Purpose• To provide a current overviewof the various projects beingplanned or constructed• Discussion of ArchitecturalChange Order


Facilities Update December 2010Projects in Development


Facilities Update December 2010Projects in Nearing Construction


Animal Services BuildingRenovationProject DescriptionProject provides for the expansionof existing Animal Control Facility.Improvements include expandedparking, kennel area, and kennelsupport spaces.Current Status• Permitting Complete• On-Call Construction Managercurrently bidding project


Astor Substation RenovationProject DescriptionRemoval of water damage mobilehome portion of building. Repairingand renovating existing site builtstructureCurrent Status• GMP submitted to the County forreview


Combined Fleet OperationsCenterProject DescriptionCreating of a consolidated FleetBuilding. Improvements includefully enclosing building, adding firesprinklers, ventilation, and electricalimprovementsCurrent Status• Permitting Complete• On-Call Construction Managercurrently bidding project. GMPsubmitted to the County inDecember, 2011


Emergency Communications &Operations CenterProject DescriptionA joint use 911dispatch/communication center andEmergency Operations Center.Building approximately 27,000 SF.Current Status• On-Call Construction Managerbidding project.• Construction Manager currentlybidding project. GMP submitted tothe County in early February, 2012


#10 Astor Fire Station MoldRemediationProject DescriptionThis is a mold remediation projectentailing the removal and replacementof ceiling tiles, drywall ceiling,ductwork, and insulation as well asproviding modifications to the HVAC.Current Status• On-Call Construction Managersubmitted GMP to the County• Contract documents and BCC agendaitem being prepared


#112 Clermont Fire Station MoldRemediationProject DescriptionThis is a mold remediation projectentailing the removal and replacementof ceiling tiles, drywall ceiling,ductwork, and insulation as well asproviding modifications to the HVAC.Current Status• On-Call Construction Managersubmitted GMP to the County• Contract documents and BCC agendaitem being prepared


Radio Operations CenterProject DescriptionProviding interior build-out of currentlyowned building adjacent to theIndustrial Park. Building will house thePublic Safety Communications sectionstaff and will result in terminated leasespace.Current Status• On-Call Construction Managersubmitted GMP to the County• Contract documents and BCC agendaitem being prepared


Facilities Update December 2010Projects in Construction


Horticultural Learning CenterSolar Pilot ProjectProject DescriptionEECBG Project that consists of addingsolar blanket to the roof to providealternative energy sourceCurrent Status• Project currently under construction• Project scheduled for completion inJanuary 2012


Leesburg Health ClinicProject DescriptionInterior renovation due to mold inbuilding.Current Status• Project currently under construction• Project scheduled for completion midDecember 2011


Public Defender BuildingReroofProject DescriptionProvide new roof and roof insulation tothe building.Current Status• Project approved by BCC• Project anticipated to start in February2012


Road Operations CenterExpansionProject DescriptionAdding a 2,000 SF expansion to theexisting building (1,000 SF OfficeSpace & 1,000 SF Storage space)Current Status• Project approved by BCC• Notice to Proceed issued tocontractor. Completion date April,2012


Southlake Health Clinic BuildingProject DescriptionBuilding a building shell for new HealthDepartment in South Lake County.Current Status• Shell to be completed by end of December2011• Stakeholders coordinating interior buildout


Tourist Welcome CenterRenovationProject DescriptionRemolding existing Tourist WelcomeCenter Building to accommodate theaddition of the Business DevelopmentCenter.Current Status• Project is currently under construction• Change Order has been requested forneeded fire safety improvements. AfterChange Order review, BCC agenda itemwill be prepared.


Judicial Center ExpansionProject DescriptionBuilding a 168,000 SF expansion tothe existing Judicial CenterCurrent Status• Under construction. Completionscheduled for summer of 2012.• Update by PPI


Thank you.


Lake County Judicial Center Expansion-Phase 2Construction UpdateDecember 20, 2011Judicial Center - Phase IIConstruction Started July, 2010


Lake County Judicial Center Expansion-Phase 2Construction Update – December 20, 2011Lake County Judicial Center - Phase 2Schedule Milestones• Permanent Power to Building – January 2012• HVAC Start Up – February 2012• Substantial Completion Main Building – July 2012• Round-a-bout Timeframe – January 2012– June 2012• Substantial Completion Area C – March 2013


Lake County Judicial Center Expansion-Phase 2Construction Update – December 20, 2011Site Plan


Lake County Judicial Center Expansion-Phase 2Construction Update – December 20, 2011Site Aerial - December 1, 2011


Lake County Judicial Center Expansion-Phase 2Construction Update – December 20, 2011Southwest Elevation


Lake County Judicial Center Expansion-Phase 2Construction Update – December 20, 2011North Elevation


Lake County Judicial Center Expansion-Phase 2Construction Update – December 20, 2011Jury Assembly


Lake County Judicial Center Expansion-Phase 2Construction Update – December 20, 2011South Breezeway


Lake County Judicial Center Expansion-Phase 2Construction Update – December 20, 2011Public Counter Area


Lake County Judicial Center Expansion-Phase 2Construction Update – December 20, 20112nd Level –Clerk Area


Lake County Judicial Center Expansion-Phase 2Construction Update – December 20, 2011Courtroom 3-A00


Lake County Judicial Center Expansion-Phase 2Construction Update – December 20, 20115 th Level - Atrium


Lake County Judicial Center Expansion-Phase 2Construction Update – December 20, 2011Electrical Equipment


Lake County Judicial Center Expansion-Phase 2Construction Update – December 20, 2011Mechanical & Fire Pump Rooms


Lake County Judicial Center Expansion-Phase 2Phase 2 Start Move In: July of 2012