Segment 1

iaerc.pmh1.ca

Segment 1

Port Mann Highway 1 ProjectInter-Agency Environmental Review CommitteeJuly 25, 2012PMH1 –IAERC2012‐07‐25


Agenda PMH1 Management Plan and Permit Update Compensation Construction Schedule PMH1 Fish and Wildlife Effectiveness Monitoring Update PMH1 Segment Construction Updates – Land Segments 2012 Instream Works Priority Replacement Culvert Construction Status General Construction Schedule and Milestones Fraser Heights Connector Update Segment 3 Construction Update and Bridge DemoPMH1 –IAERC 2012‐07‐25


PMH1 Management PlansConstruction Environmental Management Plan Revision 07 issued on June 1, 2012 Review of the plan to ensure current and update wherenecessary Updated versions of all wildlife management plans (i.e.PWS, RLF, OFS, Raptor, and Heron Rookery). Update of emergency contact and response info Update references Update general schedulePMH1 –IAERC 2012‐07‐25


PMH1 Management PlansPMH1 Fisheries i Habitat Compensation – EffectivenessMonitoring Plan Revision 07 issued on June 20, 2012 Updated to reflect current DFO Authorization Updated reference site selection memo Defines representative sub sample of restoration sites to bemonitored and their monitoring requirements Specific to on-corridor constructed habitatsPMH1 –IAERC 2012‐07‐25


PMH1 Permits and Approval DFO Authorization i Amendment F – May 2012 Project Wide Water Act Order 12 – June 2012 Numerous standalone Water Act Approval amendments Segment specific Fish Salvage Permits (DFO and MoE) Effectiveness Monitoring fish salvage permits EAC Amendment #3 for Government St. Bus RampsPMH1 –IAERC 2012‐07‐25


PMH1 Permits and ApprovalsApproximate # of “Permits/Approvals” or “No Objections” As ofJanuary 31, 2012 (not including amendments)Segment Expired‐Superseded Active PermitsTotal PermitsPermitsProject Wide 9 10 19Segment 1 12 14 26Segment 2 30 17 47Segment 3 34 32 66Segment 4 10 12 22FHC 18 36 54Ancillary Sites 2 1 3Total 115 122 Approx ‐ 237PMH1 –IAERC 2012‐07‐25


PMH1 Compensation Construction Schedule Completed: Mundy Creek, Hjorth Creek, Deer Lake Brook,Burnaby Lake Tributaries, Como Creek, and planting alongBrunette River Projected Completion 2012: Kensington I/C, Cedar Creek,Brunette River Tributaries Projected Completion 2013: Willingdon Creek, BuenaVista/Gaglardi I/C Projected Completion 2014: Fraser River North Foreshore(Watercourse H1-59) including pump station upgradePMH1 –IAERC 2012‐07‐25


PMH1 Fisheries Compensation Monitoring QEP = Triton Environmental Consultants Year 1: Deer Lake Brook, Como Creek, Burnaby LakeTributaries, and planting along Brunette River Year 2: Mundy and Hjorth CreekPMH1 –IAERC 2012‐07‐25


PMH1 Fisheries Compensation MonitoringYear 1 results for Mundy and Hjorth Creek No construction or intrinsic deficiencies were identified at Mundyor Hjorth during first year of monitoring. Coho and Stickleback captured utilizing habitats at Mundy. Salmonids not captured at Hjorth and suspected to beattributable to downstream barrier at 104 Avenue road crossing. Desired effects being met and very optimistic of the habitatpotential as these compensation areas mature.PMH1 –IAERC 2012‐07‐25


PMH1 Wildlife Effectiveness Monitoring QEP = EBB Environmental Consultants Year 1: Hjorth Creek monitoring completed; Year 2 monitoringhas commenced. Projected completion for other habitats being monitored: 2013: Gaglardi Interchange - Buena Vista Creek 2014: Willingdon Interchange – Still Creek Projected completion for wildlife culverts being monitored: 2012: Como and Lubbocks CreekPMH1 –IAERC 2012‐07‐25


