The Moonstone Project: “To design and build Britain's leading ...
The Moonstone Project: “To design and build Britain's leading ...
The Moonstone Project: “To design and build Britain's leading ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>The</strong> <strong>Moonstone</strong> <strong>Project</strong>: <strong>“To</strong> <strong>design</strong> <strong>and</strong> <strong>build</strong> Britain’s <strong>leading</strong> autonomous Eco-house”
Before the work began<br />
Description of the brief that was given to the <strong>build</strong>er:<br />
To <strong>design</strong> <strong>and</strong> <strong>build</strong> an architecturally outst<strong>and</strong>ing Cotswold contemporary positive energy Eco-home in harmony with its setting in an Area of Outst<strong>and</strong>ing Natural Beauty (AONB).<br />
<strong>The</strong> house is not to be connected to mains water, gas or any fossil fuels, mains foul or storm water services making it fully autonomous<br />
Were there any special issues that had to be taken into consideration ?<br />
<strong>The</strong> site was in an AONB area <strong>and</strong> the Planners insisted on a modern 21st Century <strong>design</strong> .<br />
<strong>The</strong> previous owners had failed for 8 consecutive years trying to get planning permission for a property on this AONB site.<br />
<strong>The</strong> planners insisted on a distinctive linear <strong>build</strong>ing cut into the hillside.<br />
<strong>The</strong> <strong>build</strong>ing had to be <strong>design</strong>ed to have heating only from a renewable source.<br />
During the construction phase all <strong>build</strong>ing waste where practical was to be recycled on site.<br />
A third of the <strong>build</strong>ing was to be underground<br />
Who drew up the plans ?<br />
Roderick James Architects were involved in the concept <strong>design</strong>. Centurion Western made extensive use of a 3-D modelling package called ArchiCAD to make further submissions<br />
to the Planning Committee in order to achieve approval to <strong>build</strong>.
During the work<br />
When was the project started ?<br />
Design, drawings <strong>and</strong> full Planning submission with successful outcome was from July 2003 to August 2004. <strong>Project</strong> was unable to commence due to Planning restrictions until March 2005.<br />
Construction started March 2005 <strong>and</strong> was completed in February 2009<br />
Construction Started: March 2005<br />
When was the project completed ?<br />
February 2009<br />
Were any special / unusual materials or <strong>build</strong>ing systems used ?<br />
To be the best Eco house in the Country, innovative <strong>and</strong> often untried technologies had to be used in its construction.<br />
<strong>The</strong> whole <strong>build</strong>ing now has levels of insulation 65% better than the very Best German Eco st<strong>and</strong>ard of the Passiv Haus—U values of the walls of 0.06 w/m 2 K cf. 0.15 w/m 2 K.<br />
Full commercial quarrying equipment was brought in to excavate <strong>and</strong> process all 12,000 tonnes of Cotswold stone material on site. All this material was recycled in the battered wall construction or for hardcore for the<br />
driveways. <strong>The</strong> only <strong>build</strong>ing waste removed from site was in three 8 cubic yard skips.<br />
A Canadian ICF (Insulated Concrete Formwork) was used with water proof concrete—to provide a water proof underground basement <strong>and</strong> water proof tanking to a third of the <strong>build</strong>ing which was<br />
underground.<br />
Large Hanson 200mm <strong>and</strong> 300mm thick 7m long x 1.2m wide floor panels had to be craned into position.<br />
Highly insulated triple glazed windows with a U value = 0.7 w/m 2 K were imported from Germany<br />
Walls were constructed with a 1m thick Cotswold stone battered wall with a 3 degree pitch with super insulation of 400mm of extruded polystyrene to totally fill the cavities. All ground floors were built on 300mm of heavy<br />
duty insulation<br />
<strong>The</strong> inner wall was treated with a epoxy tanking materials <strong>and</strong> the full height of the walls dressed with a 4mm neoprene jacket to create an air <strong>and</strong> water tight structure.<br />
Eight bore holes <strong>and</strong> a further 1 1 /2 miles of 40mm pipe was buried around the property t o provide heating to the 12Kw Ground source heat pump.<br />
A 44 square metre arrangement of flat plate solar thermal panels provide the house with 85% of its hot water <strong>and</strong> heating requirements.<br />
All drinking <strong>and</strong> other water requirements are met by an on site spring<br />
Rain water is collected from the roofs <strong>and</strong> discharged via pipe work hidden in the walls <strong>and</strong> used to fill reflection <strong>and</strong> infinity pools at the extremities of the <strong>build</strong>ing<br />
A two tier vertical reed bed was constructed to process all waste water on site—to drinking quality st<strong>and</strong>ard.<br />
