Activity ID <strong>WBS</strong> Activity Name Original<br />
Duration<br />
ATST <strong>Enclosure</strong> <strong>by</strong> <strong>WBS</strong><br />
Start Finish Total<br />
Float<br />
ATST IPS Constructio<br />
<strong>Construction</strong> - Start in Oct09 1545 01-Oct-09 02-Sep-15 513<br />
ATST Project 1545 01-Oct-09 02-Sep-15 513<br />
ATST <strong>Construction</strong> & Commissioning Com<br />
1545 01-Oct-09 02-Sep-15 513<br />
Telescope Systems 1545 01-Oct-09 02-Sep-15 513<br />
<strong>Enclosure</strong> 1545 01-Oct-09 02-Sep-15 513<br />
ENC0005 1.2.3.5 Issue <strong>Enclosure</strong> Design RFP 0 01-Oct-09 75<br />
ENC0010 1.2.3.5 <strong>Enclosure</strong> Design Vendor Proposal Period 50 01-Oct-09 09-Dec-09 75<br />
ENC0015 1.2.3.5 Receive <strong>Enclosure</strong> Design Proposal Responses 0 10-Dec-09 75<br />
ENC0025 1.2.3.5 Review <strong>Enclosure</strong> Design Proposals 20 10-Dec-09 06-Jan-10 75<br />
ENC0030 1.2.3.5 Recommendation for <strong>Enclosure</strong> Design Contract Award 0 07-Jan-10 75<br />
ENC0035 1.2.3.5 <strong>Enclosure</strong> Design Contract Negotiations 30 07-Jan-10 17-Feb-10 75<br />
ENC0036 1.2.3.5 <strong>Enclosure</strong> Design Contract Approval (AURA and NSF) 40 18-Feb-10 14-Apr-10 75<br />
ENC0037 1.2.3.5 <strong>Enclosure</strong> Design Contract Award 0 14-Apr-10 75<br />
ENC0038 1.2.3.5 <strong>Enclosure</strong> Planning and Development 20 15-Apr-10 12-May-10 75<br />
ENC0040 1.2.3.5 <strong>Enclosure</strong> Preliminary Design Effort 220 13-May-10 16-Mar-11 75<br />
ENC0040B 1.2.3.5 <strong>Enclosure</strong> Contractor Provides Loads & Interface Requirements to Building A/E<br />
Contractor<br />
0 30-Sep-10 110<br />
ENC0041 1.2.3.5 Approval of Lower <strong>Enclosure</strong> Interface Design <strong>by</strong> <strong>Enclosure</strong> Contractor 0 31-Dec-10 110<br />
ENC0042 1.2.3.5 <strong>Enclosure</strong> PDR 0 17-Mar-11 75<br />
ENC0044 1.2.3.5 <strong>Enclosure</strong> Final Design Effort 176 17-Mar-11 17-Nov-11 75<br />
ENC0048 1.2.3.5 <strong>Enclosure</strong> Procurement & Fab of long lead items (AZTrack, Arch GirdersEtc....) 240 17-Mar-11 15-Feb-12 371<br />
ENC0050 1.2.3.5 <strong>Enclosure</strong> FDR 0 17-Nov-11 215<br />
ENC0060 1.2.3.5 <strong>Enclosure</strong> Procurement & Fab Complete 0 06-Jun-13 523<br />
ENC0070 1.2.3.5 <strong>Enclosure</strong> Azimuth Track Fabrication Complete 0 19-Jul-11 436<br />
ENC0076 1.2.3.5 <strong>Enclosure</strong> <strong>Construction</strong> Contract Approval (AURA and NSF) 40 06-Apr-12 31-May-12 75<br />
ENC0087 1.2.3.5 <strong>Enclosure</strong> <strong>Construction</strong> Contract Award 0 31-May-12 75<br />
ENC0265 1.2.3.5 <strong>Enclosure</strong> Factory Assy & Test Complete 0 06-Jun-13 523<br />
ENC0270 1.2.3.5 <strong>Enclosure</strong> Disassembly & Packaging 15 05-Apr-13 25-Apr-13 75<br />
ENC0272 1.2.3.5 <strong>Enclosure</strong> Shipment from Contractor to Hawaiian Port 40 26-Apr-13 20-Jun-13 75<br />