PMH1 Wildlife Effectiveness MonitoringPreliminary i Year 1 results for Hjorth Creek Three variables have indicated a significant change frombaseline:1) Increase and Dragonfly abundance2) Increase in native vegetation abundance3) Decrease in wildlife movement through culvert All other variables being monitored do not show signficantchange.PMH1 –IAERC 2012‐07‐25


PMH1 Wildlife Effectiveness MonitoringPreliminary i Year 1 results for Hjorth Creek With exception of wildlife passage through culverts at Hjorth thedesired effects are currently being met. Likely residual influence of construction affecting wildlifepassage through culverts: Take time for wildlife populations in area to re-establish Vegetation still needs to mature Takes time for wildlife to “learn” new passage ways but arecreatures of habitat and once learned will repeatedly use.PMH1 –IAERC 2012‐07‐25


PMH1 Wildlife Effectiveness Monitoring Monitoring report will be posted on the FTP site for sharing ofinformation once finalized Sharing of wildlife information or involvement in the wildlifemonitoring program – Coordinate with K/FPMH1 –IAERC 2012‐07‐25


Segment Construction UpdatesPMH1 –IAERC 2012‐07‐25


Segment 1WestPMH1 –IAERC 2012‐07‐25


Segment 1Instream Work – Still Creek at BoundaryStill Creek Priority Replacement CulvertPMH1 –IAERC2012‐07‐25


Segment 1Instream Work (Still Creek at Boundary)• Required salvages:– Fish and amphibian• Environmental Risks:– Concrete pours– ‘A’ watercourse• Challenges:– Confined space– Storm drains leading to culvertPMH1 –IAERC2012‐07‐25


Segment 1Instream Work (Still Creek at Boundary)— ScheduleAugustSeptember8/18/28/38/48/58/68/78/88/98/108/118/128/138/148/158/168/178/188/198/208/218/228/238/248/258/268/278/288/298/308/319/19/29/39/49/59/69/79/89/99/109/119/129/139/149/15UPSTREAM TIE‐IN (NEW CULVERT)DIVERT WATERELB SEGMENTSBUILD HEAD WALLDOWNSTREAM TIE‐IN (NEW CULVERT)DIVERT WATERELB SEGMENTSBUILD HEADWALLBAFFELS IN EXISTING CULVERTDIVERT WATERINSTALL BAFFELS IN 1INSTALL BAFFELS IN 2INSPECT FOR REPAIRSPMH1 –IAERC2012‐07‐25


Segment 1Instream Work – Still Creek at WillingdonStill Creek Bridge Demolition Stage 2PMH1 –IAERC2012‐07‐25


Segment 1Instream Work (Still Creek at Willingdon)• Required salvages– Fish and amphibian– RLF• Environmental Risks– ‘A’ watercourse– Demolition debris• Challenges– Traffic and tight work area– Highly public area– Nearby utilityPMH1 –IAERC2012‐07‐25


Segment 1Instream Work (Location) — ScheduleAugust September8/18/28/38/48/58/68/78/88/98/108/118/128/138/148/158/168/178/188/198/208/218/228/238/248/258/268/278/288/298/308/319/19/29/39/49/59/69/79/89/99/109/11WATER DIVERSIONMID & SOUTH BAYNORTH BAYREMOVE LIDSMID LIDSOUTH LIDNORTH LIDREMOVE INTERIOR WALLSSOUTH WALLNORTH WALLEARTHWORK SUPPORTMID BAYSOUTH BAYNORTH BAYPLACE GRAVElPMH1 –IAERC2012‐07‐25


Instream Work – H1-131 131 at SprottTemporary culvert removal and channelcompletionSegment 1PMH1 –IAERC2012‐07‐25


Instream Work (H1-131 131 at Sprott)• Required salvages– Fish and amphibian• Environmental Risks– A(0) watercourse• Challenges– Tight working areaSegment 1PMH1 –IAERC2012‐07‐25


Segment 1Instream Work – H1-N/A at KensingtonCulvert replacementPMH1 –IAERC2012‐07‐25


