. In a way than an estimated curve can be plotted with a<br />
cash flow.<br />
7.1.2 The monitoring will be on a monthly progress report. Showing<br />
the percentage of every activities had been done in plus or minus<br />
and the total percentage of activities finish at the end of each<br />
month and a plot of bar will be shown as follows:-<br />
* BAR as Schedule<br />
* BAR as Progress<br />
* BAR as Critical activities<br />
and (S) curve will be plotted, the current curve(Progress curved ) with the<br />
estimated curve and it will show the situation of the project.<br />
7.2 SAFETY PLAN<br />
The Establishment considers safety is the first and most important in the<br />
scope of construction that is why procedure of safety is a part of training<br />
program for our main power and senior staff on a monthly basis and to<br />
control the safety, at site the following procedures has to be followed.<br />
7.2.1 A Safety engineer will be provided at site with assistants to check<br />
all the field of construction and to issue thee safety requirements for<br />
all type of work as required.<br />
7.2.2 Safety shoes and helmets will be provided for all workers and will<br />
be charged on the worker who will not implement the requirement<br />
of safety.<br />
7.2.3 Safety warning sign will be provided all over the site with all flags<br />
warning tape warning lights and warning traffic cones etc.<br />