05.01.2013 Views

ASME Message

ASME Message

ASME Message

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Abstracts<br />

site remediation, to license termination. A key feature of the EPRI Program is the collection and transfer of lessons<br />

learned and experiences from the major decommissioning projects conducted to date. The EPRI Program conducts<br />

research and development based on the needs of its utility members; the EPRI Program membership consists of utilities<br />

from the USA, France, Spain, Sweden, Italy, Taiwan, and Japan. EPRI is the mechanism through which these<br />

international utilities can conduct collaborative research and development and learn from each other’s experiences and<br />

lessons learned. In addition to collaborative research and development, the EPRI Program Team of decommissioning<br />

experts provides direct and site-specific support to its member utilities to facilitate knowledge transfer and<br />

decommissioning project optimization.<br />

This presentation will provide information about the EPRI Nuclear Power Plant Decommissioning Technology<br />

Program and discuss USA and International Decommissioning experiences to date.<br />

3) 40253 – Tokai-1 Decommissioning Project<br />

Keizaburou Yoshino , JAPC (Japan)<br />

Tokai-1 is the oldest and historical commercial Magnox reactor in Japan, which had started commercial operation in<br />

1966. The unit had helped introduction and establishment of the construction and operation technologies regarding<br />

nuclear power plant at early stage in Japan by its construction and operating experiences. However, The Japan Atomic<br />

Power Company (JAPC), the operator and owner of Tokai-1, decided to cease its operation permanently because of a<br />

fulfillment of its mission and economical reason. The unit was finally ceased in March 1998 after about 32 year operation.<br />

It took about three years for removal of all spent fuels from the site, and then decommissioning started in 2001. JAPC,<br />

always on the forefront of the nation’s nuclear power generation, is now grappling Japan’s first decommissioning of a<br />

commercial nuclear power plant, striving to establish effective, advanced decommissioning. The decommissioning for<br />

Tokai-1 was scheduled as 20 years project. At the beginning, the reactor was started to be in a static condition for ten<br />

years (“safe storage period”). While the reactor had been safely stored, the phased decommissioning works started from<br />

non-radioactive or low radioactive equipments toward high radioactive equipments. First five years of the project, JAPC<br />

concentrated to drain and clean spent fuel cartridge cooling pond and to remove conventional equipments such as turbine,<br />

feed water pump and fuel charge machine as planed and budgeted.<br />

From 2006, the project came into new phase. JAPC has been trying to remove four Steam Raising Units (SRUs).<br />

The SRUs are huge component (7ton, φ6.3m, H24.7m) of the Gas Cooling Reactor (GCR) and inside of the SRUs are<br />

radioactively contaminated. It is concerned that workers are required safety and minimizing contamination areas during<br />

SRU removal. Therefore, JAPC is developing and introducing Jack-down method and remote control multi functional<br />

removal system. This method is the method by which to remove the SRUs in turn from the bottom by lifting the SRU by<br />

a large jack and cutting for removing SRU is done remotely with this system. The system enables cutting and holding not<br />

only SRU body but also internals. This technology and experiences would be useful for the reactor removal in the near<br />

future.<br />

4) 40289 – Activities of the OECD/NEA WPDD in the Field of Decommissioning<br />

Claudio Pescatore, Patrick O'Sullivan, OECD/NEA<br />

The OECD/NEA seeks to assist its member countries in developing strategies for the management of all types of<br />

radioactive material, including waste, that are safe and sustainable and that meet the broad needs of society - with<br />

particular emphasis on the management of long-lived waste and spent fuel and on decommissioning of disused nuclear<br />

facilities. The programme of work in the area of decommissioning is supervised by the Radioactive Waste Management<br />

Committee (RWMC) and carried out by the Working Party on Decommissioning and Dismantling (WPDD). The latter is<br />

made of senior representatives from regulatory authorities, decommissioning organisations, policy making bodies, and<br />

researchand-development institutions from the NEA countries. It includes also representatives of the IAEA and of the the<br />

European Commission. The WPDD supports the RWMC by keeping under review the policy, strategic, and regulatory<br />

aspects of decommissioning of phased-out nuclear installations. Its scope of work includes decommissioning and<br />

dismantling of shutdown facilities up to and including the release of the site, but excluding fuel removal, removal of<br />

nuclear processing fluids, post-operational clean out of fuel residues and removal of operational wastes. The work<br />

programme comprises activities in the following key areas: Policy, regulation and strategy; Funding and costs;<br />

Techniques; Decommissioning materials management and site release; and Human and organisational factors. Recent<br />

trends in the above areas, as noted in a recent analysis by the WPDD, include: • Policy, regulations and strategy – most<br />

countries have adopted policies for decommissioning and for funding provisioning but a range of options were being<br />

applied to the decommissioning of nuclear power plants (early dismantling, safe store and entombment), • Funding and<br />

costs – cost calculations for decommissioning are very sensitive to the assumed end-state and to the levels of<br />

contaminations on the sites and may be greatly influenced by stakeholder requirements, • Techniques – the focus of<br />

current R&D is on the development of innovative technology for segmentation, dismantling and concrete<br />

decontamination, together with better instrumentation for material management and control • Materials management and<br />

site release – there is a significant acceleration in the number of decommissioning projects, including provision of<br />

infrastructure for storage of materials and for undertaking clearance and recycling of disused materials; • Human and<br />

organisational factors – efforts are being made to structure decommissioning contracts to optimise the supply chain<br />

relationships, with greater transparency and better communication amongst all concerned parties; and • Stakeholder<br />

participation and knowledge management – there is a range of approaches to stakeholder involvement in developing<br />

decommissioning plans and to rule making. In general, this issue is gaining momentum. A number of specific activities,<br />

-44-

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!