08.10.2022 Views

WPNL 202202

September 2022 edition of Windpowernl magazine. Theme: Wind Industry Digitalisation.

September 2022 edition of Windpowernl magazine. Theme: Wind Industry Digitalisation.

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Wind Farm in Focus

transported to the port of Kampen, a journey of one and a half to

two hours. Two pontoons were used to keep the momentum going.

And while the components were being prepared for transport, a

team was already on its way to the next wind turbine to make

preparations.

In total, 11 people were working on the water every day. Engineers

from Iver, two seamen from Wagenborg who secured the cargo on

the auxiliary pontoons, the engineers on the cranes, a skipper on

the tugboat and one on the Multicat, and finally a specialist cutter.

The latter cut the monopile. Cuperus: ‘We would have preferred to

remove the entire monopile foundation, but the specifications stated

that they had to be cut two metres below the bottom level of the

IJsselmeer.’ Faber adds: ‘This has to do with the stability function

of the dike. The Water Authority was also concerned about potential

rising seepage water due to leakage.

In the first phase of the project, the monopiles that still protruded

about 150 cm above the water surface were cut with a cutting torch

to 80 cm above the water surface. With a diameter of 3.5 metres

and an edge thickness of 3.5 cm, this process took an average of 45

minutes. The last wind turbine was removed in May. This first phase

proceeded to Iver’s complete satisfaction and without any delays.

Faber: ‘We had a lot of wind in the first week, which meant that we

could only dismantle three wind turbines. After that, we removed an

average of five wind turbines per week. The weather conditions were

great. In the end, we finished ahead of schedule.’

Processing materials

The components were transported over water to Kampen and

immediately sorted and processed on arrival. The cables and

control boxes were removed and the metals separated. The bare

steel towers and hub remained and were immediately scrapped at

the company Hoeben in Kampen. The nacelle and control boxes

were kept. Cuperus explains: ‘This is because we think there is still

a market for spare and overhaul parts and that demand will remain

for some time. Energy prices are high so now it’s attractive to keep

wind turbines that qualify for an extended lifespan operating

longer.’

The blades went to Vattenfall as agreed. Cuperus: ‘We ourselves

also offered to process these blades sustainably. Via Germany, where

these glass fibre reinforced plastics are processed as an energy

substitute and the residue as a building material for cement. We also

used this recycling method in an earlier project with the blades of

the Landtong Wind Farm. This seems to be the only method

available on a large scale at the moment.’ However, he understands

that Vattenfall wants to go a step further and challenge the market

for better applications where rotor blades can be recycled to a

higher standard. Iver was therefore only responsible for cutting the

blades into small pieces (pre-treatment) so that they could be

transported more efficiently and with fewer emissions.

Removal of monopiles

The removal of the remaining monopile sections was somewhat

exciting for both men. After all, the piles were still some 21 metres

into the ground and had to be cut off at 2 metres below the bottom

of the IJsselmeer. Cuperus: ‘We had obviously never done that on

land before. The question was therefore, how could we efficiently

cut the steel tubular piles at this depth?’

In the end, the decision was made to cut the piles from the inside.

Faber explains the process. The combined pontoon was split for this

purpose: the one with the large crane was removed, while the other

remained behind with the small crane. The piles were then dredged

to 2.5 metres below ground level. Cuperus: ‘It was important that

this work was carried out meticulously without clay adhering to the

inside of the pile. This was to prevent the cutting tool’s cutting

heads from getting stuck during the firing process.’

After the dredging of all monopiles was completed, the cutting of

the piles was started. Iver used the offshore cutting tool of TMS

from Werkendam. A winch was used to bring the tool to the right

depth, after which the lifting frame of the tool was fixed to the pile

with clamping blocks. The tool has two cutting heads and a scraper

to clean the surface to be cut. Both cutting heads rotate 185 degrees

and can thus cut the entire diameter of the pile. Underwater

cameras monitored the quality of the burn-off. The entire cutting

process was controlled and monitored from a control unit on deck

in a container. After cutting the monopile, it was lifted out of the

water with the cutting tool’s lifting frame. The monopiles were then

transported in two batches on a pontoon to Kampen. The removal

of the monopiles took only 2 weeks in total.

After removing the monopiles, the IJsselmeer lakebed was fully

restored by filling and dumping sediment. A sonar survey was

conducted to check whether the bed had been properly restored.

Repair work also had to be carried out on the dike itself. A support

remained when removing the footbridge at each wind turbine.

These had to be removed and the dike was then repaired with

basalt blocks, set by an experienced company.

© Iver

Extensive preparation

A wind turbine dismantling project is sometimes underestimated.

The complexity increases. In reality the work is similar to the

construction process but in reverse. Not everyone realises that it

involves a considerable preliminary process, says Cuperus. That was

certainly the case with the dismantling of the Irene Vorrink Wind

Farm, as it is part of the larger repowering project Windplanblauw

and has a complex maritime character.

For example, Iver’s activities took place in an area where regular

shipping and various other parties and contractors were also

working, including Ballast Nedam who were preparing the

construction of the foundations for the new wind farm further out

in the IJsselmeerand also the fishermen using fishing pots. This

involved a lot more coordination and fine-tuning, with the Marine

Coordinator of Windplanplan having to be informed on a daily

basis.

Necessary permits and notifications were also required for this

specific location. For the dismantling activities, Iver applied for a

permit from both the Zuiderzeeland Water Authority and the

municipality. As the competent authority, the Water Authority is not

only responsible for the dike but also for the first few metres in the

water. Rijkswaterstaat is also closely involved in this process because

of the use of the IJsselmeer. Such a permit process with a complex

project requires the necessary preparations, coordination and a long

lead time.

Iver has therefore drawn up an extensive project plan for this

project. Both focused on the execution method as well as the safety

measures. In addition, an ecological work protocol was drawn up

describing management methods to prevent, for example, birds

from breeding in the work area. Iver mowed strips of grass on the

dike to prevent this. The work area was checked weekly by an expert

for breeding birds and the presence of nests.

‘We took advise on the height at which to cut the piles so that a

cormorant could still escape at any time’, adds Faber.

Cuperus: ‘When you map out the preliminary process well and

make good mutual agreements, the work can proceed smoothly and

according to plan. We started on 4 April and our work proceeded

without incident or any need for intervention by the authorities or

the client.’

End of era

For Iver, the Irene Vorrink project is now complete and delivered,

although the company will continue to dismantle more wind

turbines in the region for Windplanblauw in the coming years. The

men look back on the project with pride. Never before has Iver

dismantled a wind farm with 28 wind turbines in such a complex

environment. For a number of mechanics, however, this has been

an extra special project, says Faber: ‘As a company, we have been

involved in this wind farm for years: from construction, to carrying

out maintenance for years, to dismantling.’ Cuperus: ‘A mechanic

from Iver was involved in the installation of the wind turbines in

1995 and still has photos of it. Now 27 years later (still working as a

mechanic for Iver), he and the Iver team were commissioned to

dismantle the wind turbines, for him the circle is complete.’

Anyone driving by now sees only a dike, like many other dikes in

the Netherlands. But that is only temporary. If you pay close

attention, you will see the activities that are taking place for the new

wind farm to be constructed in the IJsselmeer. Admittedly, this

wind farm will be located further out in the water from the dike,

but the new wind turbines will still be visible from the A6. •

38 | 02-2022

02-2022 | 39

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!