When Contract Power decided to<br />
become the first major user of <strong>Cummins</strong><br />
QSK78 generator sets in the world with<br />
the construction of a power station at<br />
Christmas Creek in the Pilbara, it could<br />
have been viewed as a bold move in<br />
such a remote and harsh region.<br />
At the time, Contract Power general<br />
manager Marc Grosser dismissed any<br />
possible concerns: “We like trying new<br />
equipment… we believe it gives us a<br />
leading edge over our competitors.”<br />
The power station in question was<br />
completed early in 2012, its generators<br />
vital to the operation of Fortescue’s<br />
Christmas Creek mine, in particular<br />
the two ore processing facilities that<br />
have an annual through-put capacity<br />
of more than 50 million tonnes.<br />
This is the biggest diesel power station<br />
in Australia, designed and built by<br />
Perth-based Contract Power and<br />
owned and operated by the same<br />
company – a progressive outfit that<br />
boasts the ability to do power generation<br />
business “anywhere in the world”.<br />
It is also the largest single installation<br />
of prime power <strong>Cummins</strong> QSK78<br />
generator sets in the world, each of<br />
the 27 units able to deliver 2 MW.<br />
In a previous issue of <strong>Cummins</strong><br />
Commentary (Issue 34, August 2011),<br />
we featured the first development<br />
stage of the power station. Undertaken<br />
in 2011, this first stage saw the<br />
installation of 14 generators, while the<br />
second and final stage was completed<br />
early in 2012 with the commissioning<br />
of a further 13 QSK78 units.<br />
The reliability of the power station is<br />
critical to Fortescue – Australia’s third<br />
largest producer of iron ore behind<br />
Rio Tinto and BHP Billiton – as it<br />
continues to ramp up production.<br />
For Contract Power’s Marc Grosser,<br />
“hitting the maintenance targets” is<br />
one of the key pointers to the<br />
efficiency of the power station.<br />
“Mechanically, the engine/alternator<br />
package is performing very well,” he says<br />
without hesitation. “Some of the gensets<br />
have clocked up over 10,000 hours<br />
and are hitting the maintenance targets<br />
that we have in place with <strong>Cummins</strong>.<br />
“Our experience at Christmas Creek is<br />
that maintenance costs of the QSK78<br />
genset are lower than competitors’ costs.<br />
“Fuel economy of the QSK78 is<br />
also very competitive,” he says.<br />
He points out the maintenance targets<br />
set with <strong>Cummins</strong> include injector<br />
change-out at 10,000 hours – a<br />
target that is being achieved.<br />