Port Mann Highway 1 ProjectInter-Agency Environmental Review CommitteeJuly 6, 2011PMH1 – IAERC2011-07-06


Agenda2011 Instream Works – Where, What and WhenSegment 1-4Fraser Heights ConnectorGovernment Street Rapid Bus RampsUpdate on Off-site Habitat Compensation (WilsonFarm and Upper Brunette River)PMH1 – IAERC 2011-07-06


Instream Works — LocationsSegment 1PMH1 – IAERC2011-07-06


Instream Works — LocationsSegment 1PMH1 – IAERC2011-07-06


Segment 1Types of Instream WorksCompensation Tie ins• Gaglardi compensationphase 1 tie-in– PWS and RLF salvage• Burnaby Lake Tributariestie-in and completion– PWS and RLF salvage– Raptor monitoringPMH1 – IAERC2011-07-06


Segment 1Types of Instream WorksCompensation Tie ins• Deer Lake Brook tie-in and completion– RLF salvage requiredPMH1 – IAERC2011-07-06


Segment 1Types of Instream WorksCulvert ExtensionsPermanent culvert extensions:• Hwy 1 at Sprott: H1-131/144• Kensington at Thomas St: H1-NA• EB shoulder between Kensington andGaglardi: H1-126/113• Gaglardi W/B on-ramp: H1-102Majority of clearingconducted last year.Minimal salvagesrequired and to bedetermined by QEP.PMH1 – IAERC2011-07-06


Segment 1Types of Instream WorksCulvert ExtensionsTemporary culvert extension:• Gaglardi North—H1-99a– Cleared last year, salvages tobe determined by QEP– Extension to facilitate stonecolumn worksPMH1 – IAERC2011-07-06


Segment 1Priority Replacement Culvert E8• Tie-in to H1-121/122– Previously cleared.Salvages to bedetermined by QEPPMH1 – IAERC2011-07-06


Segment 1Types of Instream WorksDitch Relocations• EB shoulder near Gaglardi—H1-113/114– Rip-rap placement– Excavation for utility installation• South Gaglardi—H1-167– Ditch relocation for highwayextension– PWS and RLF salvagePMH1 – IAERC2011-07-06


Segment 1Types of Instream WorksDitch Relocations• East of Gaglardi—H1-119/120– Ditch relocation and utility protectionPMH1 – IAERC2011-07-06


Segment 1Types of Instream worksStill Creek Fish Diversion Removal• Fish diversion will beremoved from north andsouth banks of Still CreekPMH1 – IAERC2011-07-06


Instream Works Segment 1 Schedule:August 2011Segment 1PMH1 – IAERC2011-07-06


Segment 1Instream Works Segment 1 Schedule:September 2011PMH1 – IAERC2011-07-06


Segment 1Instream Works — Segment 1 SummaryType of Work Description/Location Watercourse IDStill Creek Bridge Still Creek at Willingdon Still CreekCulvert extension Sprott H1-144/131Culvert extension Kensington and Thomas St H1-NACompensation Deer Lake Brook H1-107/162Culvert extension E/B shoulder between Kensington and Gaglardi H1-112Rip rap placementE/B shoulder between Kensington and Gaglardi H1-113/114Utility installation E/B shoulder between Kensington and Gaglardi H1-113Culvert extension Between Kensington and Gaglardi H1-126Compensation Burnaby Lake Tributaries H1-115/116Ditch relocate and utility protection E/B Shoulder at GaglardiH1-120/119Culvert extension Gaglardi H1-102PMH1 – IAERC2011-07-06


Segment 1Instream Works — Segment 1 SummaryType of Work Description/Location Watercourse IDE-Culvert E8 H1-121/122Gravel removal Gaglardi Northwest H1-100Partial tie in Gaglardi compensation H1-123Ditch relocate Southeast Gaglardi H1-167Culvert extension Gaglardi North H1-99aPMH1 – IAERC2011-07-06


2011 In-stream WorksSegment 2CentralSediment andErosion controlalong H1-85south of TransCanada HighwayPMH1 – IAERC 2011-07-06


Instream Works — LocationsSegment 2PMH1 – IAERC2011-07-06


Instream Works — LocationsSegment 2PMH1 – IAERC2011-07-06


Instream Works — LocationsSegment 2PMH1 – IAERC2011-07-06


Instream Works — LocationsSegment 2PMH1 – IAERC2011-07-06


Instream Works — LocationsSegment 2PMH1 – IAERC2011-07-06


Segment 2Instream Works—LocationsPMH1 – IAERC2011-07-06


Instream Works — LocationsSegment 2PMH1 – IAERC2011-07-06


Segment 2Types of Instream WorksPriority Culvert InstallationPMH1 – IAERC2011-07-06


Types of Instream WorksHeadwall ConstructionSegment 2PMH1 – IAERC2011-07-06


Segment 2Types of Instream WorksCompensation HabitatPMH1 – IAERC2011-07-06


Segment 2Types of Instream WorksCulvert Installation and ExtensionPMH1 – IAERC2011-07-06


