When Contract Power decided to<br />

become the first major user of <strong>Cummins</strong><br />

QSK78 generator sets in the world with<br />

the construction of a power station at<br />

Christmas Creek in the Pilbara, it could<br />

have been viewed as a bold move in<br />

such a remote and harsh region.<br />

At the time, Contract Power general<br />

manager Marc Grosser dismissed any<br />

possible concerns: “We like trying new<br />

equipment… we believe it gives us a<br />

leading edge over our competitors.”<br />

The power station in question was<br />

completed early in 2012, its generators<br />

vital to the operation of Fortescue’s<br />

Christmas Creek mine, in particular<br />

the two ore processing facilities that<br />

have an annual through-put capacity<br />

of more than 50 million tonnes.<br />

This is the biggest diesel power station<br />

in Australia, designed and built by<br />

Perth-based Contract Power and<br />

owned and operated by the same<br />

company – a progressive outfit that<br />

boasts the ability to do power generation<br />

business “anywhere in the world”.<br />

It is also the largest single installation<br />

of prime power <strong>Cummins</strong> QSK78<br />

generator sets in the world, each of<br />

the 27 units able to deliver 2 MW.<br />

In a previous issue of <strong>Cummins</strong><br />

Commentary (Issue 34, August 2011),<br />

we featured the first development<br />

stage of the power station. Undertaken<br />

in 2011, this first stage saw the<br />

installation of 14 generators, while the<br />

second and final stage was completed<br />

early in 2012 with the commissioning<br />

of a further 13 QSK78 units.<br />

The reliability of the power station is<br />

critical to Fortescue – Australia’s third<br />

largest producer of iron ore behind<br />

Rio Tinto and BHP Billiton – as it<br />

continues to ramp up production.<br />

For Contract Power’s Marc Grosser,<br />

“hitting the maintenance targets” is<br />

one of the key pointers to the<br />

efficiency of the power station.<br />

“Mechanically, the engine/alternator<br />

package is performing very well,” he says<br />

without hesitation. “Some of the gensets<br />

have clocked up over 10,000 hours<br />

and are hitting the maintenance targets<br />

that we have in place with <strong>Cummins</strong>.<br />

“Our experience at Christmas Creek is<br />

that maintenance costs of the QSK78<br />

genset are lower than competitors’ costs.<br />

“Fuel economy of the QSK78 is<br />

also very competitive,” he says.<br />

He points out the maintenance targets<br />

set with <strong>Cummins</strong> include injector<br />

change-out at 10,000 hours – a<br />

target that is being achieved.<br />