Segment 1Instream Work (H1-N/A at Kensington)• Required salvages– Fish and amphibianAugust8/18/28/38/48/58/68/78/88/98/10• Environmental Risks– A(0) watercourseDIVETR WATERSAW CUT ACDEMO CONCRETE CONNECTBETWEEN EXISITNG AND NEW• Challenges– Traffic– Subcontractor managementELBPAVEPMH1 –IAERC2012‐07‐25


Segment 1Instream Work – Kensington CompensationCompensation construction and hydraulic tie‐inPMH1 –IAERC2012‐07‐25


Segment 1Instream Work (Kensington Compensation)• Required salvages– Fish and amphibian– RLF• Environmental Risks– ‘A’ watercourse– Adjacent parkland• Challenges– Ground conditions– Highly public areaPMH1 –IAERC2012‐07‐25


Segment 1Instream Work – Cedar Creek CompensationCompensation construction and hydraulic tie‐inPMH1 –IAERC2012‐07‐25


Segment 1Instream Work (Cedar Creek Compensation)• Required salvages– Fish and amphibian– RLF– PWS• Environmental Risks– ‘A’ watercourse– Adjacent parkland• Challenges– Nearby utility– Box culvert installation– Highly ypublicareaPMH1 –IAERC2012‐07‐25


Segment 1Instream Work – Gaglardi CompensationCompensation construction and hydraulic tie‐inPMH1 –IAERC2012‐07‐25


Segment 1Instream Work (GaglardiCompensation)• Required salvages– Fish and amphibian– RLF– PWS• Environmental Risks– ‘A’ watercourse– Adjacent parkland– Multiple hydraulic connections• Challenges– Adjacent works– Large area– Nearby utilityPMH1 –IAERC2012‐07‐25


Segment 1Instream Work – Brunette River TributariesCompensationCompensation construction and hydraulic tie‐inPMH1 –IAERC2012‐07‐25


Segment 1Instream Work (Brunette River TributariesCompensation)• Required salvages– Fish and amphibian– RLF– PWS• Environmental Risks– ‘A’ watercourses– Proximity to Brunette River– Adjacent parkland– Concrete weir installation• Challenges– Nearby utility– Highly public areaPMH1 –IAERC2012‐07‐25


Segment 1Instream Work (Compensations) — ScheduleAugust September9/168/18/28/38/48/58/68/78/88/98/108/118/128/138/148/158/168/178/188/198/208/218/228/238/248/258/268/278/288/298/308888888888888888888888/319/19/29/39/49/59/69/79/89/99/109/119/129/139/149/15BRUNETTE : TIE ‐ IN 1TIE ‐ IN 2KENSINGTON: TIE ‐ IN 1TIE ‐ IN 2CEDAR CREEK: TIE ‐ IN 1TIE ‐ IN 2GAGLARDI: TIE ‐ IN 1TIE ‐ IN 2TIE ‐ IN 3PMH1 –IAERC2012‐07‐25


Segment 1Instream Work – Priority ReplacementCulverts: Burnaby LakePMH1 –IAERC2012‐07‐25


Segment 1Instream Work – Robert Burnaby Creek(H1-106) 106) Priority Replacement Culvert• Required salvages– Fish and amphibian– RLF– PWS• Environmental Risks– ‘A (0)’ watercourse– Adjacent parkland– Concrete grouting• Challenges– Traffic– Subcontractor managementPMH1 –IAERC2012‐07‐25


Segment 1Instream Work – Ramsey Creek (H1-105)105)Priority Replacement Culvert• Required salvages– Fish and amphibian– RLF– PWS• Environmental Risks– ‘A’ watercourse– Adjacent parkland– Concrete grouting• Challenges– Traffic– Subcontractor management– Nearby overhead utilityPMH1 –IAERC2012‐07‐25


Segment 1Instream Work – Osprey Creek (H1-103/118)103/118)Priority Replacement Culvert• Required salvages– Fish and amphibian– RLF– PWS• Environmental Risks– ‘A (0)’ watercourse– Adjacent parkland– Concrete grouting• Challenges– Traffic– Completion of Stage 1 construction– Nearby overhead utilityPMH1 –IAERC2012‐07‐25


