GeneralGlossaryNote: this document is available for all the<strong>MCset</strong> 1-2-3 units ordered from the 1st ofMarch 2006.UFADCL-GLTTRHBRHCMTPDITTTCVPISLVMVSMALTFunctionnal Unit (cubicle + mobile part + Sepam)Incomming / outgoing cubicleWithdrawable line coupling cubicleMeasurement and busbar earthing cubicleBus riser cubicle through the topCable riser cubicle through the toptransition panel between an <strong>MCset</strong> cubicle and a MOTORPACT cubicleFuse switch outgoing cubicleVoltage transformerCurrent transformer or current sensorVoltage Presence Indicating SystemLow voltageVoltage class, including levels 7.2 - 12 and 17.5 kVEarthing switchMobile partLFRollarc 400EVOLISCTV1ERTExtraction tableWithdrawable circuit-breaker with SF6 breaking which is used inAD and CL cubiclesSF6 breaking withdrawable contactor equipping the AD1 cubicleWithdrawable circuit-breaker with vacuum breaking which is usedin AD and CL cubiclesVacuum breaking withdrawable contactor equipping the AD1cubicleRack-in or rack-out and removal tool of the mobile parts on thegroundExtraction or insertion table without the removal tool of the mobileparts on the groundSymbolsSMALT operationPlug-in prevention position.Locking possible.Plug-in or withdrawal position.Operation position.Open earthing switch mechanical indicatorlight.07897302EN indice : C0


GeneralClosed earthing switch mechanical indicatorlight.Position can be locked using paslocks.Mobile part operationOperation position.“Plugged-in” position.“Withdrawn” position.Insertion / extraction position.RecommendationsHeight (H) of ceiling forinstallation of an anti-arc or IPX1tunnelInstallation above theswitchboardMarkingIt is necessary to have a height of ceiling H u 2.80 m to install a tunnel.All type of equipment installation such as lamp or light are forbidden.It is compulsory forbidden to walk on theparts bearing this marking.It is compulsory forbidden to removethe parts bearing this marking when theequipment is energised.Standard tighteningtorques(non greased screws and bolts)07897302EN indice : C0Screw Torque in NmØ 6 13Ø 8 28Ø 10 50Ø 12 75Ø 14 120Application methods:The elastic washers placed on the externalsides of the pads and busbars ensure betterdistribution of stress regarding screwstightened to the recommended torques.


General descriptionWarning for readersAs the <strong>MCset</strong> range is very extensive and presents a vast number of front panel options, wehave decided to present a Functional Unit presentation equipped with the maximum switchgear.AD cubicleAD1 630/1250 AAD2 630/1250 AAD3 2500/3150/3600/4000 AIncomer/outgoerwithout VT or with fixed VTIncomer/outgoer withwithdrawable VT fusesA: LV compartment doorB: protection, monitoring, control by SepamC: compartment door mobile partD: position inspection windowsof the mobile partE: operation and locking plateof the mobile partF: voltage indicatorsG: earthing switch operation and lockingplate and padlocking of the mobile partH: access panel to connectioncompartment of MV cablesor withdrawable VT fusesJ: visualisation windows of cables orof VT fuse positionK: operation and padlocking plate ofwithdrawable VT fusesL: fan compartment (on 3600 A / 4000 A)M: cable compartment (on 3600 A / 4000 A)07897302EN indice : C0


General descriptionTT1, TT2 cubiclesA: LV compartment doorB: protection, monitoring, control by SepamD: visualisation windowsF: voltage indicatorsG: earthing switch operation and lockingplate and padlocking of the mobile partH: access panel to connectioncompartment of MV cablesor withdrawable VT fusesJ: visualisation windows of cables orof VT fuse positionK: operation and padlocking plate ofwithdrawable VT fusesL: compartment door fixed busbar bridge.Voltage transformers with withdrawablefusesVoltage transformers without VT or withfixed VTCL-GL cubiclesCircuit-breakercoupling cubicleBus riser cubicleWith upstream anddownstream VT withwithdrawable fusesA: LV compartment doorB: protection, monitoring, control by SepamC: compartment door mobile partD: position inspection windowsof the mobile partE: operation and locking plateof the mobile partF: voltage indicatorsG: earthing switch operation and lockingplate and padlocking of the mobile partJ: visualisation windows of cables orof VT fuse positionL: access panel to withdrawable VT fusesand to the lower busbar compartmentsM : operation and padlocking plate ofwithdrawable VT fusesN : compartment door fixed busbar bridgeP : fan compartment (on 3600 A / 4000 A)07897302EN indice : C0


General descriptionRHB, RHC cubiclesRHB1, RHC1 630/1250 ARHB2, RHC2 630/1250 ARHB3, 2500/3150/3600/4000 ARHC3, 2500/3150 AA: LV compartment doorB: protection, monitoring, control by SepamC: compartment door mobile partD: position inspection windowsof the mobile partE: operation and locking plateof the mobile partF: voltage indicatorsG: earthing switch operation and lockingplate and padlocking of the mobile partH : acces panel to the busbars or to thewithdrawable VT fusesJ : visualisation windows of cables orof VT fuse positionK : operation and padlocking plate ofwithdrawable VT fusesL : connection through the top usingbusbars (RHB) or cables (RHC)M : fan compartment (on 3600 A / 4000 A)Withdrawable mobile partLF107897302EN indice : C0


