Lindenberg Emirates Company Profile
LE-PROFILE | ver.3 | rev.5.4 | 28-Mar-2012
LINDENBERG-EMIRATES LLC
Company Profile 3~16
� About Lindenberg Emirates 3
� Scope of Activities 4
� Completed Projects 5
� Ongoing Projects 6~7
� Representation of Lindenberg Anlagen 8
� Company Organization Chart 9
� Company Manpower Chart 10
� Company Reg., PQ & Classification 11~14
� Project References 15~16
Lindenberg Power Division 17~33
� Division Profile 17~18
� Scope of Activities 19
� Typical Power Project Organization Chart 20
� Featured Projects 21~32
� Power Stations 33
Lindenberg Water & Drainage Division 34~46
� Division Profile 34~35
� Scope of Activities 35
� Typical Water Project Organization Chart 36
� Featured Projects 37~46
Quality, Health & Safety & Environment 47~48
Company Recourses 49~57
� Workforce & Labour Camp 49
� Store Facilities 50
� Plant, Machinery, Vehicles & Equipments 51
Contact Information 52
3
About Lindenberg-Emirates
Located in the United Arab Emirates, with
its center of operation and main office in
Abu Dhabi, Lindenberg-Emirates LLC
specializes in Engineering, Procurement,
and Construction (EPC) mode of project
delivery.
Lindenberg-Emirates LLC employs manpower expertise in all aspects of contracting including civil
engineering, pipeline construction, turn-key industrial plants, substations, mechanical and electrical
installations, and services to the electromechanical industry including testing, commissioning,
maintenance and operational activities.
Company Details
� Date Established: 20.11.2001
� Ownership: UAE Partner 51%, Lindenberg Anlagen (Germany) 49%
� Incorporated in: Abu Dhabi, United Arab Emirates
� Principal Bankers: Arab Bank for Investment Foreign Trade Mashreqbank
National Bank of Abu Dhabi HSBC Bank
National Bank of Fujairah
4
Scope of Activities
Power Related Activities
� Construction & Installation of Power Transmission and Distribution Networks
� Installation of High Voltage Cables
� Substation Turnkey Low, Medium and High Voltage & Package Substation Installation
� High & Medium Voltage Switchgear & Transformer Installation
� Submarine Cable Installation
Civil & Electro-mechanical General Contracting
� Water Transmission & Distribution, Storm Water, Drainage & Irrigation Networks
� EPC Projects of Water & Sewerage including Pumping Stations
� Submarine Pipe Laying
Oil & Gas Related Activities
� On Shore and Off Shore Oil and Gas Field Services
� Maintenance Services for Oil/Gas Production Utilities
� Technical Maintenance for Equipment, Industrial and Petroleum Plant
Repair & Maintenance Works
� Repair and Maintenance of Pumping Stations, Sewerage Networks & Water Drainage Lines
5
Projects Successfully Completed in U.A.E. Project Value (AED)
� Power Supply for Presidential Palaces and Hospitals 177 Million
� Construction of Water Supply Network to Sadiyat Island 108 Million
� Power Supply for Presidential Palaces and Hospitals 103 Million
� Construction of Water Transmission Pipeline in Baniyas 94 Million
� Construction of Water Transmission Pipeline in Dubai 84 Million
� Water Transmission Lines inside Al Reem Island 56 Million
� Security & Upgrading of 11kV Electrical Networks 40 Million
� Supply of LV Panels Switchgear for Ruwais Housing Complex 29 Million
� Power Supply for Palaces and Hospitals Stage3 26 Million
� Construction of Water Transmission Line from Sweihan to Remah 26 Million
� Transfer of 11kV Load & Primary Substation in Abu Dhabi 19 Million
� Modification of Switching Stations in Abu Dhabi 17 Million
6
Ongoing Power & Civil Projects in Abu Dhabi, U.A.E. Project Value (AED)
� Replacement of 11 KV Switchgears and Substations 82 Million
� Transfer of Load to New 132/11 kV W24 and E01 Primary Substations 34 Million
� Civil Works for Shuweihat S3 Independent Power Plant 29 Million
� Supply and Installation of 11kV Package Unit Substation for Braka
Nuclear Power Plant
16.8 Million
� Transfer of 11kV Load to New 132/11kV W02 Primary Substation 13.6 Million
� Distribution Network Expansion for Farms & Ezabs Belonging to VIP
Customers in Eastern Region
� Installation of 22kV cables from 132/22 kVA - A Beach Primary to Masdar
City
13 Million
2 Million
7
Ongoing Water & Drainage Projects in Abu Dhabi, U.A.E. Project Value (AED)
� Water Transmission Scheme inside Sadiyat Island 577 Million
� Water Supply to ADCO & GASCO Facilities at Buhasa and Habshan 180 Million
� EPC for 2 Nos. 25 MiG Steel Tanks & associated Civil & Pipeline Works 174.5 Million
� Replacement of Existing Sewer Networks Inside Abu Dhabi Island 116 Million
� Construction of Sewerage Connections and Related Works in Abu Dhabi 80 Million
� Enhancement of Sector Main Loop for Sector E25 in Abu Dhabi City 7 Million
� Sheikh Khalifa Interchange, Water Pipeline Diversion 2.8 Million
8
Representation of Lindenberg Anlagen
Lindenberg Emirates represents Lindenberg Anlagen GmbH Germany for its products and services in
the United Arab Emirates.
