UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

ATTUAZIONE ED EVOLUZIONE<br />

DELLA NORMATIVA IPPC:<br />

INDICAZIONI DALLA<br />

ESPERIENZA DELLA REGIONE<br />

EMILIA-ROMAGNA<br />

Eugenio Lanzi - Regione Emilia-Romagna<br />

(elanzi@regione.emilia-romagna.it)<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Agenda<br />

?Attuazione e revisione <strong>della</strong> <strong>di</strong>rettiva IPPC;<br />

?Il rilascio dell’AIA a livello italiano: novita’?;<br />

?Qualche contribuito dall’Emilia-Romagna.<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Contenuti <strong>della</strong> comunicazione<br />

PROGRESSI NELLA IMPLEMENTAZIONE<br />

IMPATTO SOCIO-ECONOMICO<br />

SCAMBIO DI INFORMAZIONI SULLE BAT E<br />

PROCESSO DI SIVIGLIA<br />

DIFFICOLTà ATTUATIVE DERIVANTI DA INTERPRETAZIONI E<br />

DEFINIZIONI<br />

FUTURI SVILUPPI<br />

VALORI LIMITE NELLA COMUNITà<br />

IL REGISTRO DELLE EMISSIONI<br />

COLLEGAMENTO AGLI ALTRI STRUMENTI<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

COMMISSION OF THE EUROPEAN COMMUNITIES<br />

Brussels, 3 November 2005<br />

COM (2005) 540 final<br />

REPORT FROM THE COMMISSION TO THE COUNCIL AND THE EUROPEAN<br />

PARLIAMENT<br />

Report of the Commission on the implementation of Directive<br />

96/61/EC concerning<br />

integrat<strong>ed</strong> pollution prevention and control<br />

(Text with EEA relevance)<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Introduction to the first meeting of<br />

the IPPC Review Advisory Group<br />

DG ENV, 13 January 2006<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

2005 IPPC Implementation<br />

Report - Key fin<strong>di</strong>ngs<br />

? Delays in transposition, ongoing<br />

infringement proc<strong>ed</strong>ures (8 MS)<br />

? Limit<strong>ed</strong> progress in the implementation of<br />

the Directive and ne<strong>ed</strong> to accelerate<br />

process in view of Oct 2007 deadline<br />

? Description of specific implementation<br />

issues<br />

=> IPPC IMPLEMENTATION ACTION PLAN<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

IPPC Implementation<br />

Action Plan<br />

1. Full<br />

transposition<br />

2. Monitoring<br />

progress 2007<br />

5. Guidance<br />

4. Finalisation<br />

BREFs<br />

3.Implementation<br />

assessment<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Why a Review?<br />

IPPC<br />

Implementation<br />

Action Plan<br />

Thematic<br />

strategies<br />

Better<br />

regulation<br />

COM(2005) 535<br />

IPPC Review<br />

Lisbon<br />

agenda<br />

=> study<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Examine scope for legislative<br />

streamlining<br />

IPPC Directive<br />

Landfill Directive<br />

Waste<br />

Incineration<br />

Directive<br />

EIA Directive<br />

=> Study<br />

Emission<br />

Tra<strong>di</strong>ng<br />

Directive<br />

LCP Directive<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Waste<br />

Soil<br />

Air<br />

Develop and implement outcomes<br />

of the Thematic Strategies<br />

Clarification/extension of IPPC application to<br />

waste management?<br />

Soil contamination monitoring (baseline report,<br />

monitoring during operation, final status<br />

report) ?<br />

Enhance rehabilitation obligations?<br />

Intensive cattle rearing? => Air Unit study<br />

20-50 MW combustion installations?<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Encourage industry to go<br />

beyond regulatory compliance<br />

? Incentives for innovation and enhanc<strong>ed</strong><br />

deployment of environmental technologies<br />

? Economic instruments (tra<strong>di</strong>ng, taxes ...)<br />

? Environmental management systems<br />

? Administrative relief<br />

? Voluntary schemes<br />

=> Study<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

How?<br />

IPPC Advisory<br />

Group<br />

Group (input stu<strong>di</strong>es)<br />

IMPEL (enforcement)<br />

IPPC<br />

Experts Group<br />

(policy orientation)<br />

Stakeholder<br />

Hearing 2006<br />

(public debate)<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Summary projects in 2006<br />