General descriptionLF2LF3Disconnector carriageNote: available in 3 widths.Busbar earthing carriage oncircuit-breaker baseNote: option available in 3 widths.07897302EN indice : C0


General descriptionROLLARC 400CTV1EvolisNote: available in 3 widths.Busbar earthing carriage onEvolis baseNote: available in 3 widths.07897302EN indice : C0


General descriptionIdentificationEx : AD functional unitA: name of the cubicleB: manufacturer’s labelC: characteristics, designations and serialnumber.LF withdrawable mobile partD: characteristics, designations and serialnumber.Rollarc or CTV1 withdrawable mobile partE: characteristics, designations and serialnumber.Evolis withdrawable mobile partF: characteristics, designations and serialnumberG: location of operating instructions(behind the cover).Read the inscriptions onthe front panelA: procedure pictogramB: withdrawable mobile partC: earthing switch plateD: withdrawable fuse voltage transformerplate.07897302EN indice : C0


General descriptionProcedure pictogram1: mobile part operation2: earthing switch operation.Mobile <strong>part1</strong>: mechanical opening push-button2: mobile part position selector3: opening for inserting mobile partoperating handleE: mechanical indicator light for indicationof the mobile part positionF: location for disconnector carriage lock(optional).CubicleEarthing switch, voltage presence andplug-in prevention4 : earthing switch position selector5 : opening for the insertion of the earthingswitch operating handleG : voltage presenceH : plug-in prevention selector switchL : mechanical indicator of earthing switchstatusM : location for plug-in prevention lockN : location for earthing switch locks.Withdrawable voltagetransformer6 : position selector switch for voltagetransformer withdrawable fuses7 : opening for the insertion of the voltagetransformer withdrawable fuse operatinghandle.10 07897302EN indice : C0


Instructions for accessto the inside of a cubicleRemoving front protectioncover platesCubicle with or without fixedvoltage transformer (VT)Close earthing switch (see chapter “Closingthe earthing switch”).It is recommended to padlock it in thisposition (see chapter “Padlocking andpreventing access using padlocks”).In the case of a cubicle equipped with afixed VT.Open the protection switch of the VTsecondaries which is located in theregrouping sleeve or in the LV compartment.ClosureTo place back into operation, carry outoperations in the reverse order of removal(closed earthing switch).Dismantle the panel (10 screws).Cubicle equipped with awithdrawable fusevoltagetransformerWithdraw VT fuses (see chapter“Withdrawing VT fuses”).Close earthing switch (see chapter “Closingthe earthing switch”).It is recommended to padlock it in thisposition (see chapter “Padlocking andpreventing access with padlocks”).12 07897302EN indice : C0


Instructions for accessto the inside of a cubicleRemoving the manholesheetOn a cubicle equipped with VTs, removethem.Remove the screws and remove manholesheet.Access to the connection compartment ofMV cables is possible via the maintenancespace at the cubicle manhole level.Likewise, it is possible to access themaintenance space or duct through theinside of the cubicle.See chapter “Instructions for access tothe inside of a cubicle”.ClosureTo place back into operation, carry out operations in the reverse order of removal.Removing and insertingfixed or withdrawable VTsFixed VTsOn each VT, disconnect the connection rod,by unscrewing the nut, then removing thedeflector, and raising the connection rod.Similar operation whatever typeof VTDisconnect the VT low voltage connector.Remove the VTs using the handle.Closing the MV connectioncompartmentTo place back into operation, carry outoperations in the reverse order of removal.For fixed VTsTightening torque on VT: 30 Nm.14 07897302EN indice : C0


Instructions for accessto the inside of a cubicleDuring the first VT insertion, cutand remove the connector immobilisationbinding.Connect the VT low voltage connector.Access to lowercompartment (cables, CT,earthing switch, surgearresters)Safety rulesAll operations described hereaftermust be carried out in compliance withthe safety standards in force, under theresponsibility of a competent person.Access to the MV cable connectioncompartement is possible through themaintenance space by removing the cubiclemanhole sheet (see chapter “Removing themanhole sheet”).Accessing busbarsSafety rulesAll operations described hereafter must be carried out in compliance with the safetystandards in force, under the responsibility of a competent person.UpperFor access to busbars, see chapter “Instructions for access to the inside of the cubicle”.LowerAccess to lower busbars is possible through the maintenance space by removing the cubiclemanhole sheet.See chapter “Instructions for access to the inside of the cubicle”.07897302EN indice : C015


