Views
4 months ago

galvis

Water treatment

MSF system can then be

MSF system can then be calculated on the basis of the filtration area (A). Tables 5.2 shows the main construction quantities for the different MSF component items built in reinforced concrete. Similar models can be produced for brickwork. In some hilly areas the quantities may be larger, particularly if construction in terraces is needed. The cost of the plants can be established by multiplying the quantities of the different construction items with their respective unit cost. The total sum of these items (table 5.2), plus the cost of the valves, represents around 80 percent of the cost and needs to be multiplied by 1.25 (since 100/80 equals 1.25) to estimate the total construction cost. This does not include however, costs of the water intake, transmission main or water storage and distribution. Table 5.2. Models to estimate the construction quantities of main components of MSF systems in reinforced concrete. Treatment capacity in the range of 2 to 25 ls -1 . Component UGFS (2) UGFS (3) 24

Table 5.3. Time required for conducting daily and periodic O&M tasks in MSF systems. Time is shown in full time equivalents (FTE) (1, 2) Capacity (ls -1 ) MSF Alternative 1 5 10 20 DyGF + SSF 0.2 0.4 0.7 1.0 DyGF + UGFL + SSF 0.5 0.6 0.9 1.3 DyGF + UGFS (2) + SSF 0.6 0.8 1.0 1.4 DyGF + FGDS (3) + SSF 0.7 0.9 1.2 1.5 (1) 1 FTE = time equivalent of a full-time operator. (2) Daily, periodic, and occasional activities have been considered in chapters 3 and 4. They are also described in Galvis et al (1998) and Vargas et al (1999). Table 5.4. Time required for implementing occasional O&M activities of MSF plants in fulltime equivalents (FTE). MSF Alternative Capacity (ls -1 ) 1 5 10 20 DyGF + SSF 0.01 0.06 0.11 0.22 DyGF + UGFL + SSF 0.02 0.10 0.21 0.41 DyGF + UGFS (2) + SSF 0.03 0.15 0.30 0.60 DyGF + UGFS (3) + SSF 0.04 0.20 0.40 0.79 The values in this table relate to systems with a life span extending over 10 years, as most of the occasional activities occur between a few times per year to once every five years approx. 5.6.3. Administration The time required for administrative activities is estimated at 0.3 to 0.5 FTE per month. The activities included supervision, planning, user relations, purchases, payments and meetings with sector agencies. In the five treatment plants in Cauca Valley with plant capacities between 7 and 15 ls -1 serving between 95 and 545 households (El Retiro, Cañas Gordas, Ceylan, La Marina and La Sirena), the time required for the administration of these MSF systems was in the order of 0.3 to 0.5 FTE. The estimate is assumed to be valid for plant capacities between 2 and 25 ls -1 with the lower level applying to the smaller systems. 5.6.4 Estimating overall cost The estimation of total direct construction cost can be based on tables such as 5.2 which include only items representing around 80% of direct costs, and the local unit costs. Multiply this partial direct cost by 1.25 to reach the total direct construction cost. To obtain the overall investment cost for the treatment plant, other costs need to be added to the total direct costs, such as insurance, and profit, administration and contingencies (PAC). In Colombia the value for PAC varies between 20 and 30 percent. Estimation of total staff time in FTEs per year for operation, maintenance and administration can be reached by using tables 5.3 and 5.4 and adding another 0.3 to 0.5 FTE for administration costs. The sum needs to be multiplied by the average staff’s salary and by a factor of 1.15 to obtain the total recurrent cost, as staffs make up 85 percent of the recurrent cost approx. 184

Pall Aria™ AP-Series Packaged Water Treatment ... - Pall Corporation
Water Treatment Improvements and Plant Capacity ... - Ohiowater.org
The best solutions in water treatment - Istobal
Council Bluffs Water Works South Water Treatment Plant – Planning ...
Technical Advances in the Treatment of Water and Air for ... - IAAPA
Weatherford in Waste Water Treatment (WWT)
Drinking Water Treatment for Small Communities - P2 InfoHouse
P01073 ZTF - ZEKS Compressed Air Solutions
Freshwater-Aquarium-Manual
Systematic Approach to Water Treatment Plant ... - Ohiowater.org
Water treatment for the aquaculture industry
Water Quality Report - 2010 - Presidio Trust
High Heat Filtration with Industrial Air Filter Bags
advanced water treatment and recycling processes - International ...
Advances in Water Treatment and Enviromental Management
Comline - First for Filters Catalogue_web.compressed
Artificial ground-water recharge at Peoria, Illinois. - Illinois State ...
Advanced oxidation process treatment of membrane filtration ...
waste water treatment at the Hilltop Brewery - Great Lakes Water ...
Screen Filtration for Ballast Water Treatment Applications - Cross ...
Wastewater Treatment Options - Saudi Arabian Water Environment ...
PDF (1.43 MB) - P84.com
end of 2010_sales_catalog_12x18.indd - Ultrafryer Systems
Download Brochure - Excalibur Water Systems
Activated Carbon in Potable Water Treatment - Norit
R.E. Prescott Company Water Treatment Catalog
(DBP) Violations at Small Water Treatment Systems ... - Ohiowater.org