Lindenberg Anlagen GmbH Germany is a world class leader in the design and manufacturing of Power
Generation System and has international presence in more than 72 countries.
For more information about Lindenberg Anlagen GmbH, please visit www.lindenberg-anlagen.de.
9
Company Organization Chart
FINANCE &
ACCOUNTS
DEPARTMENT
Treasury Manager
Accounts Manager
Sr. Accountants
Accountants
Secretary
IT DEPARTMENT
IT Administrator
and Team
FINANCE &
ACCOUNTS
DEPARTMENT
Finance
Director
BUSINESS
SYSTEM - ERP
DEPARTMENT
Business Systems
Analyst
RECRUITMENT
DEPARTMENT
Recruitment
Manager
Recruitment Assistant
DOCUMENTS
CONTROL
DEPARTMENT
Document Controller
PURCHASING
DEPARTMENT
Commercial
Manager
Procurement Engrs.
Asst. Proc. Engrs.
Purchase Officers
Secretary
HR / ADMIN
DEPARTMENT
HR/Admin
Manager
Sr. HR/Admin Officer
Personnel Officer
Asst. Personnel Off’r.
Sr. Administrator
PRO
Doc. Controller
Admin Clerk
Camp Boss
Asst. Camp Boss
ESTIMATION &
TENDERING
DEPARTMENT
Estimation
Manager
Senior Business
Associate
Sr. Estimation Engrs.
Estimation Engrs.
Secretary
PLANT /
WORKSHOP
DEPARTMENT
Plant Manager
W/S Superintendent
W/S Administrator
Foremen Mechanics
Mechanics
Storekeeper
PRO Plant
Office Asst.
CHAIRMAN
GENERAL
MANAGER
OPERATIONS
DEPARTMENT
Operations
Manager
POWER
DIVISION
Asst. Operations
Manager - LPD
Projects Manager
Construction Mngrs.
Design Engineers
Project Engineers
T&C Engineers
Sr. Qty Surveyor
Quantity Surveyor
Exec. Secretary
Proj. Support Team
Foremen
Work Crew
Exec. Secretary /
Doc. Controller
Office Manager
Exec. Sec. / D.C.
Admin Clerk
Senior Administrator
CONTRACTS
DEPARTMENT
Contracts
Manager
Secretary
WATER &
DRAINAGE
DIVISION
Division Manager -
LWD
Project Managers
Construction Mngrs.
Project Engineers
Sr. Qty. Surveyors
Quantity Surveyors
I & C Engineers
Exec. Secretary
Secretary
Doc. Controller
Proj. Support Team
Foremen
Work Crew
CIVIL
DEPARTMENT
Civil Department
Manager
Projects Manager
Construction Mngr.
Design Engineers
Project Engineers
Quantity Surveyors
Proj. Support Team
Foremen
Work Crew
LEGAL
DEPARTMENT
Head of Legal
Department
Legal Advisor
COST CONTROL
DEPARTMENT
Cost Control
Manager
Legal Secretary
Lead Cost Control
Engineer
Technical Secretary
PLANNING
DEPARTMENT
Planning Department
Manager
Sr. Planning Engrs.
Planning Engineers
BUSINESS
DEVELOPMENT
DEPARTMENT
Business
Development
Director
Business Dev’t.
Associate
Sales Engineer
Secretary
HSE
DEPARTMENT
HSE Manager
Sr. HSE Engineers
HSE Engineers
Sr. Safety Officers
Safety Officers
Male Nurse
QA/QC
DEPARTMENT
QA/QC Manager
QA/QC Engineers
QA/QC Inspectors
QHSE Secretary
10
Company Manpower Chart
Lindenberg has got sufficient manpower, including Chartered Engineers, Certified Accountants,
Certified Electrical and Civil Discipline Technicians to participate and execute Mega Projects with
utmost professionalism and to the satisfaction of our Clients.