Implementation (ENTEC)<br />

Competitiveness (Carl Bro)<br />

Review process<br />

Env benefits<br />

(EEA)<br />

Streamlining (ENTEC)<br />

Impacts of technical<br />

Amendments (IEEP)<br />

Beyond<br />

Compliance (DHV)<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Possible Outputs, Timing?<br />

? Conclusion of review in 2007 with longterm<br />

vision on industrial emissions<br />

control<br />

? Legislative proposal if appropriate, bas<strong>ed</strong><br />

on an impact assessment, unlikely to<br />

come into effect until ~ 2012 at earliest<br />

? No change in short term, 2007 deadline<br />

unaffect<strong>ed</strong>!<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Assessment of the Implementation by the<br />

Member States of the IPPC Directive<br />

Advisory Group Meeting<br />

Friday 13 th January 2006<br />

Mark Watson<br />

Creating the environment for business<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Permit Selection Matrix<br />

30 permits select<strong>ed</strong> with 30 in reserve<br />

Iron &<br />

Steel<br />

Non-<br />

Ferrous<br />

Metal<br />

Cement<br />

Chemicals<br />

Textiles<br />

Pulp &<br />

Paper<br />

Total<br />

UK<br />

2<br />

2<br />

2<br />

6<br />

France<br />

2<br />

2<br />

2<br />

6<br />

Germany<br />

2<br />

2<br />

2<br />

6<br />

Sw<strong>ed</strong>en<br />

2<br />

2<br />

4<br />

Spain<br />

2<br />

2<br />

2<br />

6<br />

Italy<br />

2<br />

2<br />

2<br />

6<br />

Portugal<br />

2<br />

2<br />

4<br />

Greece<br />

2<br />

2<br />

4<br />

Hungary<br />

2<br />

2<br />

4<br />

Poland<br />

2<br />

2<br />

2<br />

6<br />

Czech<br />

Republic<br />

2<br />

2<br />

4<br />

Lithuania<br />

2<br />

2<br />

4<br />

Total<br />

10<br />

10<br />

10<br />

10<br />

10<br />

10<br />

60<br />

Creating the environment for business<br />

10<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

CARL BRO GROUP<br />

IPPC & Competitiveness<br />

Advisory Group Meeting<br />

13 January 2006<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

EEA assessment of environmental<br />

benefits due to the implementation of<br />

the IPPC Directive (case-study approach)<br />

IPPC Review Advisory Group meeting<br />

13 January 2006<br />

Eva Goossens<br />

1<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Complex area<br />

• Directive<br />

Case-study approach<br />

for IPPC Directive evaluation<br />

? Wide range of industrial activities<br />

? Proc<strong>ed</strong>ural Directive without numerical targets<br />

? Few data available on analysis of IPPC<br />

? New way of thinking ne<strong>ed</strong><strong>ed</strong> for<br />

? Data collection<br />

? Assessment methodology<br />

Case-study approach<br />

• Limit<strong>ed</strong> number of sectors<br />

• 1st case-study: cement sector<br />

3<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Streamlining industrial emissions<br />

legislation<br />

Caspar Corden (Entec)<br />

Andrew Farmer (IEEP)<br />

IPPC Review Advisory Group meeting 13 January 2006<br />

Creating the environment for business<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Examples of possible streamlining<br />

scenarios<br />

? Only BAT-bas<strong>ed</strong> permitting<br />

? More use of sectoral <strong>di</strong>rectives<br />

? Single framework <strong>di</strong>rective on industrial emissions<br />

(e.g. IPPC plus WID, SED, LCPD)<br />

? Broader integration on industry regulation<br />

? Facilitate Member State tra<strong>di</strong>ng in NO x<br />

and SO 2<br />

? EU-level emission tra<strong>di</strong>ng for industrial NO x<br />

and SO 2<br />

Creating the environment for business<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Data gathering and impact assessment for a<br />

