24.09.2021 Views

WPNL 202101

Wind Energy Magazine is now Windpowernl. Informing on the developments in the Dutch wind energy sector and its players.

Wind Energy Magazine is now Windpowernl. Informing on the developments in the Dutch wind energy sector and its players.

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

© WINDPARK FRYLÂN

Offshore

Wind Farm News

© TENNET HOLLANDSE KUSTNOORD

2

1

Fryslân

At the end of July the construction

of the 383 MW

Fryslân Wind Farm was completed

by Zuiderzeewind, a

consortium of Van Oord

Offshore Wind and Siemens

Gamesa Renewable Energy.

The wind farm is currently the

largest wind farm built in a

lake.

The wind farm is a project by

Windpark Fryslân BV. It features

89 Siemens Gamesa wind

turbines, each with a hub

height of 115 meters, a tip

height of 180 meters and an installed

capacity of 4.3 MW.

Due to the width of the locks

around the IJsselmeer lake and

the low water depths, no conventional

turbine installation

vessel could be used. The wind

turbines were installed simultaneously

by the two installation

platforms Sarens Soccer

Pitch and Tom-Wim. The components

were transported via a

feeder system from different

ports.

The first turbine already started

feeding power to the grid in

April this year. The power is

collected in the new transformer

station in Breezanddijk.

The wind farm is expected to

produce about 1,500 GWh of

sustainable wind energy per

year. The power is purchased

by Eneco.

Hollandse Kust Noord

Hollandse Kust Noord (HKN)

is a 759 MW offshore wind

project by CrossWind, a

joint-venture between Shell

and Eneco. The wind farm site

is located approximately 18 kilometres

off the Dutch west

coast, near Egmond aan Zee.

Sixty-nine Siemens Gamesa

type SG 11.0-200 DD, 11 MW

wind turbines will be installed

on monopile foundations. The

wind farm is due to become

operational in 2023.

Van Oord was awarded the

Balance of Plant contract. In

July this year, Van Oord selected

Dutch cable manufacturer

Twentsche Kabelfabriek (TKF)

to supply 140 km of 66 kV inter-array

cables.

In September, a start was

made on land, on the beaches

of Heemskerk and Wijk aan

Zee, with the construction of a

raised temporary work area.

This temporary elevation is

necessary to drill boreholes

under the dunes. They will

house the casing pipes in

which the export cables will

soon be pulled for the connection

of the HKN wind farm and

also HK (west Alpha).

. 3

Hollandse Kust Zuid

Offshore construction is in full

progress at the 1.5 GW

Hollandse Kust Zuid (HKZ)

Offshore Wind Farm. In July of

this year, the first batch of

foundations left for the construction

site. The foundations

are manufactured by Sif at

Maasvlakte 2. Seaway 7 is responsible

for the transport and

installation of the foundations.

The company is using its installation

vessel Seaway

Strashnov.

HKZ will feature 140 wind turbines

on TP-less monopile

foundations. Siemens is supplying

140 of its newly developed

type SG 11.0-200 DD, 11

MW wind turbine. The company

recently started serial production

of the wind turbines at

the new production site in

Cuxhaven, Germany.

Hollandse Kust Zuid is being

built around 18 to 36 kilometers

from the Dutch coast, between

The Hague and

Zandvoort. The project is developed

by Vattenfall. In June

this year, BASF joined as shareholder

(49.5%). The first

turbines are scheduled to be

commissioned in the spring of

2022, with all turbines expected

online by the summer of

2023. The electricity from the

turbines is collected and

transformed via two 700 MW

offshore transformer platforms

by TenneT. The jackets

for the two stations are already

in place. These platforms

are each connected via

220 kV AC cables to a new

land station at Maasvlakte 2.

4

Borssele 1&2

Ørsted’s first offshore wind

farm in the Netherlands,

Borssele 1&2, was officially

opened on Monday 6

September. The wind farm, located

approximately 23 km off

the coast at Westkapelle in the

province of Zeeland, has already

been operating since Q4

2020 but the opening was delayed

due to COVID-19

restrictions.

Ørsted won the tender in 2016

with a winning bid of 72.7 EUR

per MWh. In May this year,

Norges Bank Investment

Management officially became

50% shareholder in the wind

farm.

The project features 94

Siemens Gamesa SG 8.0-167

DD, 8 MW wind turbines on

monopile foundations in an

area of 112 km2 with water

depths varying between 14

and 36 meters. The main contractors

were Van Oord and

DEME Offshore (transport &

installation), Sif, EEW SPC,

EEW OSB and Bladt Industries

(foundations) and Nexans (cables).

The wind farm is connected

to the 380 kV high-voltage

land station in Borssele.

With 752 MW installed capacity,

Borssele 1&2 is the largest

operating offshore wind farm

in the Netherlands at the moment

and will be till Hollandse

Kust Zuid is completed and

operating.

1&2/© ØRSTED

BORSSELE

34 | 01-2021

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!