Pressure Protection of Inlet - A case study Kim ... - Aker Solutions

akersolutions.com
  • No tags were found...

Pressure Protection of Inlet - A case study Kim ... - Aker Solutions

Preferred partnerPressure Protection of Inlet – A Case StudyStavanger, 23.10.2012Kim Henry Kristiansen| Process Specialist EngineerAdvanced Process Control and Safety, Bergen© 2012 Aker Solutions Preferred partner


Background info■ Reservoir pressure reduced■ Maximize choke valve capacity to increase gas production■ Limiting factor Overpressure Protection■ Mal-operation of Riser ESV■ Pipeline - 12 inch, 15 km long■ Gas production (Fluid GOR: 8000-9000 Sm 3 /Sm 3 )© 2012 Aker Solutions Slide 2 6 November, 2012Preferred partner


System drawingMal operationMaximize capacity© 2012 Aker Solutions Slide 3 6 November, 2012Preferred partner


Modelling■ Model choice:■■Existing training simulatorK-Spice (software from Kongsberg Oil & Gas Technologies)■ Verification of model (significant part of the job)■■■■Piping and equipmentImportant valves: PSV, choke, PV (Pressure valves)Tuning of pipeline roughnessTuning of pressure drop in flare system© 2012 Aker Solutions Slide 4 6 November, 2012Preferred partner


Accept critera – Allowable overpressure■ Design code BS 5500 (all vessels)■ MAAP Design pressure + 10 %■ EN13445 can be used for “Exceptional load cases”■■FEM analysisCan allow for pressures up to test pressure■ Inlet Separator■■MAAP = 80 + 8 = 88 bargTest Pressure = 1.5 x Design Pressure = 120 barg© 2012 Aker Solutions Slide 5 6 November, 2012Preferred partner


Test PressuresTest Pressure =1.5 x Design Pressure =120 bargTest Pressure =1.25 x Design Pressure =100 barg© 2012 Aker Solutions Slide 6 6 November, 2012Preferred partner


Accept criteria – Allowable overpressure■ Inlet Separator and Pressure Vessels downstream■■MAAP chosen due to time constraints in the projectTo allow for pressures above MAAP FEM analysis on 8 vesselsneeded.■ HP KOD■■■EN13445 already appliedTest Pressure: 9.6 bargPiping on outlet nozzle only tested to 9.2 barg.© 2012 Aker Solutions Slide 7 6 November, 2012Preferred partner


Analysis performed (through Dynamic Simulations)■ Primary overpressure protection■ Secondary overpressure protection (PSV capacity)■ Highest flare load■ Reaction Forces (Rho*v2) Evaluation of pipe supports© 2012 Aker Solutions Slide 8 6 November, 2012Preferred partner


Analysis - summary■ Secondary Barrier Test■■Single Source Scenario (Separator not in operation, outlets closed)■ Cv = 2x108■ Results very sensitive to PSV characteristicAdditional Source Scenario (Separator in operation)■ Cv = 2x108 with limited gas production (background production)■ Decision to apply administrative control: Operational procedures andmessages on operator screens in CCR■ NB: If administrative control fails Pressure should not exceed TestPressures■ Max Flare Load■ Cv = 2x90■ Turns out to be limiting for choke capacity!!!■ Results very sensitive to control parameters for Pressure Valves (PV)■ Continue with existing control parameters■ Control parameters must not be changed without performing new analysis© 2012 Aker Solutions Slide 9 6 November, 2012Preferred partner


Secondary Barrier Test – Single Source Scenario• No primary pressure barrier• No background production• No Additional flaring• No compressor tripClosedIn-activeClosed© 2012 Aker Solutions Slide 10 6 November, 2012Preferred partner


Single source scenario■ According to existing design documentation Single sourcescenario probably limiting for choke valve capacity Our startingpoint for the analysis■ Pressure in separator Very sensitive to PSV characteristic■ No exact characteristic available from manufacturer■■■Pop action at 2-3 % overpressureFull flow capacity at 10 % overpressureBlow down 15% - 25% (Percentage below set point pressure. Valvecloses at this pressure)© 2012 Aker Solutions Slide 11 6 November, 2012Preferred partner


Percentage Lift [%]Possible PSV characteristics100Characteristic A, B og C90807060Cv=2x113Chosen characteristic(in agreement with customer)Cv=2x905040Cv=2x108Kar. A - OpeningKar. B - OpeningKar. C - Opening302010090 95 100 105 110 115 120Pressure (percentage of set point) [%]© 2012 Aker Solutions Slide 12 6 November, 2012Preferred partner


Percentage Lift [%]Chosen PSV characteristicPSV Characteristic1009080Designed for liquid and vapour.Typical when in gas service:- Pop action- Large blow down percentage7060Pop to 90 % only.Conservative for pressure5040OpeningClosing30201025 % BlowdownConservative for flare load070 75 80 85 90 95 100 105 110 115Pressure (percentage of set point) [%]© 2012 Aker Solutions Slide 13 6 November, 2012Preferred partner


