APPENDIX E<br />
EARTHEN EMBANKMENT DAM<br />
PRELIMINARY OPINION OF COST<br />
FOR ALTERNATIVE ASSESSMENT<br />
Project 09170036.00 Schnabel Engineering, LLC<br />
May 14, 2010 Copyright 2010
Ragged Mountain <strong>Dam</strong><br />
<strong>Earthen</strong> <strong>Embankment</strong> <strong>Dam</strong> Alternative<br />
Alternatives Assessment <strong>Opinion</strong> <strong>of</strong> Cost<br />
(Prices in 2010 Dollars)<br />
Schnabel Engineering 2010<br />
<strong>Dam</strong> Construction<br />
Item Number Units Quantity Unit Price Extended Price<br />
1 Mobilization & Demobilization<br />
a. General LS 1 $1,566,169 $1,566,169<br />
b. Bonds and Insurance LS 1 $671,215 $671,215<br />
2 Care and Diversion <strong>of</strong> Water<br />
a. Erosion and Sediment Control LS 1 $800,000 $800,000<br />
b. Foundation Dewatering/Water Control LS 1 $350,000 $350,000<br />
3 Clearing and Grubbing<br />
a. <strong>Dam</strong> and Emergency Spillway AC 11.00 $5,000 $55,000<br />
b. Borrow Areas AC 39.40 $4,500 $177,300<br />
c. Access Road AC 2.40 $5,500 $13,200<br />
4 Reservoir Clearing AC 102 $5,650 $577,939<br />
5 Demolition and Removal <strong>of</strong> Structures<br />
aa. Miscellaneous Structures LS 1 $10 $10,000 000 $10 $10,000 000<br />
b. Modifications to Lower <strong>Dam</strong> LS 1 $350,000 $350,000<br />
c. Removal <strong>of</strong> Upper <strong>Dam</strong> LS 1 $400,000 $400,000<br />
d. Removal <strong>of</strong> Old Piping LS 1 $50,000 $50,000<br />
6 Excavation<br />
a. Common Excavation CY 66,560 $5.00 $332,800<br />
b. Rock Excavation CY 33,000 $25.00 $825,000<br />
c. Rock Trimming CY 3,000 $75.00 $225,000<br />
d. Rock Shaping SY 500 $50.00 $25,000<br />
7 Rock Cleaning SY 5,410 $40.00 $216,400<br />
8 Foundation Drilling and Grouting SF 137,110 $20 $2,742,200<br />
9 Fill<br />
a. Common Earth Fill (Shell Fill) CY 534,020 $5.00 $2,670,100<br />
b. Select Earth Fill (Core Fill) CY 126,000 $7.00 $882,000<br />
b. Fine Drain Fill CY 15,380 $55.00 $845,900<br />
c. Coarse Drain Fill CY 6,740 $50.00 $337,000<br />
d. <strong>Embankment</strong> Test Fill LS 1 $50,000.00 $50,000<br />
10 Slope Protection<br />
a. Type I Rip Rap (Plunge Pool) CY 1,070 $80.00 $85,600<br />
b. Type II Rip Rap (Wave Action Protection) CY 7,160 $75.00 $ $537,000 $<br />
c. Rip Rap Bedding Material CY 2,530 $45.00 $113,850<br />
d. Geotextile SY 1,200 $10.00 $12,000<br />
11 Conventional Concrete (Includes Waterstop)<br />
a. Structural Concrete (Riser, Bridge Pier, Pipe Encasement, Retaining Walls) CY 2,700 $750.00 $2,025,000<br />
b. Dental Concrete CY 2,500 $250.00 $625,000<br />
12 Steel Reinforcing Bars LB 459,000 $0.80 $367,200<br />
13 Gates<br />
a. 24-inch Sluice Gate (unseating head) EA 1 $80,000 $80,000<br />
b. 24-inch Sluice Gate (seating head) EA 2 $37,500 $75,000<br />
c. 6-inch Sluice Gate EA 1 $8,500 $8,500<br />
14 36-Inch Steel Pipe (Conduit through <strong>Dam</strong>) LF 750 $522 $391,500<br />
15 Drainage Pipe and Materials<br />
a. Solid 8-inch PVC Pipe LF 1,180 $30 $35,400<br />
b. Perforated 8-inch PVC Pipe LF 1,020 $35 $35,700<br />
