<strong>Wimbledon</strong> – operational requirements<br />

<strong>Crossrail</strong> 2 Requirements:<br />

• Operate 30 trains per hour in the Central Operating Section (COS)<br />

• Ability to run a 20 trains per hour service in the COS during disruption on NR<br />

network<br />

• Ability to start the service at TCR at 5.45 AM<br />

• Maintain trains efficiently<br />

• Serve Kingston, Epsom and Chessington Branch Lines<br />

• Keep existing railways operational throughout the construction works<br />

• Provide a <strong>station</strong> at <strong>Wimbledon</strong> and Raynes Park<br />

These requirements give rise to the following<br />

• Turn back sidings for 10 trains per hour near the south end of the COS<br />

• Train maintenance depot and stabling near the south end of the COS<br />

• Four platforms at the end of the COS (currently <strong>Wimbledon</strong>)<br />

• 6-tracking between New Malden and the 6 end of the COS