Staff Category (Total: 256) Skilled & Unskilled Workers (Total: 801)
QA/QC
Engineers, 4
Planning & Cost
Control, 4
Engineers - All
Discipline, 62
Foreman &
Supervisors, 46
Draftsman - All
Discipline, 9
Doc Controllers, 7
Coordinators, 6
Officers & Legal
Advisors, 6
Administrators, 6
Project Managers /
Dept. Heads, 29
Storekeepers /
Timekeepers, 10
Office Assistants, 17
Safety Officers, 12
Secretaries, 14
Accountants, 11
Land
Surveyors, 13
Laborers, 293
Painters, 6
Mechanics, 9
Welders, 12
Pipe Fitters, 19
Carpenters, 119
Charged Hands, 27
Masons, 68
Operators, 46
Cleaners / Office Boy,
30
Electrician, 66
Steel Fixers, 59
Drivers - All Discipline,
47
Data as of Dec-2011
11
Registration / Clients List
Lindenberg is registered / pre-qualified or have submitted tender with the following companies /
government agencies:
1. Abu Dhabi Distribution Company (ADDC)
2. Abu Dhabi Future Energy Company
(MASDAR)
3. Abu Dhabi Gas Industries Ltd. (GASCO)
4. Abu Dhabi Health Services Co. PJSC (SEHA)
5. Abu Dhabi Marine Operating Company
(ADMA-OPCO)
6. Abu Dhabi Ministry of Defense – Military
Works Department
7. Abu Dhabi National Oil Company (ADNOC)
8. Abu Dhabi Oil Refining Company (TAKREER)
9. Abu Dhabi Police General Head Quarters
10. Abu Dhabi Polymers Co. Ltd. (Borouge)
11. Abu Dhabi Sewerage Services Company
(ADSSC)
12. Abu Dhabi Transmission & Despatch
Company (TRANSCO)
13. Abu Dhabi Water & Electricity Authority
(ADWEA)
14. Al Ain Distribution Company (AADC)
1 2 3 4 5 6
7 8 9 10 11 12
13 14 15 16 17 18
19 20 21 22 23 24
15. ALDAR Properties PJSC 20. Municipality of Abu Dhabi
16. Dubai Electricity & Water Authority (DEWA) 21. National Central Cooling Co. PJSC (TABREED)
17. Federal Electricity & Water Authority (FEWA) 22. Sultanate of Oman – Public Authority for Electricity and Water
18. International Petroleum Investment Co. (IPIC) 23. Tourism Development & Investment Company (TDIC)
19. Mubadala Development Company 24. UAE Armed Forces – Special Operations Command
12
Registration / Clients List
Lindenberg is highly experienced working with the following Project Consultants:
1. Deutsche Energie Consult GmbH (DECON)
2. Dorsch Consult
3. Dr. M. H. Ali El-Saie Consulting Engineers
4. Hyder Consulting Middle East Limited
5. ILF Consulting Engineers
6. Italconsult
7. Lahmeyer International GmbH
8. Mott Macdonald
9. Ozen Levent Power Engineering
Consultancy LLC
10. Parsons Brinckerhoff Power
11. Parsons International Ltd.
12. Tebodin Consultants & Engineers
1 2 3 4
5 6 7 8
9 10 11 12
13
Lindenberg was Prequalified & Tendered for ADSSC’s STEP Project:
1. Lindenberg Emirates was one of the 5
prequalified companies for the Sewerage
Tunnel Enhancement Project “STEP Project”
comprising of a 45 km tunnel of 5-meter
diameter at a depth of 40-45 meters which is
expected to be worth of AED 3 Billion. For
this tender, Lindenberg formed a consortium
with Major Korean Construction Companies.
2. Tender No. O-1506, STEP Deep Tunnel Sewer
Contract T-02.
3. Tender No. O-1578, STEP Deep Tunnel Sewer
Contract T-03.
14
Company Classification at Abu Dhabi Department of Planning & Economy
SN Field Scope of Works Category
1. WATER PROJECTS
2. ELECTRICAL PROJECTS
3. SEWERAGE PROJECTS
4.