Segment 1Instream Work – Cedar Creek (H1-119)119)Priority Replacement Culvert• Required salvages– Fish and amphibian– RLF– PWS• Environmental Risks– ‘A’ watercourse– Adjacent parkland– Concrete grouting• Challenges– Traffic– Subcontractor managementPMH1 –IAERC2012‐07‐25


Segment 1Instream Work (Priority ReplacementCulverts Burnaby Lake) — ScheduleAugustSeptember8/18/28/38/48/58/68/78/88/98/108/118/128/138/148/158/168/178/188/198/208/218/228/238/248/258/268/278/288/298/308/319/19/29/39/49/59/69/79/89/99/109/119/129/139/149/159/169/179/189/199/209/219/22ROBERT BURNABY CULVERTSTAGE 4NORTH TIE‐INSOUTH TIE‐INRAMSEY CREEK CULVERTSTAGE 4NORTH TIE‐INSOUTH TIE‐INOSPREY CREEK CULVERTSTAGE 4STAGE 1NORTH TIE‐INSOUTH TIE‐INCEDAR CREEK CULVERTSTAGE 4NORTH TIE‐INSOUTH TIE‐INTraffic FlipPMH1 –IAERC2012‐07‐25


Segment 1Priority Replacement Culvert ConstructionWatercourse Status Anticipated works in 2012Still Creek Stage 3 out of 4 Hydraulic tie‐in of new culvert, restoration of existingculvert and restoration plantingGuichon Creek (H1‐138) 138) Stage 2 complete Complete stage 3 out of 4Lubbocks Creek (H1‐110/128) Not started Complete stage 1Robert Burnaby Creek (H1‐115/106) Stage 3 out of 4 Hydraulic tie‐in and restoration plantingRamsey Creek (H1‐105) Stage 3 out of 4 Hydraulic tie‐in and restoration plantingOsprey Creek (H1‐103/118) Stage 3 out of 4 Hydraulic tie‐in and restoration plantingCedar Creek (H‐119) Stage 3 out of 4 Hydraulic tie‐in and restoration plantingTributary to Buena Vista H1‐121/122) Substantially complete Maintenance and installation of wildlife drift fencingTributary to Buena Vista (H1‐100) Not started Complete stage 1Buena Vista (H1‐99) Not started Complete stage 1Buena Vista (H1‐99/123) Not started Complete stage 1PMH1 –IAERC2012‐07‐25


Segment 1Segment 1 - General Construction Schedule andMilestonesWorkBoundary and BNSF2GrandviewWillingdon/Still CreekSprottKensingtonGaglardiBrunette/BNSF1Government StreetStatus•Commencement of Stage 3•Stage 2 demolition•On/off ramp works ongoing•Completion of median walls•TrafficT flip to east side of interchange•Demolition of Willingdon Overpass•Stage 2 construction•Demolition of Sprott overpass•Stage 2 construction•Completion of bridge structure•Ongoing work on approaches and on/off ramps•Completion of ground improvements•Completion of abutment walls•Pier work ongoing•Drilled shafts completed•BNSF1 girders placed July 2012•Brunette River girders scheduled for August 2012•Ongoing pier and abutment works•E/B completed•Traffic flip to south side of highway•Commencement of HOV ramps to city streetsPMH1 –IAERC2012‐07‐25


General Construction ti Schedule andMilestonesSegment 1PMH1 –IAERC2012‐07‐25


Segment 2Central – Brunette Interchange to Port Mann BridgePMH1 –IAERC 2012‐07‐25


Fish & Wildlife SalvagesSegment 2• No sensitive habitat to salvage for wildlife in 2012 fishwindow landward dwork areas:• Pacific Water Shrew• Red‐Legged Frog• Oregon forest Snail• Bird Surveys bi being conducted don an ongoing basis• Song Birds –– all brush cleared until July 31 st or QEP recommendation• Raptors –– none present on segment 2 at this time• Heron Rookery –– Was heavily monitored during 2012– Now inactive for seasonPMH1 –IAERC2012‐07‐25


• Only Fish andAmphibiansalvages will needto be conductedduring the 2012FW.• Conducted by QEPas per requiredcommitments andpermits.Fish & Wildlife Salvages