Segment 2Types of Instream WorksCulvert Outlets and Tie-insPMH1 – IAERC2011-07-06


Segment 2Types of Instream WorksGreen wall / MSE ConstructionPMH1 – IAERC2011-07-06


Segment 2Instream Works — Segment 2 Summary andScheduleArea: Activity: Watercourse (s): Location: AnticipatedStart Date:Culvert Improvements x 2 –insert steel sleevesH1-70 and H1-65 and H1-74LHH between dogbone andunited interchangeAugust 15, 2011LHH east of thedogboneCulvert Installations – Outfall#29 areaH1-65 and H1-74 and H1-70 green ditchLHH between dogbone andunited interchangeAugust 1, 2011E23 Headwall ConstructionMundy CreekLHH EB east of UnitedInterchangeAugust 1, 2011PMH1 – IAERC 2011-07-06


Segment 2Instream Works — Segment 2 Summary andScheduleArea: Activity: Watercourse (s): Location: AnticipatedStart Date:Culvert DecommissionH1-63 and H1-62 and H1-64Under the dogbone from“Planet Ice” to Taft areaSeptember 1, 2011DogboneCulvert Installation –Galvanized PipeH1-68 and H1-65 Northeast Dogbone August 15, 2011Culvert Installations – Outfall41 & 46H1-66 and H1-67 and H1-63LHH at Northwest Dog bone September 1, 2011PMH1 – IAERC2011-07-06


Segment 2Instream Works — Segment 2 Summary andScheduleArea: Activity: Watercourse (s): Location: AnticipatedStart Date:Como Creek CompensationHabitat ConstructionComo CreekComo Creek South of CPRand north of UnitedAugust 1, 2011Temporary culvert removals H1-83West of the CPR overpass(1627)August 1, 2011Trans Canada South“Six-Pack” Culvert Extensions8353 Green WallContinuationComo CreekPopeye CreekSouth of TCH between KingEdward and Coleman RampSouth of TCH between KingEdward and Coleman RampEarly worksrequested - July 18thpending DFOapprovalEarly worksrequested - July 18thpending DFOapprovalE14 and E15 CulvertContinuationComo and Popeye CreeksSouth of TCH between KingEdward and Coleman RampEarly worksrequested - July 18thpending DFOapprovalPMH1 – IAERC2011-07-06


Segment 2Instream Works — Segment 2 Summary andScheduleArea: Activity: Watercourse (s): Location: AnticipatedStart Date:Temporary culvert removals H-197North of LHH in ColemanareaAugust 1, 2011LHH SchoolhouseareaGuide Sign Installation H1-199Head Wall installation,Temporary culvert removaland ditch tie-inLHH EB just west ofSchoolhouseAugust 15, 2011H1-200 Schoolhouse and LHH September 1, 2011PMH1 – IAERC 2011-07-06


Segment 2Instream Works — Segment 2 Summary andScheduleArea: Activity: Watercourse (s): Location: AnticipatedStart Date:BrunetteCulvert extensions H-193 / H1-Unknown / H-192aBrunette Interchange -SouthSeptember 1, 2011Nelson Creek Culvert Continuation - E13 Nelson CreekA north south lineimmediately west of“Home-Outfitters”August 13, 2011Under the Bridge“Pizza Hut” Culvert – CulvertTie InH1-59 East bank of H1-59 September 1, 2011Area 1B Stone Columns H1-59 Full length of H1-59TBD – awaiting finaldesignPMH1 – IAERC2011-07-06


Port Mann Bridge Construction UpdateSegment 3BridgeInsert Segmentupdated picture fromyour segment in thisspacePMH1 – IAERC 2011-07-06


Segment 3Segment 3 – Construction Works, SouthConstruction ofmain spanPile Installation (vibratory andimpact hammer) for backspan tie downConstruction of roadaccess for SFPRDisassembly andmobilization of TrussPMH1 – IAERC2011-07-06


Segment 3Segment 3 – Construction Works, SouthRed-tailed Hawk Nest• Returned to nest mid-march• No sign of disturbance duringconstruction works including useof impact hammer at pier S1.• Two juvenile hawks successfullyfledged from the nest in lateJune.• No further monitoring requiredPMH1 – IAERC2011-07-06


Segment 3Segment 3 – Construction Works, MarineConstruction of columns andpier tablesConstruction ofInstallation of piles (impactand vibratory hammer)stabilizersand mainspanPMH1 – IAERC2011-07-06


Segment 3Segment 3 – Construction Works, MarineOsprey Nest• Returned to nest mid-April• No sign of disturbanceduring construction works• Female is incubating• Continue to monitorPMH1 – IAERC2011-07-06


Segment 3Segment 3 – Construction Works, NorthMobilize and construction ofTrussErection of segmentsbetween Piers N15 andN8Construction of piersN7 to N9Completion of drilled shaftsPMH1 – IAERC2011-07-06


Segment 3Segment 3 – Construction Works, NorthHeron Rookery• Returned to the Rookery inlateMarch• No sign of disturbanceduring construction works,• Females and young havebeen observed in nests.• Further monitoring of theRookery required.PMH1 – IAERC2011-07-06