1. Water Transport Plants & Networks
2. Water Distribution Plants & Networks
1. Power Distribution Networks & Plants
2. Communications Networks
1. Main Sewerage Networks
2. Sewerage Sub-Networks & House Connections
MECHANICAL & ELECTRICAL
WORKS PROJECTS 1. Mechanical and Electrical Works 5 th
5. BUILDING PROJECTS
1. All types of Buildings
2. Metallic Constructions
1 st
1 st
2 nd
5 th
5 th
5 th
5 th
5 th
15
Selected Power & Civil Projects
SN Contract No. Contract Name Client Contract Value Award Date Consultant Status
1
2
3
4
5
6
7
8
9
10
11
12
R-99-0157
G-6334
G-1882
Security of the Electric Power Supply and Upgrade of the Network for Presidential
Palaces and Hospitals
Electrical & Civil Engineering Works for the Implementation of 4 MW NGK Battery
Energy Storage (42MW)
Security of the Electric Power Supply and Upgrade of the Network for Presidential
Palaces and Hospitals (Stage-III Phase-III)
ADWEA AED 176,957,025 08.02.2000 Mott MacDonald Completed
ADWEA AED 142,271,120 23.11.2009 DECON Ongoing
ADWEA AED 103,122,825 07.08.2005
Lahmeyer
International GmbH
Completed
D-6990 Replacement of 11 KV Switchgears in W13, E15 and Salt & Chlorine Substations ADDC AED 81,991,962 03.01.2010 Parsons Brinckerhoff Ongoing
D-7150
D-10624
115979C13E
Security and Upgrading of 11 kV Electrical Network for H.H. Shk. Khalifa Palace
in Abu Dhabi & Erection of Equipment in Substation No. 4 & 5 in Beach Palace
Transfer of Load to New 132/11 kV W24 and E01 Primary Substations in Abu
Dhabi Island
Ruwais Housing Complex Expansion – Phase III, Procurement of Electrical
Equipment – Low Voltage (LV) Panels Switchgear
- Shuweihat S3 IPP Civil Work Package 3
G-1494
D-10599
Security of the Electric Power Supply and Upgrade of the Network for Presidential
Palaces and Hospitals, Stage-III Phase-III, Lot-1
Transfer of 11kV Load to E48/02 & Khalifa A2 Primary Substation in Abu Dhabi
Island & Eastern Region
ADDC AED 40,667,381 05.05.2008
Ozen Levent
Power Engineering
Consultancy LLC
Completed
ADDC AED 34,028,598 25.05.2010 DECON Ongoing
ADNOC AED 29,675,361 23.04.2009 - Completed
Daewoo
E&C
AED 29,191,474 27.07.2011
ADWEA AED 25,914,216 05.02.2003
Fichtner Consulting
Engineers
Lahmeyer
International GmbH
Ongoing
Completed
ADDC AED 19,683,403 10.02.2010 DECON Completed
D-7720 Modification of Switching Stations in Abu Dhabi Island ADDC AED 16,999,999 06.10.2008 - Completed
4600037153
Supply and Installation of 11kV Package Unit Substation for Braka Nuclear Power
Plant
Hyundai E&C AED 16,865,843 27.07.2011 - Ongoing
16
Selected Water & Drainage Projects
SN Contract No. Contract Name Client Contract Value Award Date Consultant Status
1
2
3
4
5
6
7
8
9
10
N-5807
Water Transmission Scheme from Sas Al Nakheel (UAN) Junction to Sadiyat /
Abu Dhabi Island
TRANSCO AED 569,594,995 20.01.2008
D-10924 Water Supply to ADCO & GASCO Facilities at Buhasa and Habshan ADDC AED 179,999,340 08-01-2012
N-6821
O-1463
EPC Works for Al Ain Distribution Network – Pipelines Umn Ghaffa Floating
Reservoir Station – Lot D
Works Associated with the Replacement of Existing Sewer Networks at Some
Sectors Inside Abu Dhabi Island - Category A
TRANSCO AED 174,524,364 07.03.2010
Tebodin Consultants
and Engineers
Tebodin Consultants
and Engineers
ILF Consulting
Engineers
Ongoing
Ongoing
Ongoing
ADSSC AED 116,026,699 13.06.2010 Dorsch Gruppe Ongoing
N-2622.1 Water Supply to Sadiyat Island and Adjacent Areas – Lot A,B, & C TRANSCO AED 108,118,493 22.07.2007
Tebodin Consultants &
Engineers
Completed
D-7310.1 Replacement of 2 DN 600 Pipelines in Baniyas along Al Ain Highway ADDC AED 94,037,448 22.05.2008 Italconsult Completed
O-10841
CW/119C/
2007
11 D-5630
Construction of Sewerage Connections and Related Works in Abu Dhabi Island
and Main Land - Phase VII
Supply, Installation, Testing and Commissioning of Fiber Cement / Glass
Reinforced Epoxy / Ductile Iron Water Transmission Pipelines and Associated
Works at Various Locations in Emirates of Dubai (1200 mm Dia Pipeline Along
Emirates Road)
ADSSC AED 80,000,000 29-Mar-2012
DEWA AED 73,794,659 08-Jul-2007
N-5386 Water Transmission Lines Inside Al Reem Island – Lot A TRANSCO AED 56,455,067 03.02.2008
AECOM Middle East
Ltd.
NJS Consultants
Co. Ltd.