ENC0274 1.2.3.5 <strong>Enclosure</strong> Offloading @ Port & Transport to Storage Yard 5 21-Jun-13 27-Jun-13 75<br />
ENC0285 1.2.3.5 <strong>Enclosure</strong> Packaging & Transportation to Hawaii Complete 0 29-Aug-13 463<br />
ENC0290 1.2.3.5 <strong>Enclosure</strong> Site Fab, Assy & Test Complete 0 27-Oct-14 161<br />
ENC0295 1.2.3.5 Issue <strong>Enclosure</strong> <strong>Construction</strong> RFP 0 18-Nov-11 75<br />
ENC0300_M2 1.2.3.5 <strong>Enclosure</strong> Contract Closeout 0 02-Mar-15 468<br />
ENC0305 1.2.3.5 Install <strong>Enclosure</strong> Apron (Tie into Rainwater Collection) 22 08-Aug-15 02-Sep-15 466<br />
ENC0307 1.2.3.5 Install <strong>Enclosure</strong> Apron (Tie into Rainwater Collection) Complete 0 02-Sep-15 513<br />
ENC0310 1.2.3.5 <strong>Enclosure</strong> <strong>Construction</strong> Vendor Proposal Period 50 18-Nov-11 26-Jan-12 75<br />
ENC0315 1.2.3.5 Receive <strong>Enclosure</strong> <strong>Construction</strong> Proposal Responses 0 27-Jan-12 75<br />
ENC0320 1.2.3.5 Recommendation for <strong>Enclosure</strong> <strong>Construction</strong> Contract Award 0 24-Feb-12 75<br />
ENC0325 1.2.3.5 Review <strong>Enclosure</strong> <strong>Construction</strong> Proposals 20 27-Jan-12 23-Feb-12 75<br />
ENC0335 1.2.3.5 <strong>Enclosure</strong> <strong>Construction</strong> Contract Negotiations 30 24-Feb-12 05-Apr-12 75<br />
Carousel 766 18-Nov-11 27-Oct-14 161<br />
ENC0075 1.2.3.5.1 ENC Carousel Procurement & Fab 100 01-Jun-12 18-Oct-12 75<br />
ENC0080 1.2.3.5.1 ENC Carousel Factory Assy & Test 120 19-Oct-12 04-Apr-13 75<br />
ENC0090 1.2.3.5.1 ENC Carousel Fab, Assy & Test @ Site 180 11-Oct-13 02-Aug-14 0<br />
ENC0092 1.2.3.5.1 Complete ENC Carousel Fab, Assy & Test @ Site 60 04-Aug-14 27-Oct-14 161<br />
ENC0094_M1 1.2.3.5.1 <strong>Enclosure</strong> Weather-tight & Internals Complete 0 04-Aug-14 0<br />
ENC0110 1.2.3.5.1 ENC Azimuth Track Factory Disassembly & Packaging 10 19-Jan-12 01-Feb-12 348<br />
ENC0120 1.2.3.5.1 ENC Azimuth Track Factory Assy & Test 44 18-Nov-11 18-Jan-12 348<br />
ENC0130 1.2.3.5.1 ENC Azimuth Track Assy & Test @ Site 60 02-Aug-13 10-Oct-13 0<br />
ENC0170 1.2.3.5.1 ENC Azimuth Track Shipment from Contractor to Hawaiian Port 40 02-Feb-12 28-Mar-12 348<br />
ENC0180 1.2.3.5.1 ENC Azimuth Track Offloading @ Port & Transport to Storage Yard 3 29-Mar-12 02-Apr-12 348<br />
Carousel Drive Sys System 616 01-Jun-12 11-Oct-14 135<br />
ENC0100 1.2.3.5.2 ENC Carousel Drives Procurement & Fab 100 01-Jun-12 18-Oct-12 75<br />
ENC0105 1.2.3.5.2 ENC Carousel Drives Factory Assy & Test 120 19-Oct-12 04-Apr-13 75<br />
ENC0115 1.2.3.5.2 ENC Carousel Drives Assy & Test @ Site 240 11-Oct-13 11-Oct-14 162<br />
<strong>Enclosure</strong> Thermal Systems 1412 01-Oct-09 02-Mar-15 646<br />
ENC0020 1.2.3.5.4 ENC Thermal Design Vendor Proposal Period 50 01-Oct-09 09-Dec-09 463<br />
Q Q Q Q Q Q Q3 Q Q Q Q Q4 Q Q Q3 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q<br />
2009 2010 2011 2012 2013 2014 2015 2016 2017 8<br />
