Major Phosphoric Acid Incident - U.S. National Response Team (NRT)
Major Phosphoric Acid Incident - U.S. National Response Team (NRT)
Major Phosphoric Acid Incident - U.S. National Response Team (NRT)
- No tags were found...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Timeline of Events12 September 2007 (continued) EPA issued CERCLA Order to RP to preventstack failure – gave some leeway forcontrolled release GST pump load arrived & staged @ SectorHouston-Galveston Agrifos commenced controlled release intocounty ditch with one 10” and one 8” 8 line;pumping from top of stacks as well; notifiedneighboring facilities and waterway uses. UC made adjustments to IAP to deal w/TS