Tebodin Consultants
and Engineers
Ongoing
Completed
Completed
N-4604 DN 1000mm Transmission Pipeline from Sweihan to Remah TRANSCO AED 25,889,764 23.07.2007 Mott Mac Donald Completed
Urgent Works at Al Qadra Village Owned by
HH Sheikh Mansour Bin Zayed
ADWEA AED 16,877,777 15.04.2006 Italconsult Completed
12 O-1047 Sewerage and Surface Drainage Works (SAS Al Nakheel & Seeh Shua’ib) ADSSC AED 10,400,000 30.01.2008 Parsons Intl Ltd Completed
17
Division Profile
Lindenberg Power Division provides expertise in implementing Electromechanical and
Instrumentation projects on turnkey basis, starting from the design stage to construction, testing and
commissioning and maintenance services for diverse industrial projects.
Having the expertise in turnkey contracting on many projects, the Power Division is very familiar
with all criteria necessary for the successful execution of Electromechanical projects. The Power
Division builds these mandatory requirements into all projects:
� Reliable and efficient performance
� Single-point responsibility
� ISO-certified quality control procedures
� Proven safety programs
� Cost controls and reductions
� Productive and on-time scheduling
18
Division Profile
The Power Division provides a dedicated technical and managerial team necessary to design and
construct new facilities or upgrades. By bringing together every aspect of a power project under a
single management team, the division provides economical and efficient solutions to meet the needs
of a diverse industry base.
The project management team comprised of specialists in the design, construction and operation of
complex type of projects. From concept through acceptance, the division provides the optimal
resources, equipment and services to meet all contractual requirements. The EPC team is
accountable for the following critical functions:
� Planning, organizing and procedures
� Scheduling and tracking
� Cost control
� Document control
� Single-point customer contact
� Progress reporting
19
Scope of Activities
� Contracting works for Power Networks and Distribution Systems
� Underground cable network including jointing, termination, testing and commissioning
� Complete electrical and instrumentation works for Power Plants, Refineries, Power Stations,
Desalination Plants and Sewerage Treatment Plants
� Turnkey contracting works for LV / MV / HV Substations
� EPC works for electric generators
� Installation and commissioning of auxiliary powers, package substation, control panels and
transmission lines
� Contracting works for plant fire fighting and safety alarm systems, remote monitors, and fire
suppression systems.
� Control / MCC room fire suppression systems installation
� Submarine Cable Installation
� Industrial Building Construction
� HVAC Works
� LV / MV / HV Switchgear and Transformer Installation
� Installation and Commissioning of Auxiliary Power Supplies
20
Typical Power Project Organization Chart
ENGINEERING
Civil Engineer
Electrical Engineer
PLANNING & QS
Planning Engineer
Quantity Surveyor
Mechanical Engineer Site Civil Engineer
Mechanical Foreman
HEAD OF POWER DIVISION
PROJECT MANAGER
CONSTRUCTION
Construction Manager /
Project Engineer
HSE & QA/QC
HSE Engineer
QA/QC Engineer
Site Electrical Engineer Testing & Comm. Eng.
Civil Foreman Electrical Foreman Draftsmen
OFFICE SUPPORT
Design Coordinator
Coordinator
Secretary
Doc. Controller
Storekeeper
Timekeeper
Watchman
21
Featured Projects
Security of the Electric Power Supply and Upgrade of the Network for Presidential
Palaces and Hospitals
Contract No. R-99-0157
Client Abu Dhabi Water & Electricity Authority (ADWEA)
Value AED 176,957,025
Award Date 08-Feb-2000
Description Supply, Installation, Testing & Commissioning Works
Project was completed.
22
Featured Projects
Electrical & Civil Engineering Works for the Implementation of 4 MW NGK Battery
Energy Storage (42MW)
Contract No. G-6334
Client Abu Dhabi Water and Electricity Authority (ADWEA)
Value AED 142,271,120
Award Date 23-Nov-2009
Description Design & Construction of 10 Nos. BESS Substation & Installation Testing
Commissioning of NGK Batteries & Supply of Auxiliary Items.
23
Featured Projects
Security of the Electric Power Supply and Upgrade of the Network for Presidential
Palaces & Hospitals (Stage-III Phase-III)
Contract No. G-1882
Client Abu Dhabi Water & Electricity Authority (ADWEA)
Value AED 103,122,825
Award Date 07-Aug-2005
Description Design, Supply, Installation Testing and Commissioning including remote
control monitoring system, ISMS, and Medium Voltage Panels.
Project was completed in May 2010.
24
Featured Projects
Replacement of 11 KV Switchgears in W13, E15 and Salt & Chlorine Substations
Contract No. D-6990
Client Abu Dhabi Distribution Company (ADDC)
Value AED 81,991,962
Award Date 03-Jan-2010
Description Design & Construction of 1 New 132/11 kV Substation & Modification of
11 kV Network and Replacement with new 11 kV Switchgear @ 2 nos.
Substation.