02-Sep-15<br />
02-Sep-15<br />
02-Sep-15<br />
02-Sep-15<br />
02-Sep-15<br />
Issue <strong>Enclosure</strong> Design RFP<br />
<strong>Enclosure</strong> Design Vendor Proposal Period<br />
Receive <strong>Enclosure</strong> Design Proposal Responses<br />
Review <strong>Enclosure</strong> Design Proposals<br />
Recommendation for <strong>Enclosure</strong> Design Contract Award<br />
<strong>Enclosure</strong> Design Contract Negotiations<br />
<strong>Enclosure</strong> Design Contract Approval (AURA and NSF)<br />
<strong>Enclosure</strong> Design Contract Award<br />
<strong>Enclosure</strong> Planning and Development<br />
<strong>Enclosure</strong> Preliminary Design Effort<br />
<strong>Enclosure</strong> Contractor Provides Loads & Interface Requirements to Building A/E Contractor<br />
Approval of Lower <strong>Enclosure</strong> Interface Design <strong>by</strong> <strong>Enclosure</strong> Contractor<br />
<strong>Enclosure</strong> PDR<br />
<strong>Enclosure</strong> Final Design Effort<br />
<strong>Enclosure</strong> Procurement & Fab of long lead items (AZTrack, Arch GirdersEtc....)<br />
<strong>Enclosure</strong> FDR<br />
<strong>Enclosure</strong> Procurement & Fab Complete<br />
<strong>Enclosure</strong> Azimuth Track Fabrication Complete<br />
<strong>Enclosure</strong> <strong>Construction</strong> Contract Approval (AURA and NSF)<br />
<strong>Enclosure</strong> <strong>Construction</strong> Contract Award<br />
<strong>Enclosure</strong> Factory Assy & Test Complete<br />
<strong>Enclosure</strong> Disassembly & Packaging<br />
<strong>Enclosure</strong> Shipment from Contractor to Hawaiian Port<br />
<strong>Enclosure</strong> Offloading @ Port & Transport to Storage Yard<br />
<strong>Enclosure</strong> Packaging & Transportation to Hawaii Complete<br />
<strong>Enclosure</strong> Site Fab, Assy & Test Complete<br />
Issue <strong>Enclosure</strong> <strong>Construction</strong> RFP<br />
<strong>Enclosure</strong> Contract Closeout, -----> ITC<br />
Install <strong>Enclosure</strong> Apron (Tie into R<br />
Install <strong>Enclosure</strong> Apron (Tie into R<br />
<strong>Enclosure</strong> <strong>Construction</strong> Vendor Proposal Period<br />
Receive <strong>Enclosure</strong> <strong>Construction</strong> Proposal Responses<br />
Recommendation for <strong>Enclosure</strong> <strong>Construction</strong> Contract Award<br />
Review <strong>Enclosure</strong> <strong>Construction</strong> Proposals<br />
<strong>Enclosure</strong> <strong>Construction</strong> Contract Negotiations<br />
27-Oct-14<br />
ENC Carousel Procurement & Fab<br />
ENC Carousel Factory Assy & Test<br />
ENC Carousel Fab, Assy & Test @ Site<br />
Complete ENC Carousel Fab, Assy & Test @ S<br />
<strong>Enclosure</strong> Weather-tight & Internals Complete<br />
ENC Azimuth Track Factory Disassembly & Packaging<br />
ENC Azimuth Track Factory Assy & Test<br />
ENC Azimuth Track Assy & Test @ Site<br />
ENC Azimuth Track Shipment from Contractor to Hawaiian Port<br />