possible technical review of the IPPC<br />

Directive<br />

An introduction to the project<br />

Patrick ten Brink, IEEP<br />

Support<strong>ed</strong> by<br />

Peter Vercaemst, VITO and Shailendra Mudgal, Bio<br />

On behalf of the project team: IEEP, VITO, Bio, Ecologic, IVM<br />

IPPC Advisory Group Meeting<br />

13 January 2006<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

A Amendments to permitting and monitoring provisions<br />

1 A.1 ELV<br />

2 A.2 Clarification of “perio<strong>di</strong>cally” for reconsidering permit con<strong>di</strong>tions<br />

3 A.3 Clarification of “perio<strong>di</strong>cally” for monitoring reports<br />

4 A.4 Obligation to perform regular inspections<br />

5 A.5 Requirements re. <strong>di</strong>scharges to water<br />

B Amendments on the exchange of information on BAT<br />

6 B.1 Clarification of onus on MS in exchange of information on BAT<br />

C Amendments to Annex I of the IPPC Directive<br />

7 C.1<br />

Lower threshold for combustion installations in energy industries<br />

from 50 to 20 MW thermal input<br />

8 C.2 Intensive aquaculture<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Amendments to be cover<strong>ed</strong> in possible future<br />

work<br />

Other possible amendments to Annex 1:<br />

C Amendments to Annex I of the IPPC Directive<br />

C.2 Extension of the current IPPC activity definition<br />

9 a Any gasification and liquefaction (not just coal)<br />

10 b Production of any primary wood products (not just paper and board)<br />

11 c Coal rolling mills<br />

12 d Manufacture of coal fuel products and solid smokeless fuel<br />

13 e Independently operat<strong>ed</strong> industrial wastewater treatment plants<br />

14 f Industrial plants for the preservation of wood and wood products<br />

15 h Installations for the buil<strong>di</strong>ng of, and painting of or removal of paint from ships<br />

… and other amendments that may arise from other potential<br />

contributors and other activities (e.g IEG work on guidance)<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Potential Amendment A1: ELV<br />

Issue<br />

‘The permit shall include emission limit values for pollutants, in particular,<br />

those list<strong>ed</strong> in in Annex III, likely to be emitt<strong>ed</strong> from the installation<br />

concern<strong>ed</strong> in significant quantities, having regard to their nature and<br />

their potential to transfer pollution from one m<strong>ed</strong>ium to another (water,<br />

air and land). (…)’ [art 9(3)]<br />

‘The permit shall contain suitable release monitoring requirements,<br />

specifying measurement methodology and frequency, evaluation<br />

proc<strong>ed</strong>ure and an obligation to supply the competent authority with<br />

data requir<strong>ed</strong> for checking compliance with the permit. (…)’ [art 9(5)]<br />

Problem Definition<br />

• Difficult to compare ELVs in permits across Europe.<br />

• Currently ELVs often set in terms of e.g. mg/Nm3 – could it be better<br />

present<strong>ed</strong> e.g. by g/tonne?<br />

• Improving information could lead to benefits of transparency, use in<br />

benchmarking, and encourage eco-efficiency.<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Potential Amendment A2:<br />

permit review frequency<br />

Issue<br />

‘Member States shall take the necessary measures to ensure that<br />

competent authorities perio<strong>di</strong>cally reconsider and, where necessary,<br />

update permit con<strong>di</strong>tions.’ [art. 13(1)]<br />

Problem definition<br />

• Frequency of permit renewal is not defin<strong>ed</strong> – either as a method to<br />

determine appropriate time periods or as fix<strong>ed</strong> timescales for renewal<br />

• Wide range of practices in <strong>di</strong>fferent MS.<br />

• Some countries are concern<strong>ed</strong> that others are unsuitably gaining by low<br />

permit review frequency – in terms of lower costs to business and later<br />

upgrade to latest BAT<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Potential Amendment A3:<br />

monitoring report frequency<br />

Issue<br />

‘Member States shall take the necessary measures to ensure that:<br />

(…) the operator regularly informs the competent authority of the results of<br />

the monitoring of releases and without delay of any incident or accident<br />

significantly affecting the environment (…)’ [art 14]<br />

Problem Definition<br />

• Monitoring report frequency is not defin<strong>ed</strong><br />

• IPPC reporting is complicat<strong>ed</strong> by other reporting and links to initiatives<br />

to r<strong>ed</strong>uce reporting requirements<br />

• There are arguments that the current data report<strong>ed</strong> is insufficient and<br />

that more data on actual emissions could usefully be requir<strong>ed</strong>.<br />