25
Featured Projects
Security and Upgrading of 11 kV Electrical Network for H.H. Shk. Khalifa Palace in Abu
Dhabi & Erection of Equipment in Substation No. 4 & 5 in Beach Palace
Contract No. D-7150
Client Abu Dhabi Distribution Company (ADDC)
Value AED 40,667,381
Award Date 05-May-2008
Description Design, Supply, Installation Testing and Commissioning of 11KV
Switching Station & replacement of Switchgears, Control Panels, DC
system in Beach Palace Stations B4, B5 Stations & Standby power plant
in H.H.Shk Khalifa Switching station. Completed in July 2010.
26
Featured Projects
Security of the Electric Power Supply and Upgrade of the Network for Presidential
Palaces and Hospitals Stage-III Phase-III. Lot-1
Contract No. G-1494
Client Abu Dhabi Water & Electricity Authority (ADWEA)
Value AED 25,914,216
Award Date 05-Feb-2003
Description Design, Supply, Installation Testing and Commissioning Works
Project was completed.
27
Featured Projects
Transfer of 11kV Load to E48/02 & Khalifa A2 Primary Substation in Abu Dhabi Island &
Eastern Region (2010)
Contract No. D-10599
Client Abu Dhabi Distribution Company (ADDC)
Value AED 19,683,403
Award Date 10-Feb-2010
Description Installation of Underground 11 kV Cables of 112 km & FO Cables of 20
km.
28
Featured Projects
Supply and Installation of 8 Nos. 415 Volts Diesel Generators
Contract No. G-1206
Client Abu Dhabi Water & Electricity Authority (ADWEA)
Value AED 13,039,984
Award Date 10-Apr-2002
Description Design, Supply, Installation, Testing and Commissioning of 8 Nos. 415
Volts Diesel Generators.
29
Featured Projects
Transfer of Load to New 132/11 kV W24 and E01 Primary Substations in Abu Dhabi Island
Contract No. D-10624
Client Abu Dhabi Distribution Company (ADDC)
Value AED 34,028,598
Award Date 25-May-2010
Description Supply of 11kV Switchgear, DC System, LVAC, DMS System, Auxiliary Transformer and Joints & Terminations.
Installation of Power Cables, 11/0.415kV Package S/S and Civil Works i.e. Building, Trenching, etc.
Ruwais Housing Complex Expansion – Phase III, Procurement of Electrical Equipment – Low Voltage (LV) Panels Switchgear
Contract No. 115979C13E
Client Abu Dhabi National Oil Company (ADNOC)
Value AED 29,675,361
Award Date 23-Apr-2009
Description Supply & Delivery of Low Voltage Panels Switchgear.
30
Featured Projects
Shuweihat S3 IPP Civil Work Package 3
Client Daewoo E&C-Siemens (Consortium)
Value AED 29,191,475
Award Date 20-Jul-2011
Description Civil works which includes excavation, filling, concreting, finishing, waterproofing, structural steel works, etc. for
fuel gas pipelines with sleeper foundations & trenches, storm drain works and site roads with asphalt.
Supply and Installation of 11kV Package Unit Substation for Braka Nuclear Power Plant
Contract No. 4600037153
Client Hyundai Engineering & Construction
Value AED 16,865,843
Award Date 27-Jul-2011
Description Commissioning of 18 Nos. 11 kV Package Substations.
31
Featured Projects
Modification of Switching Stations in Abu Dhabi Island
Contract No. D-7720
Client Abu Dhabi Distribution Company (ADDC)
Value AED 16,999,999
Award Date 06-Aug-2008
Description Supply, Installation & Commissioning of RMU’s and Modification of
Transformer Panel to Feeder Panel in Switching Stations.
Long Term Rate Agreement for Installation of Underground Cables, Electrical Distribution Equipment, OHL and allied works in Abu
Dhabi Eastern Region
Contract No. D-9710/C
Client Abu Dhabi Distribution Company (ADDC)
Value AED 10,000,000 per year
Award Date 16-Apr-2009
Description Installation of Underground Cables, Electrical Distribution Equipments, OHL and Allied Works as per Work Order
Basis.
32
Featured Projects
Transfer of 11kV Load to New 132/11kV W02 Primary Substation in Abu Dhabi Island
Contract No. D-11915
Client Abu Dhabi Distribution Company (ADDC)
Value AED 13,603,107
Award Date 23-Oct-2011
Description Excavation and 11 kV cable laying works in Central Market Area, in order to transfer 11 kV load to new 132/11 kV
W02 Primary Substation.
Installation of 22 kV Cables from 132/22 kVA - A Beach Primary to Masdar City
Client Abu Dhabi Distribution Company (ADDC)
Value AED 2,121,525.65
Award Date 15-Sep-2011
Description Installation & commissioning of 22 kV power cables with 144 fiber optic cables to provide the power supply to the
initial demand for Masdar City Development.