Instructions for accessto the inside of a cubicleAccessing plug-in pinsSafety rulesAll operations described hereafter must be carried out in compliance with the safetystandards in force, under the responsibility of a competent person.Opening and closing lower flapsUsing a screwdriver, raise the vane torelease the locking.Push the ball into the link axis.The flaps fall downwards up to locking.To close, pull the flaps upwards up tolocking.Opening and closing upper flapsUsing a screwdriver, raise the vane torelease the locking.Push the ball into the link axis.Push the flaps upwards up to locking.To close, pull the flaps downwards up tolocking.Before re-plugging in the mobile part, ensure that the shutters mechanisms haveBefore re-plugging in the mobile part, ensure that the shutters mechanisms havebeen put back into their initial position (locked closed). Failure to comply with this instructionmay result in damage to the equipment.16 07897302EN indice : C0


Installation and operationrecommendationthe switchgear’s resistanceto ageing in an MVsubstation depends on 3main factors:The necessity of correct implementationof connections:New cold retractable or slip-on technologyoffers ease of installation that favoursresistance over time.Their design allows them to used in pollutedenvironments with harsh climatic conditions.Impact of the relative humidity factor:Installing a heating device is essential inclimates with high relative humidity levelsand major temperature differences.Ensure that draughts and / or thermal shocksare avoided in all cubicle compartments inorder to avoid the creation of dew points(sources of partial discharges).The equipment must be installed inconformity with the relevant IEC standard.Outside of these normal usage conditions,we recommend contacting <strong>Schneider</strong><strong>Electric</strong> to determine the operations tobe carried out as well as their frequencyaccording to the actual service conditions.Ventilation control:Grid size must be suited to the powerdissipated in the substation. These gridsmust be placed exclusively in the vicinityof the transformer, in order to avoid aircirculation on the LV switchboard.Operation and maintenanceIt is strongly advised to periodically carryout, (minimun every 2 years approximately),a few operation cycles on operatingdevices.Outside normal conditions of use,(between -5°C and 40°C , absence of dust,corrosive gas, etc.), it is recommended toexamine, with our <strong>Schneider</strong> <strong>Electric</strong>services centre, the steps to be taken, inorder to ensure correct functioning of theinstallation.After 6 to 12 month operations, werecommend you to check the busbars andMV cable connection tightening.It should be done with a calibrated torquespanner, adjust to lower torque compare tovalues indicated in page 4.If no problems are detected and if thebusbars and cable connections haven’t beenmodified, it will not necessary to do againthis check.In case of dismantling, the elastic washersmust be change and replace by new onessupplied by <strong>Schneider</strong> <strong>Electric</strong>.Our service centre is at your disposal atany time:- To undergo an installation diagnostic,- To offer you, if need be, suitablemaintenance operations,- To offer you maintenance contracts,- to offer you adaptations.Ab Version 3600 A / 4000 A:We strongly recommend that you cleanthe ventilation grids regularly (every 2years):A : standard gridsB : grids on RHB version.b A fan monitoring system must beinstalled with the cubicle control andmonitoring devices.Permanent operation of the followingmust be guaranteed:- 1 fan for version 3600 A- 2 fans for version 4000 A.A07897302EN indice : C017


Steps for the testsVoltage presence on MVcablesCubicle equipped with VPISvoltage indicator boxesVPIS : Voltage Presence Indicating System,a box with 3 integrated lamps.Characteristics:The definite “voltage presence” indication isensured on the voltage range stipulated byIEC 61958.Instruction for useVPIS must not be used as a VDS (VoltageDetecting Systems).The indication of a VPIS alone does notsuffice to ensure that the system is deenergised:if the operation rules require this, thensuitable voltage detectors in compliancewith IEC 61243 must be used for this.A: voltage presence indicator light(1 for each phase)B: connection points enabling a phaseconcordance unit to be connected.Once the cables are energised, the voltageindicator lights should light up.MV cable testsTest conditionOpen earthing switch.Cables connected to injection tools.Voltage injections on MV cableheadsOn outgoing cables(without VT)Check voltage absence.Voltage indicator lights are not lit.Close the earthing switch.See chapter “Closing the earthing switch”.18 07897302EN indice : C0


Steps for the testsRemove front protective cover plates.See chapter “Instructions for access tothe inside of a cubicle”.Connect the voltage injection circuit to cablelugs.Open the earthing switch. See chapter“Opening the earthing switch”, then carryout the tests.At the end of the tests:- Close the earthing switch- Remove the accessories.07897302EN indice : C019


Operating InstructionsExtracting or inserting themobile partStarting statusCubicle + mobile partin a disconnected /testposition.Note: the following operations are describedusing the extraction and insertion toolapplication and the removal of mobile ERTparts ......the operating mode is identical when usingthe extraction table.These tools can be adjusted in width andheight. See the corresponding <strong>manual</strong>s.ExtractionOpen the access door to the mobile part bypulling then turning the handle towards theright.Disconnect the LV auxiliary cord by pressingon the red button and by pulling the socketlock (circuit-breaker or contactor).Bring the ERT into position (the pinsentered into the holes intended for thispurpose on the cubicle).Lock the latching mechanism by pushing in,then tipping the 2 OED notching operatingmechanism handles to the right (checklatching mechanism).Block the 2 ERT castors.20 07897302EN indice : C0