Scope of 2012 – Fish Window Work1. General Highway Construction ‐ Drainage Works2. Priority Replacement Culverts – Fish & WildlifePassage3. Culvert tDecommissioni4. Guide Sign and Light Bases5. Watercourse Restoration Planting


1. General Highway Construction ‐Drainage Works


Segment 2Work Locations and ScheduleWork TypeWatercourseKiewit-Flatiron /SubcontractorDrainage Installation / Tie‐in – Outfall #22 & 29 Dawes Hill Creek Tributary ‐ H1‐65 KFDrainage Installation / Tie‐in – Outfall #30 H1‐196 KFTemp pipe removal & Tie In Como Creek Tributary ‐ H1‐77 KFTemp pipe removal / Ditch Restoration / Tie In Como Creek Tributary ‐ H1‐81 & H1‐82 KFPMH1 –IAERC2012‐07‐25


Segment 2Instream Work: Drainage Upgrades at Outfall #22and #29• Lougheed Highway at eastern most portion ofSegment 2 / H1‐65PMH1 –IAERC2012‐07‐25


Segment 2Instream Work: Drainage Upgrade Outfall #30• Lougheed Highway at Schoolhouse Rd / H1‐196• Drainage upgrade and tie inPMH1 –IAERC2012‐07‐25


Instream Work: Temporary Pipe RemovalSegment 2• Between Coleman Ave. and King Edward St. / H1‐77• Removal of existing temporary pipe and tie inPMH1 –IAERC2012‐07‐25


Instream Work: Tie in H1-81, H1-82• Between Coleman Ave. and King Edward St.• Removal of temporary pipe• Tie in of H1‐81 and H1‐82Segment 2PMH1 –IAERC2012‐07‐25


2. Priority Replacement Culverts – Fish& Wildlife Passage


Segment 2Priority Replacement Culvert ConstructionPriority Replacement Culvert Status ExpectationsE‐13 – Nelson Creek Finish installation and tie‐ins To be completed during 2012 FWE‐14 –Como Creek Tie in to “six‐pack” and Wildlife Crossing To be completed during 2012 FWE‐15 – Popeye py Creek Completed in 2011 FW Functioning as intendedE‐15a ‐ Popeye Creek Finish installation and tie‐in To be completed during 2012 FWE‐16 –Dawes Hill Creek On hold –NotStarted No work scheduled for 2012E‐18 –Dawes Hill Creek On hold – Requires Tie‐in No work scheduled for 2012E‐19 –Dawes Hill Creek On hold – Requires Tie‐in No work scheduled for 2012E‐23 – Mundy Creek Hydrodynamic Adjustments To be completed during 2012 FWPMH1 –IAERC2012‐07‐25


Fish/Wildlife Culvert - E13Nelson Creek & Associated Works• King Edward St. at Hwy 1 / H1‐79, H1‐85, H1‐80, H1‐84• Temp bridge removal – Woolridge• CPR bridge Construction• C114 Hydro duct Installation• Completion of E‐13• Tie in of H1‐79,H1‐85 and H1‐80Segment 2PMH1 –IAERC2012‐07‐25


Fish/Wildlife Culvert - E14Como CreekSegment 2• Between Coleman Ave. and King Edward St. / H1‐76• Tie in of “six pack” to Como Creek at E‐14n• Build up of culvert inlet headwall / Wildlife CulvertPMH1 –IAERC2012‐07‐25


Fish/Wildlife Culvert - E15aPopeye Creek & Associated Utility CrossingSegment 2• Coleman Avenue on‐ramp / H1‐197 & Popeye Creek• Remove temporary pipe• Installation of headwall at Outfall #37• Completion of E‐15a• Install Utilities for Tolling StationPMH1 –IAERC2012‐07‐25


Fish/Wildlife Culvert – E23Mundy Creek• Lougheed Highway at United Blvd / H1‐72Segment 2• Ditch area to be re‐graded to allow for settlementPMH1 –IAERC2012‐07‐25