ENC Azimuth Track Offloading @ Port & Transport to Storage Yard<br />
11-Oct-14<br />
ENC Carousel Drives Procurement & Fab<br />
ENC Carousel Drives Factory Assy & Test<br />
ENC Carousel Drives Assy & Test @ Site<br />
02-Mar-15<br />
ENC Thermal Design Vendor Proposal Period
Activity ID <strong>WBS</strong> Activity Name Original<br />
Duration<br />
Start Finish Total<br />
Float<br />
ENC0045 1.2.3.5.4 ENC Thermal Design Issue RFP 0 01-Oct-09 463<br />
ENC0046 1.2.3.5.4 ENC Thermal Design Contract Approval (AURA and NSF) 40 18-Feb-10 14-Apr-10 463<br />
ENC0051 1.2.3.5.4 Approval of Lower <strong>Enclosure</strong> Interface Design <strong>by</strong> <strong>Enclosure</strong> Contractor 0 01-Oct-09 2058<br />
ENC0055 1.2.3.5.4 ENC Thermal Design Receive Proposal Responses 0 10-Dec-09 463<br />
ENC0056 1.2.3.5.4 ENC Thermal <strong>Construction</strong> Contract Approval (AURA and NSF) 40 06-Apr-12 01-Jun-12 463<br />
ENC0057 1.2.3.5.4 ENC Thermal Design Contract Award 0 14-Apr-10 463<br />
ENC0058 1.2.3.5.4 ENC Thermal Planning and Development 20 15-Apr-10 12-May-10 463<br />
ENC0059 1.2.3.5.4 ENC Thermal Preliminary Design Effort 220 13-May-10 16-Mar-11 463<br />
ENC0059A 1.2.3.5.4 ENC Thermal Contractor Provides Loads & Interface Requirements to Building A/E<br />
Contractor<br />
0 30-Sep-10 1798<br />
ENC0059B 1.2.3.5.4 ENC Thermal PDR 0 17-Mar-11 463<br />
ENC0059C 1.2.3.5.4 ENC Thermal Final Design Effort 176 17-Mar-11 18-Nov-11 463<br />
ENC0059C10 1.2.3.5.4 ENC Thermal Design - Start Phase 3 0 17-Mar-11 463<br />
ENC0059C20 1.2.3.5.4 ENC Thermal Final Design Review (FDR) 0 18-Nov-11 463<br />
ENC0059D 1.2.3.5.4 ENC Thermal Procurement & Fab of long lead items (Plate Coil Etc....) 240 17-Mar-11 16-Feb-12 803<br />
ENC0065 1.2.3.5.4 ENC Thermal Design Review Proposals 20 10-Dec-09 06-Jan-10 463<br />
ENC0067 1.2.3.5.4 ENC Thermal <strong>Construction</strong> Contract Award 0 01-Jun-12 463<br />
ENC0085 1.2.3.5.4 ENC Thermal Design Contract Negotiations 30 07-Jan-10 17-Feb-10 463<br />
ENC0095 1.2.3.5.4 ENC Thermal <strong>Construction</strong> Issue RFP 0 18-Nov-11 463<br />
ENC0125 1.2.3.5.4 ENC Thermal <strong>Construction</strong> Receive Proposal Responses 0 27-Jan-12 463<br />
ENC0135 1.2.3.5.4 ENC Thermal <strong>Construction</strong> Review Proposals 20 27-Jan-12 24-Feb-12 463<br />
ENC0140 1.2.3.5.4 ENC Thermal Systems Procurement & Fab 264 01-Jun-12 06-Jun-13 463<br />
ENC0142 1.2.3.5.4 ENC Thermal Systems Factory Packaging 15 06-Jun-13 27-Jun-13 463<br />
ENC0144 1.2.3.5.4 ENC Thermal Systems Shipment from Contractor to Hawaiian Port 40 27-Jun-13 22-Aug-13 463<br />
ENC0145 1.2.3.5.4 ENC Thermal <strong>Construction</strong> Contract Negotiations 30 24-Feb-12 06-Apr-12 463<br />
ENC0146 1.2.3.5.4 ENC Thermal Systems Offloading @ Port & Transport to Storage Yard 5 22-Aug-13 29-Aug-13 463<br />
ENC0150 1.2.3.5.4 ENC Thermal Systems Fab, Assy & Test @ Site 180 04-Aug-14 02-Mar-15 411<br />