An Aquatron worm biogester unit composts all solid wastes from toilets <strong>and</strong> waste food <strong>and</strong> is then re-used as compost<br />
<strong>The</strong> house was the first domestic property in the UK to use Rehau Earth pipes installed 3 metres below ground. Via this pipe work incoming air is ducted through 6 lengths of 50m underground Earth pipes pre-warming the<br />
air in the winter months <strong>and</strong> cooling it in the summer months.<br />
A full mechanical heat recovery system, filters <strong>and</strong> purifies all incoming air into the property <strong>and</strong> recovers wasted heat from the kitchen, bathrooms, tumble dryer <strong>and</strong> Aquatron bio-gester.<br />
<strong>The</strong> house is illuminated with LED lighting saving an additional 60% over normal energy efficient lighting.<br />
A CLIPSAL lighting <strong>and</strong> automation system was fitted into the house, with PIR’s switching lights on <strong>and</strong> off when necessary <strong>and</strong> all lighting circuits are set on timers with occupancy detection to save<br />
further electricity. All light switches are fully programmable with SMART phone control; lights can be remotely turned on <strong>and</strong> off. <strong>The</strong> house can be monitored fully from remote internet sites.<br />
A Schluter super thin 25mm screed underfloor heating system, provides rapid heating comparable with traditional radiators <strong>and</strong> traditional underfloor systems. <strong>The</strong> very thin Supa flow liquid screed only needs an input temperature<br />
of 35 degrees to reach a room temperature of 21 degrees, making it perfect for the small Ground source heat pump.<br />
Two 1500 litre stratified hot water thermal storage cylinders have multiple inputs allowing for easily connection of solar thermal, ground source heat pumps <strong>and</strong> other renewable energies.<br />
<strong>The</strong> 3000 litre hot water storage covers the house for approximately 7 days, with any short fall being met by the Ground source heat pump.
During the work<br />
How well were any problems <strong>and</strong>/or changes to the initial brief dealt with ? Please provide examples:<br />
Planning Permission.<br />
Despite a 12 month consultation period with the local Planning team, <strong>and</strong> initial 100% acceptance for our ideas, a change in personnel of the planning team, meant after 12 months they rejected our scheme.<br />
<strong>The</strong> architect was unwilling to submit the scheme without written planning officer approval, therefore Centurion Western invested heavily in a 3D modelling architectural software providing detailed images of the<br />
proposed property showing life like wall finishes <strong>and</strong> 3D models with DVD production showing animations of the proposed dwelling. <strong>The</strong> <strong>build</strong>er supported the customer at the planning committee meeting<br />
contributing to final committee approval for the plans.<br />
Over coming a very steep site;<br />
<strong>The</strong> <strong>build</strong>ing site is perched on a steep hillside in the Cotswolds AONB area. Careful demolition <strong>and</strong> on-site crushing of existing industrial <strong>build</strong>ings were completed prior to the excavation 11 metres below ground into<br />
the rock face to create the underground section of the house. <strong>The</strong> <strong>build</strong>ers then had to create a wide temporary driveway down to this level for the plant including a 60tonne crane, <strong>and</strong> over 120 concrete wagons<br />
Minimise waste <strong>and</strong> recycle, where possible, all materials on site.<br />
We were keen that the <strong>build</strong>ing process should be as green as possible asking for materials <strong>and</strong> suppliers to be sourced within a 30 mile radius from site minimising the carbon foot print of the property. 12,000 tonnes<br />
of excavated stone were re-used in the large 1 metre thick battered stone walls <strong>and</strong> the driveways <strong>and</strong> l<strong>and</strong>scaping around the house. Crushing <strong>and</strong> sorting machinery was brought in to produce different sizes of<br />
aggregates for different uses on site. Large ready mixed self coloured mortar silo’s were brought in to accurately produce a consistent mix <strong>and</strong> colour for the stone walls <strong>and</strong> minimise waste materials associated with<br />
piles of bulk s<strong>and</strong>.<br />
Extreme weather conditions <strong>and</strong> break-ins. 2007 Gloucester floods<br />
<strong>The</strong> <strong>build</strong> experienced extreme flooding in the summer of 2007 —with May through to August being a complete wash out, <strong>and</strong> the nearby stream water level rising by 2 1/2 metres. November through to January was<br />
regularly impacted by heavy snow falls. In 2005, flooding in New Orleans (USA) resulted in a 40% increase in the cost of raw zinc material for the extensive curved roof curved roof.<br />