3. Culvert tDecommissioniSegment 2Work TypeWork Locations and ScheduleWatercourseKiewit-Flatiron /SubcontractorCulvert abandonment / Fill Dawes Hill Creek Tributary KF• Dawes Hill CreekTributary H1‐62 /H1‐64• Decommissioningof culvert andbackfilling of ditchon east and west ofculvertPMH1 –IAERC2012‐07‐25


4. Guide Sign and Light BasesWork Locations and ScheduleWork TypeWatercourseKiewit-Flatiron /SubcontractorLight base Removal Como Creek Tributary –H1‐200 KFGuide Sign Upgrade H1‐75 KF


Segment 2Light Base Removal• Lougheed Hwy East Bound at Woolridge St / H1‐200• Removal of existing light basePMH1 –IAERC2012‐07‐25


Segment 2Guide Sign 1959 Upgrade• Between Coleman Ave. and King Edward St. / H1‐75• Upgrade of guide signPMH1 –IAERC2012‐07‐25


5. Watercourse Restoration Planting


Work TypeWork Locations and ScheduleWatercourseKiewit-Flatiron /SubcontractorRestoration ti Planting Como Creek kTib Tributary – H1‐77 SUB


H1‐77


Segment 2Segment 2 - General Construction ti ScheduleWorkStatusWorkStatusConstruction of Structure 5902Construction of Structure 5910Construction of Structure 5912Construction of Structure 5904Construction of Structure 1627 –Phase 3Construction of Structure 5913Construction of Structure 5905OngoingOngoingOngoingOngoingOngoingCompleted – WaterproofingongoingOngoingConstruction of Bicycle pathsand bridge at C.H. InterchangeStarted in Spring of 2012Construction of E 16 Anticipated in 2013 FWDemolition of DogboneAnticipated in September ofOverpasses2012Demolition of Mary Hill Bridge Anticipated in August of 2012Stone columns at MH Bypassand UnitedOngoingCIP wall 8342Ongoing8340 Wall Completed – summer 2012Construction of Structure 5906Ongoing8348 MSE Wall OngoingConstruction of Structure 5908Anticipated Start – September2012LHH Drainage workOngoingConstruction of Structure 5909and embankment5909 – Ongoing, Embankment –Waiting on settlementTemporary pipe removal, ditchrestoration, tie ins, plantingAnticipated completion – 2014FWPMH1 –IAERC2012‐07‐25


Segment 2 – Traffic Detours / ClosuresSegment 2Name: Description Implementation DateDetour ‐39B Minor LHH Lane Shift on LHH‐ WB Week of July 23 rdDetour ‐ Stage 5 MHB to United Boulevard July 27 th to 29 thUnited EB Squeeze @ MHBBrunette Interchange Lane ShiftsReduce 4 EB Lanes @ United to EB 2 Lanes forManhole and Utility InstallTypical lane shifts to facilitate drainage culvertcrossingAug 3 rd ‐5 thAug 10 th – 12thAug 17 th – 19 thAug 24 th –26 thAug 10 th to 24 thWoolridge Closure Close from Home Outfit. To King Ed Oct 1 st to 7 thDetour ‐26D Putting WB Exit 44 over 5906 SeptemberDetour ‐ Stage 9 Putting EB LHH under CPR Bridge SeptemberWeekend Warrior Putting WB LHH on new fly‐over to EB HWY 1 SeptemberPMH1 –IAERC2012‐07‐25


Segment 3Port Mann BridgePMH1 –IAERC 2012‐07‐25


Segment 3Segment 3 – Construction Works Update, SouthConstruction of main span, incl. fascia Concrete finishingpanels, pylon roof, parapet construction,ti works, paving of theand erection of precast panels and steel south approach deckgirders, installation of drainage pipe,(pier S2 to S10)sidewalksPMH1 –IAERC 2012‐07‐25


Segment 3 – Construction Works, SouthWildlife Update - Red-tailedHawk Nest• Returned to nest mid-march• No sign of disturbance duringconstruction works• Monitored as per the RaptorNest Management Plan• Successfully fledged – nowinactiveSegment 3PMH1 –IAERC 2012‐07‐25


Segment 3 – Construction Works Update,MarineSegment 3Balance cantileversegment erection, piersN5 to N2, removal ofcofferdams,Erection of main span deck(rebar, form work, concretepours, cable stay installation)PMH1 –IAERC 2012‐07‐25