ENC0220 1.2.3.5.4 ENC Thermal Design Recommendation for Contract Award 0 07-Jan-10 463<br />
ENC0230 1.2.3.5.4 ENC Thermal <strong>Construction</strong> Vendor Proposal Period 50 18-Nov-11 27-Jan-12 463<br />
ENC0260 1.2.3.5.4 ENC Thermal <strong>Construction</strong> Recommendation for Contract Award 0 24-Feb-12 463<br />
Ancillary Mechanic Mechanical Equipment 626 01-Jun-12 27-Oct-14 161<br />
ENC0160 1.2.3.5.5 ENC Ancillary Mechanical Equipment Procurement & Fab 100 01-Jun-12 18-Oct-12 75<br />
ENC0165 1.2.3.5.5 ENC Ancillary Mechanical Equipment Factory Assy & Test 120 19-Oct-12 04-Apr-13 75<br />
ENC0175 1.2.3.5.5 ENC Ancillary Mechanical Equipment Fab, Assy & Test @ Site 180 11-Oct-13 02-Aug-14 0<br />
ENC0255 1.2.3.5.5 ENC Ancillary Mechanical Equipment - Alt Cable, Dome Crane Complete 0 04-Aug-14 0<br />
ENC0275 1.2.3.5.5 ENC Ancillary Mechanical Equipment Fab, Assy & Test Complete 60 04-Aug-14 27-Oct-14 161<br />
<strong>Enclosure</strong> Control System 1031 15-Apr-10 27-Mar-14 312<br />
ENC0047 1.2.3.5.6 Common Services Site Release 1.0 Required at ECS Contrator 0 17-Mar-11 882<br />
ENC0066 1.2.3.5.6 ECS Contract Approval (AURA and NSF) 40 02-Sep-10 27-Oct-10 983<br />
ENC0077 1.2.3.5.6 ECS Contract Award 0 27-Oct-10 983<br />
ENC0155 1.2.3.5.6 ECS Issue RFP 0 15-Apr-10 983<br />
ENC0181 1.2.3.5.6 TCS Interface Simulator Required at <strong>Enclosure</strong> Contractor 0 18-Nov-11 707<br />
ENC0185 1.2.3.5.6 ECS Procurement & Fab 140 18-Nov-11 31-May-12 707<br />
ENC0188 1.2.3.5.6 TCS Functional Simulator Required at <strong>Enclosure</strong> Contractor 0 01-Jun-12 707<br />
ENC0190 1.2.3.5.6 ECS Factory Assy & Test 80 03-Aug-12 22-Nov-12 662<br />
ENC0195 1.2.3.5.6 ECS Receive Proposal Responses 0 24-Jun-10 983<br />
ENC0199 1.2.3.5.6 Start ECS Assy & Test @ Site 0 28-Jun-13 351<br />
ENC0200 1.2.3.5.6 ECS Assy & Test @ Site 120 11-Oct-13 27-Mar-14 276<br />
ENC0205 1.2.3.5.6 ECS Review Proposals 20 24-Jun-10 21-Jul-10 983<br />
ENC0245 1.2.3.5.6 ECS Contract Negotiations 30 22-Jul-10 01-Sep-10 983<br />
ENC0280 1.2.3.5.6 ECS Vendor Proposal Period 50 15-Apr-10 23-Jun-10 983<br />
ENC0300 1.2.3.5.6 ECS Recommendation for Contract Award 0 22-Jul-10 983<br />
Enclousure Local In Interlock Contro Controller 921 16-Sep-10 27-Mar-14 312<br />
ENC0210 1.2.3.5.7 ENC LIC Procurement & Fab 140 01-Jun-12 13-Dec-12 75<br />
ENC0212 1.2.3.5.7 GIS Simulator Required at <strong>Enclosure</strong> Contractor 0 16-Sep-10 661<br />
ENC0215 1.2.3.5.7 ENC LIC Factory Assy & Test 80 14-Dec-12 04-Apr-13 75<br />
ENC0225 1.2.3.5.7 ENC LIC Assy & Test @ Site 120 11-Oct-13 27-Mar-14 312<br />
<strong>Enclosure</strong> Tools an and Equipment 565 01-Jun-12 31-Jul-14 222<br />
ENC0235 1.2.3.5.8 ENC Tools & Equipment Procurement & Fab 100 01-Jun-12 18-Oct-12 75<br />
ENC0240 1.2.3.5.8 ENC Tools & Equipment Factory Assy & Test 120 19-Oct-12 04-Apr-13 75<br />
ENC0250 1.2.3.5.8 ENC Tools & Equipment Assy & Test @ Site 210 11-Oct-13 31-Jul-14 222<br />
Q Q Q Q Q Q Q3 Q Q Q Q Q4 Q Q Q3 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q<br />