CWL offered costs savings in other areas to offset the unexpected increased costs. Four break-ins on site , the first within just 2 months of commencing works <strong>and</strong> resulting in over £50,000 worth of damage <strong>and</strong> theft<br />
to machinery <strong>and</strong> equipment on site. <strong>The</strong> first theft—caused a 10 week set back as all the specification drawings <strong>and</strong> CAD models were stolen resulting in having to go back to the drawing board.<br />
Being an innovative <strong>build</strong>.<br />
As an experimental house using new <strong>and</strong> untested technologies with little application in the UK the <strong>build</strong>er regularly faced new challenges <strong>and</strong> worked hard to forge relationships with local <strong>and</strong> European suppliers. This<br />
attention to detail in many areas (e.g. LED lighting system, waterproofing, triple glazing system, ceiling features, solar, heat pumps <strong>and</strong> reed beds) enabled the <strong>build</strong>er to successfully integrate a range of high tech systems<br />
to function effectively to create a true example of a passive house. <strong>The</strong> <strong>build</strong>er was innovative in dealing with challenges <strong>and</strong> managing potential conflicts of systems on site in a timely manner. He also challenged<br />
suppliers with potential installation issues prior to arrival on site to reduce delay <strong>and</strong> cost to the project.
Overall satisfaction<br />
Which aspect of the work delighted you the most ?<br />
<strong>The</strong> overall finishing—the details that most people never see. <strong>The</strong> battered Cotswold stone walling looks stunning. <strong>The</strong> 5mm shadow gaps, in the ceiling are a detail that never ceases<br />
to make me smile. I’m delighted that all our human waste is managed on site by worms <strong>and</strong> reeds, that we create our own hot water <strong>and</strong> have rarely needed the underfloor heating on<br />
(even in extreme temperatures of minus 13 degrees - winter 2010).<br />
What was the most difficult aspect of the <strong>build</strong> ?<br />
<strong>The</strong> glass box <strong>design</strong> <strong>and</strong> installation.<br />
Huge glass windows crane <strong>and</strong> winds<br />
Please provide examples of courtesy <strong>and</strong> considerations shown by the <strong>build</strong>er <strong>and</strong> their team during the project:<br />
<strong>The</strong> <strong>build</strong>er was highly supportive throughout the <strong>build</strong> stepping in to support us in the initial planning stages when our architect ab<strong>and</strong>oned us at the first sniff of defeat. <strong>The</strong> <strong>build</strong>er advised<br />
us on eco products <strong>and</strong> went to great lengths to exp<strong>and</strong> his own knowledge on existing products. <strong>The</strong> <strong>build</strong>er was excellent at managing site visitors whilst focusing on <strong>build</strong> aims<br />
<strong>and</strong> timescales. He coped with extensive involvement from the client <strong>and</strong> managed our expectations <strong>and</strong> our amendments to the brief in a diplomatic but open fashion.<br />
<strong>The</strong> <strong>build</strong>er <strong>and</strong> his team implemented a courteous <strong>build</strong>er policy.<br />
In no more than 250 words please state why you think your <strong>build</strong>er should be “Master Builder of the Year 2010”<br />
Centurion Western Ltd took on a hugely ambitious project —to <strong>build</strong> the best UK example of a PassivHaus. We believe they have achieved this, unlike many examples of eco houses<br />
<strong>Moonstone</strong> is truly innovative <strong>and</strong> the eco features work in harmony with each other. <strong>The</strong>re has been no need to retrofit boilers or radiators—the brief has been met.<br />
To achieve this Centurion Western embarked on a huge learning curve with regard to innovative eco products whilst maintaining sensitivity to cost <strong>and</strong> practicalities of a family house.<br />
<strong>The</strong>y took on a lead role from planning to completion. <strong>The</strong> result is a property of 15,500 square feet of floor area (approx. the same size as 20 average 3 bedroom houses) that has a<br />
heat loss equivalent to less than half a st<strong>and</strong>ard three bedroom house. Typically a normal house has a heat loss of 55 kWh/m 2 /year, a German PassivHaus has a heat loss of 15kWh/m 2 /<br />
year <strong>and</strong> we have achieved 6.6kWh/m 2 /year.<br />
<strong>The</strong> innovative approach to this project attracted the attention of the media with the result that Discovery TV channel has filmed the whole <strong>build</strong> process <strong>and</strong> intends to transmit 4 halfhour<br />
programmes solely devoted to the construction of this state-of-the-art eco house.