Segment 3 – Construction Works Update,MarineWildlife Update – Osprey Nest• Returned to nest mid-May• No sign of disturbance due toconstruction works• Monitored as per RaptorNest Management Plan• Inactive – no fledglings, notsuccessfulSegment 3PMH1 –IAERC 2012‐07‐25


Segment 3 – Construction Works, NorthSegment 3Paving works,N15 – N6Parapet construction(rebar and form work,concrete pours),Drainage pipe installationand concrete finishingworksPMH1 –IAERC 2011‐07‐06


Segment 3 – Construction Works, NorthWildlife Update – Heron Rookery• Returned to rookery in March• No sign of disturbance due toconstruction works• Monitored rearing successduring breeding season withfledging of young• Now inactive as of July 18 th• Successful breeding seasonSegment 3PMH1 –IAERC 2011‐07‐06


Segment 3 – In stream worksSummer 2012:Segment 3• Start removing finger trestles(piers N5, N4, N3, N2 and N1)• PMBD – re-using trestle pile• No on-land Segment 3 worksPMH1 –IAERC 2011‐07‐06


Segment 3Priority Replacement Culvert Construction• Bon Accord Creek, E26 and CN Ditch, E25(Segment 4 works)E25E26PMH1 –IAERC2012‐07‐25


Segment 3General Construction ti Schedule andMilestonesShort Term:• Complete paving across bridge• Complete miscellaneous items: concrete finishingworks, tower crane disassembly, balancecantilever segment erection (phase I), parapetwork etc.Fll2012 Fall and beyond:• Traffic EB/WB on new PMB – December 1st• Commencement of demolition, start of Phase II(deconstruction of north approach of old PMB)PMH1 –IAERC2012‐07‐25


Segment 3Compensation Works• Because of Port Mann Bridge Demolitioncompensation works for both north and southsides, such as:– Bon Accord Creek– CN Ditch (H1‐179)– H1‐59won’t be completed until 2014PMH1 –IAERC2012‐07‐25


Port Mann Bridge Demolition (PMBD)Segment 3N9NDemolition of Port MannBridge (Piers 9N to 5S)5SDemolition of north andsouth abutments apart ofPMH1 Project (Phase II)PMH1 –IAERC2012‐07‐25


NORTH APPROACHPort Mann Bridge DemolitionMAIN SPAN BRIDGE and SideSpan ApproachesSegment 39N1N1S5SSOUTH APPROACHPMH1 –IAERC2012‐07‐25


Segment 3PMBD - Methods• Access• Removingsuperstructure(concrete deck andsteel)• Removingsubstructure(concrete piers)1N1SPMH1 –IAERC2012‐07‐25


PMBD Methods: Marine AccessSegment 3TrestleExcavationPMH1 –IAERC2012‐07‐25


Segment 3PMBD Methods: South Approach AccessClearing/grubbingCulvertInstallation –Bon AccordCreekPMH1 –IAERC2012‐07‐25


PMBD Methods: SuperstructureSegment 3Superstructure (bridge deck, steel girders)• removal of roadside barrier, deck removal will start frompier 2N working away from main span– Asphalt deck;– Steel railings;– Barriers; and– Lamp stands, utilities etc.• Asphalt milling• Install containments• Saw cutting, slab lbsaw, hoe ramming• Cut steel into manageable piecesPMH1 –IAERC2012‐07‐25


PMBD Methods: SubstructureSubstructure (Piers)Segment 3• Saw cutting concrete into manageable sizes,hoisted onto barges or trucks,• On‐land pier will be removed to 0.5 metersbelow ground surface• Marine –pier cap, column and pedestal – allremoved to pile capPMH1 –IAERC2012‐07‐25


ACTIVITYPMBD PermitsACT/REGULATIONPERMIT TYPESegment 3AGENCYIn river worksIn river worksFederal FisheriesActProvincial WaterActDFO 35 (2)AuthorizationWater Act Section 9ApprovalDFOMoEIn river works Navigable Navigable Waters Transportwaters Act Protection Act Permit CanadaIn river works,marine excavationCanada MarineActProject PermitPMVDemolition Wildlife Act Wildlife Permit MoEDike MaintenanceActDikeMaintenanceActInspector of Dikes MoE –Inspector ofDikesPMH1 –IAERC2012‐07‐25