• How to amend to ensure that it respects/implements Aarhus?<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Potential Amendment A4:<br />

inspection frequency<br />

Issue<br />

‘‘Member States shall take the necessary measures to ensure that:<br />

(…) operators of installations afford the representatives of the competent<br />

authority all necessary assistance to enable them to carry out any<br />

inspections within the installation, to take samples and to gather any<br />

information necessary for the performance of their duties for the<br />

purposes of this Directive.’ [art 14]<br />

Problem Definition<br />

• Inspections should be carri<strong>ed</strong> out regularly to assess whether<br />

installations conform with permit requirements<br />

• Early IMPEL l<strong>ed</strong> work rais<strong>ed</strong> the issue that the quality of inspections (inc.<br />

frequency) was very variable across Europe and l<strong>ed</strong> to the creation of<br />

the Minimum Criteria on Inspections.<br />

• IPPC sets out no precise inspection requirement (unlike Seveso), so<br />

some amendment may be appropriate.<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Potential Amendment A5<br />

Requirement re <strong>di</strong>scharges to water<br />

Issue<br />

Introduction of explicit requirements relat<strong>ed</strong> to <strong>di</strong>scharges to water from<br />

IPPC installations of priority substances and priority hazardous<br />

substances, as specifi<strong>ed</strong> by Annex X of the Water Framework Directive<br />

2000/60/EC.<br />

Problem Definition<br />

• Clear link between IPPC Directive and WFD through the <strong>di</strong>scharges to<br />

water from the installation.<br />

• To ensure that the link is optimal, a permit application could have more<br />

information on <strong>di</strong>scharges and the permit could include con<strong>di</strong>tions to<br />

ensure compliance.<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Issue<br />

Potential amendment B1:<br />

BAT information exchange<br />

Cf. Art 16(2): ‘The Commission shall organise an exchange of information<br />

between Member States and the industries concern<strong>ed</strong> on best<br />

available techniques, associat<strong>ed</strong> monitoring, and developments in<br />

them.’<br />

Problem definition<br />

• Provision of information for the BREFs, e.g. on emissions data, is<br />

variable<br />

• Data limitations affect ability to draw timely BAT conclusions<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Potential Amendment C1<br />

Lower thresholds for power plant 50 to<br />

20MW<br />

Issue<br />

Categories of industrial activities referr<strong>ed</strong> to in Article 1<br />

1. Energy industries<br />

1.1. Combustion installations with a rat<strong>ed</strong> thermal input exce<strong>ed</strong>ing 50 MW<br />

(1) [Annex I]<br />

Problem Definition<br />

• Power plants in the range of 20MW to 50MW currently fall outside<br />

IPPC, but have been identifi<strong>ed</strong> as significant emission sources in<br />

CAFE work and are under ET scheme<br />

• Should they be includ<strong>ed</strong> in IPPC?<br />

• A better understan<strong>di</strong>ng of costs is ne<strong>ed</strong><strong>ed</strong>– how many installations<br />

involv<strong>ed</strong>, what level costs at an average installation, overall etc.<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Issue<br />

Potential amendment C2: Intensive<br />

aquaculture<br />

Potential ad<strong>di</strong>tion of intensive aquaculture to the Annex I list of cover<strong>ed</strong><br />

activities, eg with a production capacity of 1,000 tonnes of fish or<br />

shellfish per year.<br />

Problem definition<br />

Aquaculture can cause environmental degradation, e.g.:<br />

• Biological Pollution: Fish that escape from aquaculture facilities may harm<br />

wild fish populations;<br />

• Organic Pollution and Eutrophication: <strong>di</strong>scharges of fish wastes and uneaten<br />

fe<strong>ed</strong> can bring local nutrient loa<strong>di</strong>ng;<br />

• Chemical Pollution: use of antibiotics and pesticides may bring antibiotic<br />

resistance and harm to non-target species;<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Beyond Regulatory Compliance<br />