33
Power Stations
Power Station with Diesel Engine for operation
on Diesel, Crude Oil and HFO
Power Station with Gas Engines Power Station with Dual Fuel Engines
Turnkey Power Stations up to 12 MW
Powered with Diesel, Gas and Dual Fuel Engines
34
Division Profile
In order to accommodate the brisk developments of UAE’s industry, Lindenberg Water and Drainage
Division was established to provide water and drainage solutions.
The Division has up-to-date working knowledge of and is very well conversant with the requirements
in water supply and water distribution network. The necessary infrastructure, including manpower,
reliable sources of suppliers, equipment are readily available at our disposal.
35
Division Profile
The Water & Drainage Division is acknowledged as the premier provider of the highest quality
professional service in the field of water and drainage facilities; insuring absolute client satisfaction
through the expertise and experience of its people. The division aims to provide new technologies,
processes, and materials to build and deliver water and drainage facilities that are best suitable for
their class & area of usage.
Scope of Activities
� Water Pipeline Networks
� Water & Irrigation Reservoirs
� Water & Sewerage Pumping Stations
� Sewage Treatment Plants
� Operation & Maintenance of Sewerage
Networks and Pumping Stations
36
Typical Water & Drainage Project Organization Chart
ENGINEERING
Civil Engineer
Electromech’l Engineer
Inst & Ctrl. Engineer
Water Tank Works
(Concrete Construction)
PLANNING & QS
Planning Engineer
Quantity Surveyor
DIVISION MANAGER
PROJECT MANAGER
CONSTRUCTION
Construction Manager /
Project Engineer
HSE Engineer
QA/QC Engineer
Site Engineer Site Engineer Site Engineer
OFFICE SUPPORT
Coordinator
Secretary
Doc. Controller
Draftsman
Storekeeper
Timekeeper
Civil Works Pipeline Works Chamber Works Electromechanical Works Inst’n & Control Works
Work Crew Land Surveyor Land Surveyor Land Surveyor E/W Work Crew I & C Work Crew
Civil Work Crew Pipeline Crew Chamber Crew
HSE & QA/QC
Foreman Civil Foreman Pipeline Foreman Chamber Foreman E/M Foreman I & C Foreman
37
Featured Projects
Water Transmission Scheme from Sas Al Nakheel (UAN) Junction to Sadiyat / Abu Dhabi
Island
Contract No. N-5807
Client Abu Dhabi Transmission & Despatch Company (TRANSCO)
Value AED 569,594,995
Award Date 20-Jan-2008
Description Construction of DI/CS Pipelines
38
Featured Projects
Water Supply to ADCO & GASCO Facilities at Buhasa and Habshan
Contract No. D-10924
Client Abu Dhabi Distribution Company (ADDC)
Value AED 179,999,340
Award Date 08-Jan-2012
Description Construction of 65 km DN 400~500 DI Pipelines, 2 x 0.5 Million Gallons
Storage Steel Tanks and Pump Station of 7 Million Gallons per day
capacity.
39
Featured Projects
EPC Works for Al Ain Distribution Network - Pipelines Umn Ghaffa Floating Reservoir
Station - Lot D
Contract No. N-6821
Client Abu Dhabi Transmission & Despatch Company (TRANSCO)
Value AED 174,524,364
Award Date 07-Mar-2010
Description EPC for 2 Nos. 25 Million Gallons Steel Tanks and associated Civil and
Pipeline Works.
40
Featured Projects
Works Associated with the Replacement of Existing Sewer Networks at Some Sectors
Inside Abu Dhabi Island - Category A
Contract No. O-1463
Client Abu Dhabi Sewerage Services Company (ADSSC)
Value AED 116,026,699
Award Date 13-Jun-2010
Description Construction, Replacement & Rehabilitation of Existing Sewer Lines and
Manholes Inside Abu Dhabi Island.
