12.07.2015 Views

ASPIRE Spring 11 - Aspire - The Concrete Bridge Magazine

ASPIRE Spring 11 - Aspire - The Concrete Bridge Magazine

ASPIRE Spring 11 - Aspire - The Concrete Bridge Magazine

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Design and Construction of thei-10 Trinity River <strong>Bridge</strong>by Michael D. Hyzak, David P. Hohmann, David Collins,and Brian Merrill, Texas Department of TransportationBy February 20<strong>11</strong>, traffic was using thewestbound bridge. <strong>The</strong> total project was75% complete. All photos and drawings:Texas Department of Transportation.A combination ofconcrete solutions<strong>The</strong> Trinity River <strong>Bridge</strong> carries heavilytraveled I-10 over the Trinity Riverbetween Houston and Beaumont.<strong>The</strong> existing bridge built in the 1950sconsisted of twin structures with acombined roadway width of 52 ftfor two lanes in each direction. <strong>The</strong>existing bridge also had steep 4%grades to provide for 73 ft of navigationclearance. <strong>The</strong> main span consisted offracture-critical steel through-girdersystems. <strong>The</strong> existing bridge representeda choke point for the current trafficvolume of 47,000 vehicles/day. <strong>The</strong>roadway to the west had already beenwidened to three or more lanes in eachdirection, and similar work is beingdone to the east. For these reasons, theproject will provide welcome relief to avital route.Design SolutionAn original concept was conceivedusing twin continuous steel plate girderswith piers in the water for the mainriver crossing and precast, prestressedconcrete I-beams on the approaches.On the river crossing, this would havenecessitated a significant amount ofriver access for construction. In addition,construction and maintenance of thepier fender systems would be required.With a river opening of 400 ft andenvironmental and navigational reasonsto span the entire waterway, the mostviable option became a segmental boxgirder bridge built using the balancedcantilever method. To minimize projectcosts, the approach spans remainedprecast, prestressed concrete I-beams.With the resulting reduced lengthof segmental spans, a cast-in-placesegmental box girder cast with formtravelers was the preferred structure type.<strong>The</strong> project was let to contract in 2006.In February 20<strong>11</strong>, the project wasapproximately 75% complete. <strong>The</strong> newTrinity River <strong>Bridge</strong> has twin structures3636 ft long with approach spansof 72-in.-deep precast, prestressedconcrete I-beams supported onreinforced concrete bents using 18-in.-square, precast, prestressed concretepiles. Twin 990-ft-long segmentalbox girder units carry traffic over thenavigable Trinity River with 50 ft ofvertical clearance. Each cast-in-placeconcrete box girder unit consists of a450-ft-long main span flanked by two270-ft-long end spans. <strong>The</strong> girder depthvaries between 25 ft at the piers to 10.5ft at midspan. This span arrangementwith a back span-to-main span lengthratio of 0.60 required a nominal amountof shored construction at each end.This was required to avoid conflict withexisting multi-pile footing foundationsfrom the existing structure.<strong>The</strong> twin cell box girder structures are62 ft wide at the top slab level. <strong>The</strong> 60ft roadway width provides space forfour lanes plus shoulders for each ofthe twin structures, for a total of eightlanes of capacity. <strong>The</strong> project phasingdictated the complete construction ofthe westbound bridge. <strong>The</strong>n, all trafficwas rerouted onto the new structure topermit removal of the existing bridgeprofiletrinity river <strong>Bridge</strong>/ between houston and beaumont, texasbridge design Engineer: Texas Department of Transportation, <strong>Bridge</strong> Division, Austin, Tex.segmental construction engineer: Summit Engineering Group, Littleton, Colo.prime contractor: Williams Brothers, Houston Tex.precaster: Valley Prestress Products Inc., Eagle Lake, Tex.post-tensioning contractor: Williams Brothers, Houston, Tex.post-tensioning hardware and services: VSL, Grand Prairie, Tex.22 | <strong>ASPIRE</strong>, <strong>Spring</strong> 20<strong>11</strong>

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!