ASME Message
ASME Message
ASME Message
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Abstracts<br />
site remediation, to license termination. A key feature of the EPRI Program is the collection and transfer of lessons<br />
learned and experiences from the major decommissioning projects conducted to date. The EPRI Program conducts<br />
research and development based on the needs of its utility members; the EPRI Program membership consists of utilities<br />
from the USA, France, Spain, Sweden, Italy, Taiwan, and Japan. EPRI is the mechanism through which these<br />
international utilities can conduct collaborative research and development and learn from each other’s experiences and<br />
lessons learned. In addition to collaborative research and development, the EPRI Program Team of decommissioning<br />
experts provides direct and site-specific support to its member utilities to facilitate knowledge transfer and<br />
decommissioning project optimization.<br />
This presentation will provide information about the EPRI Nuclear Power Plant Decommissioning Technology<br />
Program and discuss USA and International Decommissioning experiences to date.<br />
3) 40253 – Tokai-1 Decommissioning Project<br />
Keizaburou Yoshino , JAPC (Japan)<br />
Tokai-1 is the oldest and historical commercial Magnox reactor in Japan, which had started commercial operation in<br />
1966. The unit had helped introduction and establishment of the construction and operation technologies regarding<br />
nuclear power plant at early stage in Japan by its construction and operating experiences. However, The Japan Atomic<br />
Power Company (JAPC), the operator and owner of Tokai-1, decided to cease its operation permanently because of a<br />
fulfillment of its mission and economical reason. The unit was finally ceased in March 1998 after about 32 year operation.<br />
It took about three years for removal of all spent fuels from the site, and then decommissioning started in 2001. JAPC,<br />
always on the forefront of the nation’s nuclear power generation, is now grappling Japan’s first decommissioning of a<br />
commercial nuclear power plant, striving to establish effective, advanced decommissioning. The decommissioning for<br />
Tokai-1 was scheduled as 20 years project. At the beginning, the reactor was started to be in a static condition for ten<br />
years (“safe storage period”). While the reactor had been safely stored, the phased decommissioning works started from<br />
non-radioactive or low radioactive equipments toward high radioactive equipments. First five years of the project, JAPC<br />
concentrated to drain and clean spent fuel cartridge cooling pond and to remove conventional equipments such as turbine,<br />
feed water pump and fuel charge machine as planed and budgeted.<br />
From 2006, the project came into new phase. JAPC has been trying to remove four Steam Raising Units (SRUs).<br />
The SRUs are huge component (7ton, φ6.3m, H24.7m) of the Gas Cooling Reactor (GCR) and inside of the SRUs are<br />
radioactively contaminated. It is concerned that workers are required safety and minimizing contamination areas during<br />
SRU removal. Therefore, JAPC is developing and introducing Jack-down method and remote control multi functional<br />
removal system. This method is the method by which to remove the SRUs in turn from the bottom by lifting the SRU by<br />
a large jack and cutting for removing SRU is done remotely with this system. The system enables cutting and holding not<br />
only SRU body but also internals. This technology and experiences would be useful for the reactor removal in the near<br />
future.<br />
4) 40289 – Activities of the OECD/NEA WPDD in the Field of Decommissioning<br />
Claudio Pescatore, Patrick O'Sullivan, OECD/NEA<br />
The OECD/NEA seeks to assist its member countries in developing strategies for the management of all types of<br />
radioactive material, including waste, that are safe and sustainable and that meet the broad needs of society - with<br />
particular emphasis on the management of long-lived waste and spent fuel and on decommissioning of disused nuclear<br />
facilities. The programme of work in the area of decommissioning is supervised by the Radioactive Waste Management<br />
Committee (RWMC) and carried out by the Working Party on Decommissioning and Dismantling (WPDD). The latter is<br />
made of senior representatives from regulatory authorities, decommissioning organisations, policy making bodies, and<br />
researchand-development institutions from the NEA countries. It includes also representatives of the IAEA and of the the<br />
European Commission. The WPDD supports the RWMC by keeping under review the policy, strategic, and regulatory<br />
aspects of decommissioning of phased-out nuclear installations. Its scope of work includes decommissioning and<br />
dismantling of shutdown facilities up to and including the release of the site, but excluding fuel removal, removal of<br />
nuclear processing fluids, post-operational clean out of fuel residues and removal of operational wastes. The work<br />
programme comprises activities in the following key areas: Policy, regulation and strategy; Funding and costs;<br />
Techniques; Decommissioning materials management and site release; and Human and organisational factors. Recent<br />
trends in the above areas, as noted in a recent analysis by the WPDD, include: • Policy, regulations and strategy – most<br />
countries have adopted policies for decommissioning and for funding provisioning but a range of options were being<br />
applied to the decommissioning of nuclear power plants (early dismantling, safe store and entombment), • Funding and<br />
costs – cost calculations for decommissioning are very sensitive to the assumed end-state and to the levels of<br />
contaminations on the sites and may be greatly influenced by stakeholder requirements, • Techniques – the focus of<br />
current R&D is on the development of innovative technology for segmentation, dismantling and concrete<br />
decontamination, together with better instrumentation for material management and control • Materials management and<br />
site release – there is a significant acceleration in the number of decommissioning projects, including provision of<br />
infrastructure for storage of materials and for undertaking clearance and recycling of disused materials; • Human and<br />
organisational factors – efforts are being made to structure decommissioning contracts to optimise the supply chain<br />
relationships, with greater transparency and better communication amongst all concerned parties; and • Stakeholder<br />
participation and knowledge management – there is a range of approaches to stakeholder involvement in developing<br />
decommissioning plans and to rule making. In general, this issue is gaining momentum. A number of specific activities,<br />
-44-