<strong>Segment</strong> 1<strong>Segment</strong> 1 - General Construction Schedule andMilestonesWorkBoundary and BNSF2GrandviewWillingdon/Still CreekSprottKensingtonGaglardiBrunette/BNSF1Government StreetStatus•Commencement of Stage 3•Stage 2 demolition•On/off ramp works ongoing•Completion of median walls•TrafficT flip to east side of interchange•Demolition of Willingdon Overpass•Stage 2 construction•Demolition of Sprott overpass•Stage 2 construction•Completion of bridge structure•Ongoing work on approaches and on/off ramps•Completion of ground improvements•Completion of abutment walls•Pier work ongoing•Drilled shafts completed•BNSF1 girders placed July 2012•Brunette River girders scheduled for August 2012•Ongoing pier and abutment works•E/B completed•Traffic flip to south side of highway•Commencement of HOV ramps to city streetsPMH1 –IAERC2012‐07‐25