Segment 3PMBD Permits• CEAA Letter no longer required• Submit to agencies in early August– DF0– MoE (Water Act Section 9)– PMV– Nav Waters• Approvals early OctoberPMH1 –IAERC2012‐07‐25


PMBD Schedule• Fall 2012 (start with marine access) – 2015Segment 3– Substructure works below water June 15 ‐ February28 (pile driving, excavation, and removal ofpedestals)– Start on north approach at pier 2N followed bysouth approach– Dredging from July 15 –March 1– On‐land in stream works (Bon Accord Creek)August 1 – September 30PMH1 –IAERC2012‐07‐25


Segment 4EastPMH1 –IAERC 2012‐07‐25


Segment 4Instream Work - Location• Bon Accord Creek – E25 & E26• Leoran Brook – E30 & E31• Latimer Creek –E32• 104 th Ave DitchPMH1 –IAERC2012‐07‐25


Instream Work (Bon Accord Creek)Segment 4Bon Accord– 1,663 m2 (Instream) & 4,854 m2 (Riparian)PMH1 –IAERC2012‐07‐25


Instream Work (Bon Accord Creek)• Work: Installation ofa 14 m (L) concretebox culvert.• Start Date: August 1 st• Duration: 2 weeks• Salvages:PWS/RLF/SBN/Fish• Restoration Work:Sept 2012Segment 4PMH1 –IAERC2012‐07‐25


Instream Work (Leoran Brook)Segment 4Leoran Brook – 125 m2 (Instream) & 2,345 m2 (Riparian)PMH1 –IAERC2012‐07‐25


Instream Work (Leoran Brook)• Work: Installationtiof a 119 msteel/CSP culvert(3000 mm).• Hydraulic Tie‐in:Sept 15 th• Duration: 1 day• Salvages: RLF/Fish• Restoration Work:Sept 2012Segment 4PMH1 –IAERC2012‐07‐25


Instream Work (Latimer Creek)Segment 4Lti Latimer Creek – 213 m2 (Instream) & 2,338 m2 (Riparian) i PMH1 –IAERC2012‐07‐25


Instream Work (Latimer Creek)• Work: Installation of a 121 m steel/CSPculvert (3000mm)• Hydraulic Tie‐in: July 16 th• Duration: 1 day• Salvages: RLF/Fish/SBN• Restoration ti Work: Sept t2012Segment 4PMH1 –IAERC2012‐07‐25


Instream Work (Latimer Creek)Segment 4PMH1 –IAERC2012‐07‐25


Instream Work (104 th Ave Ditch)Segment 4104 th Ave Ditch – 251 m2 (Instream) & 4,3519 m2 (Riparian) i PMH1 –IAERC2012‐07‐25


Instream Work (104 th Ave Ditch)• Work: Installation oftwo 36 m (L) CSPculverts (1400 mm)• Start Date: July 24 th• Duration: 2 weeks• Salvages:RLF/SBN/Fish• Restoration Work:Sept 2012Segment 4PMH1 –IAERC2012‐07‐25


General Construction ti Schedule andMilestones• Aug 1 st – 176 th St I/C Completed• Aug 21 st – 160 th St I/C Completed• Sept 15 th – Landscaping (100,000 m2)• Oct 30 th – 156 th St I/C (8 Lane) CompletedSegment 4• Nov 7 th –E2 (168 th St to 200 th St) Completed• Nov 21 st – PMB to 152 nd St (8 Lane) CompletedPMH1 –IAERC2012‐07‐25


Fraser Heights ConnectorFHC SummaryPMH1 –IAERC2012‐07‐25


General Construction Schedule andMilestones• Aug 15 th –CN Access Completed• Aug 28 th – FHB Completed• Sept 15 th –Start Restoration Work• Nov 2 nd – FHC CompletedSegment 4PMH1 –IAERC2012‐07‐25