2.5.2 Progress towards objectives – tasks worked on and achievements made<br />
Task 5a) - Science, Engineering and business plans for generic cable and stand-alone<br />
sites<br />
<strong>Activity</strong> 5a1: Science – Generic cable site WG<br />
<strong>Activity</strong> 5a2: Science – Stand-alone site WG<br />
<strong>Activity</strong> 5a3: Engineering – Generic cable site WG<br />
<strong>Activity</strong> 5a4: Engineering – Stand-alone site WG<br />
<strong>Activity</strong> 5a5: Business plan and financial model – Generic cable site WG<br />
<strong>Activity</strong> 5a6: Business plan and financial model – Stand-alone site WG<br />
Considerable advances were achieved in WP5 over the course of <strong>Period</strong> 3 for the ESONET<br />
NoE. In the previous reporting period, report D5 had been prepared and delivered which<br />
outlined the preliminary work done in the Generic Cable and Generic Stand-alone WGs (Task<br />
5a). The science, business and engineering backgrounds for each solution have been fully<br />
described in D5.<br />
Task 5b) – Legal, Ethical and Environmental (LEE)<br />
<strong>Activity</strong> 5b3: Phase 3. Analysis of content<br />
<strong>Activity</strong> 5b4: Phase 4. Best Practices and guidelines<br />
These activities are reported below for a more comprehensive reading.<br />
Task 5c) – Comparative work<br />
For D48, the focus of some WP5 participants was mainly on Task 5c – Comparative work<br />
between the two work groups (WGs) from a science, engineering and business plan/costing<br />
perspective. This work has primarily been done by Fiona Grant (IMI) in conjunction with<br />
Jaume Piera and Xavier Garcia (CSIC). Important background work had already been done by<br />
other WP participants listed above. The science and engineering elements were prepared by<br />
CSIC colleagues while the IMI focused on comparative costings for both solutions. There was<br />
also an update for some of the legal issues around the application for ERIC status and<br />
decommissioning.<br />
In parallel with the process of reporting to EMSO on the implementation model (D46), the<br />
project coordinators and Steering Committee members strove to finalise the implementation<br />
plan for ESONET-EMSO. This work also formed the basis of D48. Jean-Francois Rolin<br />
(IFREMER) and Fiona Grant (IMI) devoted time to the refinement of the cost models for the<br />
revised implementation plans. This work has proven invaluable for funding agencies and the<br />
Steering Committees of both the ESONET and EMSO projects.<br />
D47, the online database to include local, national and European legal, ethical and<br />
environmental (LEE) documents became available in early 2010 for use by Partners and the<br />
EMSO PP. It proved an invaluable information source for the preparation of material on<br />
Regional Legal Entities for ESONET/EMSO.<br />