Segment 3 – Future Works• In-River works, i.e. removal ofsheet pile and cofferdam frame- November 2011Segment 3• No on-land in-stream worksplanned for 2011• Main span deck erection atpiers N1 and S1• Pile installation andconstruction of back span pilePMH1 – IAERCcap near pier S12011-07-06


2011 Instream WorksSegment 4EastPMH1 – IAERC 2011-07-06


Segment 4Segment 4 – 2011 Instream Work LocationsArea DescriptionWatercourse Name156 th St. to 160 th St. (Surrey) Guilford Brook Tributary (H1-28)156 th St. Underpass (Surrey) Guilford Brook Tributary (H1-44)160 th St. Interchange (Surrey) Upper Serpentine Tributary (H1-24)160 th St. to 168 th St. (Surrey) Meridian Creek (H1-22)Tynehead Drive (Surrey)Unnamed (H1-17, H1-20 & H1-21)176 th St. to GEC (Surrey) Leoran Brook (H1-12)184 th St. to 192 nd St. (Surrey) Unnamed (H1-08 & H1-08c)192 nd St. Overpass (Surrey) Bartesko Creek Tributary (H1-07)194 th St. Turnaround (Surrey) Bartesko Creek (H1-06)200 th St. Interchange (Langley) Latimer Creek (n/a)PMH1 – IAERC2011-07-06


Segment 4Segment 4–2011 Instream Works DescriptionCulvert Tie-ins Culverts were installed between 2009 to 2011. Locations: H1-44, H1-28, H1-24, H1-08, H1-08c, H1-07 & H1-06. Anticipated Schedule: August 8 th to August20 th Duration: approx 2 to 4 days (each). Work Description: channel construction &rip-rap detail. Majority of work will be done on night shift. Mitigation Measures: wildlife & fish salvages (if necessary); sump & pump to divert water aroundoperation; and ESC (e.g., ECBs, straw, hydroseed).PMH1 – IAERC2011-07-06


Segment 4Segment 4–2011 Instream Works DescriptionTynehead Drive (H1-17, H1-20 & H1-21) Anticipated Start: September 5 th . Duration: approx. 1 week. Work Description: Installation of three800 mm culverts under Tynehead Drivevia a cut and cover. Mitigation Measures: Wildlife salvage (No) & fish salvage(No); Sump and pump will be utilized toconvey water around the work site;and ESC (e.g., ECBs, straw, hydroseed).PMH1 – IAERC2011-07-06


Anticipated Start: August 8 th Duration: approx. 2 to 3 weeks. Work Description: The existing 800 mmculvert will be slip-lined with a smallerdiameter pipe (750 mm). Access roadswill have to be constructed on the bothsides of the Highway. Mitigation Measures: Wildlife salvage (RLF & PWS) & fishsalvage (No); A gravity fed flume will be used toconvey flows; and ESC (e.g., ECBs, straw, hydroseed).Segment 4Segment 4–2011 Instream Works DescriptionMeridian CreekPMH1 – IAERC2011-07-06


Segment 4Segment 4–2011 Instream Works DescriptionLeoran Brook (E30/31) Anticipated Start: August 1 st . Instream:Late September. Duration: approx. 6 to 8 weeks. Work Description: Cut & Cover andHorizontal Pile Driving methods will beutilized to install the 3000 mm culvert.Access will have to be prepared on bothsides of the Highway. Mitigation Measures: Wildlife salvage (PWS, RLF & OFS) &fish salvage (Yes); Water will flow through the existing 900mm culvert & temporary extension. ESC (e.g., ECBs, straw, hydroseed).PMH1 – IAERC2011-07-06


Anticipated Start: August 1 st . Instream: LateSeptember. Duration: approx. 6 to 8 weeks. Work Description: Cut & Cover andHorizontal Pile Driving methods will beutilized to install the 3000 mm culvert. Accesswill have to be prepared on both sides of theHighway. Mitigation Measures: Wildlife salvage (PWS, RLF & OFS) &fish salvage (Yes); Water will flow through the existing 1500mm culvert & temporary extension. ESC (e.g., ECBs, straw, hydroseed).Segment 4Segment 4–2011 Instream Works DescriptionLatimer Creek (E32)PMH1 – IAERC2011-07-06


FHC – Construction UpdateFraser Heights BridgeFraser Heights ConnectorPMH1 – IAERC2011-07-06


FHC – Construction UpdateFraser Heights BridgeFraser Heights ConnectorUp coming work:PMH1 – IAERC Completing Clean-out of Pier24N. Pour piles and cap for Pier24N. Begin pile driving P23S &P23N. Place girders between P25S& P26S. Stitch pour precast panelsbetween P25N & P27N. Phase 3 wildlife salvage –late summer2011-07-06


FHC – Construction UpdateFraser Heights ConnectorCN Access Temp WaterMain: Received DFO “Letter of NoObjection”; Fish and amphibian salvagecompleted; Temporary diversion aroundwork site; Retained a small foot printduring construction; and No water quality issuesobserved.PMH1 – IAERC2011-07-06