Historical Courthouse RenovationProject DescriptionInterior remodel of the 2 nd through5 th floor. Remodeled space willhouse LCSO administrative and civilcase staff membersCurrent Status• Current approved project budget$1,472,525.50• Stakeholders are reviewingdrawings


Facilities Update October 2012Projects Nearing Construction


Transportation HeadquartersProject DescriptionInterior and restroom renovation toFruitland Park facility previously usedas FHP office.Current Status• GMP draft in review


Animal Services BuildingRenovationProject DescriptionProject provides for the expansion ofexisting Animal Control Facility.Improvements include expandedparking, kennel area, and kennelsupport spaces.Current Status• Awaiting Bond and InsuranceDocumentation from ConstructionManager• Notice to Proceed issued shortlythereafter


Facilities Update October 2012Projects in Construction


Combined Fleet OperationsCenterProject DescriptionCreating of a consolidated FleetBuilding. Improvements includefully enclosing building, adding firesprinklers, ventilation, and electricalimprovementsCurrent Status• Construction underway


Project Summary• Projects are within their approved budget• Per the scheduling set forth within the projectdocuments these projects are current and ontime


Facilities Update October 2012PresentationCPPI ConstructionEmergency Communication &Operations Center Update


Lake County Emergency Communications &Operations CenterConstruction UpdateOctober 9, 2012Notice to Proceed - March 12, 2012


Lake County Emergency Communications & Operations CenterConstruction Update – October 9, 2012Lake County EOCSchedule Milestones• Permanent Power to EOC – October 2012• HVAC Start Up – November 2012• Substantial Completion – January 2013


Lake County Emergency Communications & Operations Center◦ Construction Update – October 9, 2012Site Aerial – September 4, 2012


Lake County Emergency Communications & Operations Center◦ Construction Update – October 9, 2012Exterior Elevations


Lake County Emergency Communications & Operations Center◦ Construction Update – October 9, 2012911 Call Center Progress


Lake County Emergency Communications & Operations Center◦ Construction Update – October 9, 2012Second Floor Classroom


Lake County Emergency Communications & Operations Center◦ Construction Update – October 9, 2012Electrical & Mechanical Rooms


Lake County Emergency Communications & Operations Center◦ Construction Update – October 9, 2012Sanitary Storage Tank Installed


Lake County Emergency Communications & Operations Center◦ Construction Update – October 9, 2012Generator & Fuel Tank Installed


Lake County Emergency Communications &Operations CenterCompletion: January of 2013


Facilities Update October 2012PresentationCPPI ConstructionJudicial Center Update


Lake County Judicial Center Expansion-Phase 2Construction UpdateOctober 9, 2012Judicial Center - Phase IIConstruction Started July, 2010


Lake County Judicial Center Expansion-Phase 2Construction Update – October 9, 2012Lake County Judicial Center - Phase 2Schedule Milestones• Permanent Power to Building – January 2012• HVAC Start Up – April 2012• Substantial Completion Main Building – November 15, 2012• Round-a-bout Timeframe – December 1, 2012• Substantial Completion Area C – July 2013


Lake County Judicial Center Expansion-Phase 2Construction Update – October 9, 2012Site Plan


Lake County Judicial Center Expansion-Phase 2Construction Update – October 9, 2012Site Aerial – September 4, 2012


Lake County Judicial Center Expansion-Phase 2Construction Update – October 9, 2012Southwest Elevation


Lake County Judicial Center Expansion-Phase 2Construction Update – October 9, 2012Southeast Elevation


Lake County Judicial Center Expansion-Phase 2Construction Update – October 9, 2012Round-About Progress


Lake County Judicial Center Expansion-Phase 2Construction Update – October 9, 2012Jury Assembly


Lake County Judicial Center Expansion-Phase 2Construction Update – October 9, 2012Atrium Progress


Lake County Judicial Center Expansion-Phase 2Construction Update – October 9, 20125 th Floor Corridor


Lake County Judicial Center Expansion-Phase 2Construction Update – October 9, 2012Judges Chambers


Lake County Judicial Center Expansion-Phase 2Construction Update – October 9, 20124 th Floor Corridor


Lake County Judicial Center Expansion-Phase 2Construction Update – October 9, 2012Secure Holding


Lake County Judicial Center Expansion-Phase 2


Thank you.