41
Featured Projects
Water Supply to Sadiyat Island and Adjacent Areas – Lots A, B, & C
Contract No. N-2622.1
Client Abu Dhabi Transmission & Despatch Company (TRANSCO)
Value AED 108,118,493
Award Date 22-Jul-2007
Description Supply, Construction, & Installation of Water Supply Network
The Project was completed in June 2009
42
Featured Projects
Replacement of 2 DN 600 Pipelines in Baniyas along Al Ain Highway
Contract No. D-7310.1
Client Abu Dhabi Distribution Company (ADDC)
Value AED 94,037,448
Award Date 22-May-2008
Description Supply and Replacement of Water Transmission Pipelines
The Project was completed in November 2010
43
Featured Projects
Water Transmission Lines Inside Al Reem Island – Lot A
Contract No. N-5386
Client Abu Dhabi Transmission & Despatch Company (TRANSCO)
Value AED 56,455,067
Award Date 03-Feb-2008
Description Installation of DI/CS Pipelines
The Project was completed in January 2010
44
Featured Projects
DN 1000mm Transmission Pipeline from Sweihan to Remah
Contract No. N-4604
Client Abu Dhabi Transmission & Despatch Company (TRANSCO)
Value AED 25,889,764
Award Date 23-Jul-2007
Description Supply, Construction, and Installation of Water Transmission Pipelines
The Project was completed in June 2009
45
Featured Projects
Urgent Works at Al Qadra Village Owned by HH Sheikh Mansour Bin Zayed
Contract No. D-5630
Client Abu Dhabi Water & Electricity Authority (ADWEA)
Value AED 16,877,777
Award Date 15-Apr-2006
Description Supply, Construction & Maintain Water Supply Network
The Project was completed in July 2008
46
Featured Projects
Sewerage and Surface Drainage Works (SAS Al Nakheel & Seeh Shua’ib)
Contract No. O-1047
Client Abu Dhabi Sewerage Services Company (ADSSC)
Value AED 10,400,000
Award Date 30-Jan-2008
Description Miscellaneous Sewerage and Drainage Works at Sas Al Nakheel & Sash
Shuhaib
The Project was completed in July 2009
47
QHSE Policy
LINDENBERG implements and maintains an effective QHSE Management System in line with the
requirements of ISO 9001:2008, ISO 14001:2004 & OHSAS 18001:2007.
It is our policy to
� Meet or exceed our clients' expectations, the first time and every time, through the application of
proven quality principles at all levels of our business;
� Minimize the generation of hazardous & toxic waste, preventing the release of harmful substances
into the environment, while encouraging the reduction, recycling and re-use of materials;
� Instilling and promoting safety consciousness to prevent ill health, injury and incidents; and provide a
safe and healthy working environment for our employees, clients, and subcontractors.
We are committed to
� Ensuring that adequate resources are made available for QHSE purposes.
� Ensuring that QHSE is accepted as a core management activity, given equal priority as other
objectives and management functions, and included in the company business plan.
� Promoting a positive QHSE culture within the top management and encouraging active employee
participation in QHSE throughout all levels of the company.
LE-IMS-Pol | rev. 1
AHMAD ZAABRI
General Manager
48
QHSE Certificates & Membership
Lindenberg Emirates is an Integrated Management System (IMS) certified company and has
established, implemented and maintained an effective Quality, Occupational Health & Safety and
Environmental Management System, in line with the requirements of ISO 9001:2008, ISO 14001: 2004
and OHSAS 18001:2007 to ensure that customer satisfaction and requirements are being met.
ISO 9001:2008
ISO 14001:2004
OHSAS 18001:2007
British Safety Council
49
Workforce and Labour Camp
Lindenberg-Emirates LLC employs almost 800 Skilled and Unskilled Labors. Labor Camps with all
modern facilities are established in Al Faya, Mussafah and Al Ain to accommodate the requirements of
the health & safety of the workforce.
Camp Location Size No. of Rooms
Al Faya 1,300 m 2
Magenta Camp (rented)
Al Ain 400 m 2
Current No. of
Occupants
96 600
46 264
28 45
Data as of 10-Oct-2011
50
Store Facilities
Aside from Projects Sites Stores and Yards, two Main Stores of 30x20 m 2 are operational at Mussafah to
help in storing & preserving the materials received for different projects, also used for storage of our
standard erection tools required during installation/ commissioning activities.
51
Plant, Machineries, Vehicles and Equipment
Lindenberg Emirates’ policy in Vehicles, Equipment and Machinery is to:
� purchase and own all equipment to cover the project needs.
� self-maintain these vehicles, equipment and machinery.
� hire vehicles, equipment and machinery to prevent delays in the project execution.
52
Contact Information
We hope that the information given and detailed in this Company Profile is sufficient to illustrate the
potential and capabilities of Lindenberg. We will be pleased to provide further information on your
request. Kindly contact us.
Lindenberg Emirates LLC Lindenberg Water & Drainage Division
Villa 101, Al Nahyan Camp Area, (A Division of Lindenberg Emirates LLC)
Muroor Road, P.O. Box 42630, Tel: +971 2 642 2576
Abu Dhabi, United Arab Emirates Fax: +971 2 642 2579
Tel: +971 2 642 2576 E-mail: lwd@lindenberg.ae
Fax: +971 2 642 2591
E-mail: info@lindenberg.ae Lindenberg Power Division
Website: www.lindenberg.ae (A Division of Lindenberg Emirates LLC)
Tel: +971 2 642 2576
Fax: +971 2 642 2571
E-mail: lpd@lindenberg.ae
P.O. Box 42630, Abu Dhabi, United Arab Emirates
Tel: +971 2 6811061, Fax: +971 2 6813655
E-mail: info@lindenberg.ae
Website: www.lindenberg.ae