2009 2010 2011 2012 2013 2014 2015 2016 2017 8<br />
ENC Thermal Design Issue RFP<br />
ENC Thermal Design Contract Approval (AURA and NSF)<br />
Approval of Lower <strong>Enclosure</strong> Interface Design <strong>by</strong> <strong>Enclosure</strong> Contractor<br />
ENC Thermal Design Receive Proposal Responses<br />
ENC Thermal <strong>Construction</strong> Contract Approval (AURA and NSF)<br />
ENC Thermal Design Contract Award<br />
ENC Thermal Planning and Development<br />
ENC Thermal Preliminary Design Effort<br />
ENC Thermal Contractor Provides Loads & Interface Requirements to Building A/E Contractor<br />
ENC Thermal PDR<br />
ENC Thermal Final Design Effort<br />
ENC Thermal Design - Start Phase 3<br />
ENC Thermal Final Design Review (FDR)<br />
ENC Thermal Procurement & Fab of long lead items (Plate Coil Etc....)<br />
ENC Thermal Design Review Proposals<br />
ENC Thermal <strong>Construction</strong> Contract Award<br />
ENC Thermal Design Contract Negotiations<br />
ENC Thermal <strong>Construction</strong> Issue RFP<br />
ENC Thermal <strong>Construction</strong> Receive Proposal Responses<br />
ENC Thermal <strong>Construction</strong> Review Proposals<br />
ENC Thermal Systems Procurement & Fab<br />
ENC Thermal Systems Factory Packaging<br />
ENC Thermal Systems Shipment from Contractor to Hawaiian P<br />
ENC Thermal <strong>Construction</strong> Contract Negotiations<br />
ENC Thermal Systems Offloading @ Port & Transport to Storag<br />
ENC Thermal Systems Fab, Assy & Test<br />
ENC Thermal Design Recommendation for Contract Award<br />
ENC Thermal <strong>Construction</strong> Vendor Proposal Period<br />
ENC Thermal <strong>Construction</strong> Recommendation for Contract Award<br />
27-Oct-14<br />
ENC Ancillary Mechanical Equipment Procurement & Fab<br />
ENC Ancillary Mechanical Equipment Factory Assy & Test<br />
ENC Ancillary Mechanical Equipment Fab, Assy &<br />
ENC Ancillary Mechanical Equipment - Alt Cable,<br />
ENC Ancillary Mechanical Equipment Fab, Ass<br />
27-Mar-14<br />
Common Services Site Release 1.0 Required at ECS Contrator<br />
ECS Contract Approval (AURA and NSF)<br />
ECS Contract Award<br />
ECS Issue RFP<br />
TCS Interface Simulator Required at <strong>Enclosure</strong> Contractor<br />
ECS Procurement & Fab<br />
TCS Functional Simulator Required at <strong>Enclosure</strong> Contractor<br />
ECS Factory Assy & Test<br />
ECS Receive Proposal Responses<br />
Start ECS Assy & Test @ Site<br />
ECS Assy & Test @ Site<br />
ECS Review Proposals<br />
ECS Contract Negotiations<br />
ECS Vendor Proposal Period<br />
ECS Recommendation for Contract Award<br />
27-Mar-14<br />
ENC LIC Procurement & Fab<br />
GIS Simulator Required at <strong>Enclosure</strong> Contractor<br />
ENC LIC Factory Assy & Test<br />
ENC LIC Assy & Test @ Site<br />
31-Jul-14<br />
ENC Tools & Equipment Procurement & Fab<br />
ENC Tools & Equipment Factory Assy & Test<br />
ENC Tools & Equipment Assy & Test @ Site