<strong>Moonstone</strong> Room <strong>and</strong> Floor layouts<br />
Second floor: Lounge, bar <strong>and</strong> first floor office & roof terraces<br />
House is arranged over 7 floors—with two floors underground<br />
Basement level: Cinema, games room <strong>and</strong> Aquatron worm biogester<br />
First Floor: Kitchen, dining room, Gr<strong>and</strong> hall, garage & Oak pod<br />
Ground Floor: Bedrooms, library, Sauna & steam room, Swimming pool, Guest wing
Property is optimized for Passive solar gain - facing due South with large over hanging roofs for solar shading in the<br />
summer months, while the low winter sun penetrates the glazing <strong>and</strong> heats the huge thermal mass of the house.
All glazing is triple glazed, argon filled with U=0.7w/m2k Curved zinc roofs achieve U=0.10 w/m2k Underground basement achieves U=0.07 w/m2k All Cotswold stone was quarried on site with additional stone coming from a quarry only 6 miles away.<br />
<strong>Moonstone</strong> has an internal floor area of 1550 square metres arranged over 7 floors (the size of 20 average 3 bedroom houses), with a third of the <strong>build</strong>ing underground.<br />
Total Heat loss for property is just 6.6Kw less than half a modern 3 bedroom house.
44 square metres of TiSun flat plate solar collectors, provide 3000 litres of hot water storage to two innovative stratified Proclean water tanks. From early March to mid-November 2009, all hot water came from these panels- no<br />
additional heating was required. Other DHW heating comes from a NIBE heatpump connected to eight 70m deep boreholes <strong>and</strong> four slinky trenches with an additional 1.4Km of solar collecting pipe work.<br />
NO FOSSIL FUELS ARE CONSUMED ON OR OFF-SITE.
Site excavations <strong>and</strong> recycling / processing of 12,000 tonnes of quarried Cotswold stone <strong>and</strong> basement floor slab
Basement construction with Quadlock walls<br />
Ground floor beam installation
Water proof tanking to underground walls<br />
Structural steel framework to upper floors
Triple glazed windows <strong>and</strong> curtain walling.
Curved zinc roof cladding
Stone wall cladding <strong>and</strong> insulation
Oak frame installation
Cedar cladding
Superstructure completion
Ground source heat collectors: 1.5km of slinkies & 8No. 60m deep<br />
Underground ventilation earth pipes <strong>and</strong> insulation of underground pool <strong>and</strong>
Stone slip cladding <strong>and</strong> gabion baskets<br />
Underfloor heating & superflow liquid screed<br />
500m of Schluter underfloor heating pipes laid on top of a Bekotec heating system uses just a 25mm thick screed cf. a conventional<br />
70mm screed. This results in a very responsive heating system similar to a traditional radiator system. Input water is only at 34 degrees<br />
hence is optimised to work perfectly with a Heatpump.
Winter 2010: minus 13 degrees 18 inches of snow <strong>and</strong> still no need for heating
L<strong>and</strong>scaping & planting of wild flower meadows
<strong>The</strong> <strong>Moonstone</strong> <strong>Project</strong>