Secondary Barrier Test – Additional Source Scenario• No primary pressure barrier• Background production• Compressor trip• Additional flaring• No help from control systemFreezeIn-activeIn-activeTripcompressorsBackgroundProductionFreezeIn-active© 2012 Aker Solutions Slide 14 6 November, 2012Preferred partner


Additional Source Scenario■ The Additional Source Scenario gives higher pressure build-up thanthe Single Source Scenario■ Reduction of gas production before start-up of pipeline would help■ Solution:■■Use administrative control to limit gas production before start-up.BUT! Pressure should not exceed test pressure if administrative controlfails.■ …No reduction of calculated choke Cv compared to the single sourcescenario © 2012 Aker Solutions Slide 15 6 November, 2012Preferred partner


Max Flare Load• No primary pressure barrier• Background production• Compressor trip• Additional flaring• Control System workingactiveactiveactiveTripcompressorsBackgroundProductionactiveactive© 2012 Aker Solutions Slide 16 6 November, 2012Preferred partner


Max Flare Load■ Assumes that administrative control have failed High gasproduction before incident■ Pressure build-up in the HP Flare system is limiting the choke valvecapacity !! Cv = 2x90■ Evaluation of valve capacity – PV on Inlet Separator■■■■30-40 % more capacity than neededIf PV goes fully open in short time – capacity reduction is a good ideaWith “slow” control parameters the extra 30-40% is not utilized.Conclusion: Control parameters more important than valve capacity© 2012 Aker Solutions Slide 17 6 November, 2012Preferred partner


Max Flare Load■ Evaluation of control parameters – PV’s■■■Keep existing “slow” control parametersChoosing wrong parameters could give too high pressures in HP FlareChange of PV control parameters should not be done without performingnew analysis.■ Some examples are shown on the next 3 slides■■■Example 1: Using existing control parameters for all 3 PV’s.Example 2: The Inlet Separator PV has got “fast” parameters.Example 3: The 2 PV’s on the glycol contactors have got “fast” controlparameters.© 2012 Aker Solutions Slide 18 6 November, 2012Preferred partner


Ex. 1: All 3 PV’s have “slow” contr. par. (Existing)10 6Acceptableoverpressure© 2012 Aker Solutions Slide 19 6 November, 2012Preferred partner


Ex. 2: PV on Inlet Separator has fast contr. par.Could helpreducing PVcapacity10 6Unacceptableoverpressure!© 2012 Aker Solutions Slide 20 6 November, 2012Preferred partner


Ex. 3: PV’s on Contactors have “fast” contr. par.10 6Unacceptableoverpressure!© 2012 Aker Solutions Slide 21 6 November, 2012Preferred partner


Main conclusions / Lessons learned■ Achievement: Choke capacity increased by 50%■ Initial assumption was wrong: The limiting scenario was not thesingle source scenario.■ Thorough evaluation of the accept criteria and design basis are ofhigh importance.■ Perform sensitivity studies. Surprising dynamic effects are oftenrevealed.■ PV Control Parameters and the PSV characteristic are importantfactors and should not be underestimated.© 2012 Aker Solutions Slide 22 6 November, 2012Preferred partner


Copyright and disclaimerCopyrightCopyright of all published material including photographs, drawings and images in this document remains vested in Aker Solutions andthird party contributors as appropriate. Accordingly, neither the whole nor any part of this document shall be reproduced in any form norused in any manner without express prior permission and applicable acknowledgements. No trademark, copyright or other notice shallbe altered or removed from any reproduction.DisclaimerThis Presentation includes and is based, inter alia, on forward-looking information and statements that are subject to risks anduncertainties that could cause actual results to differ. These statements and this Presentation are based on current expectations,estimates and projections about global economic conditions, the economic conditions of the regions and industries that are majormarkets for Aker Solutions ASA and Aker Solutions ASA’s (including subsidiaries and affiliates) lines of business. These expectations,estimates and projections are generally identifiable by statements containing words such as “expects”, “believes”, “estimates” or similarexpressions. Important factors that could cause actual results to differ materially from those expectations include, among others,economic and market conditions in the geographic areas and industries that are or will be major markets for Aker Solutions’ businesses,oil prices, market acceptance of new products and services, changes in governmental regulations, interest rates, fluctuations in currencyexchange rates and such other factors as may be discussed from time to time in the Presentation. Although Aker Solutions ASA believesthat its expectations and the Presentation are based upon reasonable assumptions, it can give no assurance that those expectations willbe achieved or that the actual results will be as set out in the Presentation. Aker Solutions ASA is making no representation or warranty,expressed or implied, as to the accuracy, reliability or completeness of the Presentation, and neither Aker Solutions ASA nor any of itsdirectors, officers or employees will have any liability to you or any other persons resulting from your use.Aker Solutions consists of many legally independent entities, constituting their own separate identities. Aker Solutions is used as thecommon brand or trade mark for most of these entities. In this presentation we may sometimes use “Aker Solutions”, “we” or “us” whenwe refer to Aker Solutions companies in general or where no useful purpose is served by identifying any particular Aker Solutionscompany.© 2012 Aker Solutions Slide 23 6 November, 2012Preferred partner

More magazines by this user
Similar magazines