c. Solid 6-inch PVC Pipe LF 280 $25 $7,000<br />
d. Perforated 6-inch PVC Pipe LF 1,840 $30 $55,200<br />
16 Chain-Linked Chain Linked Fence and Gates LS 1 $5,000 $5,000<br />
17 Instrumentation LS 1 $165,000 $165,000<br />
18 Riser Bridge LS 1 $135,000 $135,000<br />
19 Storm Drainage System<br />
a. Manhole EA 5 $2,000 $10,000<br />
b. 18-inch HDPE Pipe LF 840 $75 $63,000<br />
20 Metal Work LS 1 $100,000 $100,000<br />
21 Landscaping and Site Restoration<br />
a. Topsoil CY 9,710 $6.00 $58,260<br />
b. Permanent Turf Establishment (with Matting) (20% <strong>of</strong> Area) AC 49 $3,000 $146,160<br />
G:\2009 Jobs\09170036.00 Ragged Mountain\Task 7- <strong>Preliminary</strong> Design (30%)\Quantities\Construction Cost Estimates Ragged Mountain-Alternatives Assessment Final Report 5/14/20101:04 PM
22 4800-Feet 18-inch Pipe, Open Cut, 6-foot Depth, Ductile Iron Pipe<br />
a. Furnish and Install Pipe LF 4,480 $270.00 $1,209,600<br />
b. Clearing and Grubbing LF 4,480 $22.00 $98,560<br />
c. Site Restoration LF 4,480 $13.00 $58,240<br />
d. Rock Removal (25% Rock, 4.5-foot Wide Trench) CY 1,750 $200.00 $350,000<br />
23<br />
1260-Feet <strong>of</strong> 36-inch Pipe, Open Cut, 10-foot Depth, Class 53 Ductile Iron Pipe<br />
(Outside <strong>of</strong> <strong>Dam</strong>)<br />
a. Furnish and Install Pipe LF 1,260 $689.00 $868,140<br />
b. Clearing and Grubbing LF 1,260 $22.00 $27,720<br />
c. Site Restoration LF 1,260 $16.00 $20,160<br />
d. Rock Removal (50% Rock, 6-foot Wide Trench) CY 1,402 $200.00 $280,400<br />
24 Valves, Rubber Seated, Electric Motor-Operated<br />
a. 36-inch Valve EA 2 $71,000 $142,000<br />
b. 6-Inch Valve EA 1 $10,000 $10,000<br />
c. Install Valves EA 3 $12,000 $36,000<br />
25 Ball Valves, Electrical and Controls<br />
a. Electrical EA 1 $100,000 $100,000<br />
b. Controls EA 1 $100,000 $100,000<br />
26 Staging Area (Holiday Trails)<br />
a. Land Rental (16 ( Months) ) LS 1 $100,000 $ , $100,000 $ ,<br />
b. Restoration (Site and Stream) LS 1 $150,000 $150,000<br />
27 Roadways<br />
a. Reservoir Drive Upgrade and Maintenance LS 1 $250,000 $250,000<br />
b. Traffic Control LS 1 $150,000 $150,000<br />
c. Roadway Surfacing SY 7,200 $12 $86,400<br />
d. Access Road Improvements LS 1 $200,000 $200,000<br />
28 Unlisted Items LS 1 $1,065,421 $1,065,421<br />
Construction Costs Subtotal: $24,611,235<br />
Contingency (%): 20%<br />
Subtotal Estimated Construction Costs Plus Contingency: $29,533,482<br />
Engineering Services<br />
29 Engineering Services<br />
a. Engineering Design LS 1 $890,298 $890,298<br />
b. Construction Observation and Testing LS 1 $2,800,000 $2,800,000<br />
Engineering Services Subtotal: $3,690,298<br />
Contingency (%): 10%<br />
Subtotal Estimated Engineering Services Plus Contingency: $4,059,328<br />
Construction and Engineering Costs Total: $28,301,533<br />
Estimated Total Construction and Engineering Costs Plus Contingency: $33,592,810<br />
G:\2009 Jobs\09170036.00 Ragged Mountain\Task 7- <strong>Preliminary</strong> Design (30%)\Quantities\Construction Cost Estimates Ragged Mountain-Alternatives Assessment Final Report 5/14/20101:04 PM