Incentives to improve the environmental<br />

performance of IPPC installations<br />

IPPC Review EC<br />

EC DG Environment<br />

E.P.Schenk Januari 2006<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Beyond Regulatory Compliance?<br />

BRC = Companies that achieve higher environmental performance than requier<strong>ed</strong> by their IPPC<br />

permits<br />

Examples are companies that are using<br />

– EMS (eg EMAS/ISO 14001 (Akzo Sassenheim NL)) or<br />

– product stewardship (VNCI, Chemical Industry Netherlands; U.S.)<br />

to perform beyond the basic requirements that are in their permit.<br />

Other tools or instruments are:<br />

– covenants, tax reliefs, <strong>di</strong>fferentiation in enforcement, name and fame publicity, etc.<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

LE NORME DI<br />

APPLICAZIONE<br />

DELL’IPPC IN ITALIA<br />

DIRETTIVA 96/61/CE<br />

D.Lgs.<br />

372/99<br />

impianti<br />

esistenti<br />

D.Lgs.<br />

59/2005<br />

integrale<br />

recepimento<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Il quadro <strong>di</strong> riferimento tracciato dal D.lgs<br />

59/05 non è ancora definitivo poiché<br />

mancano i decreti attuativi che riguardano:<br />

- il rilascio dell’AIA ad impianti soggetti a<br />

più autorità competenti;<br />

- la definizione del tariffario;<br />

- l’adozione delle linee guida nazionali;<br />

- la possibilità <strong>di</strong> fissare “Requisiti<br />

generali” per talune categorie <strong>di</strong> impianti.<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

D.lgs 14 Aprile 2006 n. 152 “NORME IN MATERIA AMBIENTALE”<br />

Parte II^: : Proc<strong>ed</strong>ure per la VAS, per la VIA e per l’IPPCl<br />

Art. 34: relazioni tra VIA e IPPC e abroga il comma 9 dell’art. 5 del D.Lgs. . 59/05,<br />

relativo alla Commissione Istruttoria IPPC<br />

Per le opere sottoposte a Via che rientrano nel campo <strong>di</strong> applicazione del Dlgs<br />

59/05 è facoltà del proponente ottenere che la proc<strong>ed</strong>ura <strong>di</strong> Via sia integrata nel<br />

proc<strong>ed</strong>imento per il rilascio dell’AIA con le seguenti conseguenze:<br />

a) lo stu<strong>di</strong>o <strong>di</strong> impatto ambientale dovrà contenere anche le informazioni<br />

richieste nella proc<strong>ed</strong>ura per l'AIA;<br />

b) le forme <strong>di</strong> informazione e partecipazione stabilite per la Via<br />

sostituiscono, ad ogni effetto, quelle del Dlgs 59/2005;<br />

c) il proc<strong>ed</strong>imento per l‘AIA l<br />

viene sospeso;<br />

d) l'istruttoria tecnica viene condotta dagli organi preposti all'istruttoria<br />

sulla domanda AIA;<br />

Una volta conclusa la proc<strong>ed</strong>ura <strong>di</strong> valutazione ambientale, il giu<strong>di</strong>zio verrà<br />

comunicato all'autorità competente per l‘AIA l<br />

che, tenendone conto, riprenderà<br />

il proprio proc<strong>ed</strong>imento.<br />

Il richi<strong>ed</strong>ente versa un unico corrispettivo per il giu<strong>di</strong>zio <strong>di</strong> compatibilitc<br />

ompatibilità e per<br />

l’AIA<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

D.lgs 14 Aprile 2006 n. 152 “NORME IN MATERIA AMBIENTALE”<br />

Risolve la interrelazione virtuosa fra i tre strumenti?<br />

VAS<br />

VIA<br />

IPPC<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

PC<br />

PR<br />

RE<br />

MO<br />

FE<br />

BO<br />

RA<br />

1 Attività energetiche<br />

2 Produzione e trasformazione metalli<br />

FC<br />

RN<br />

3 Industria dei prodotti minerali<br />

4 Industria chimica<br />

5 Gestione dei rifiuti<br />

6 Altre attività<br />

6.6 Allevamenti<br />

N° impianti >200<br />

100 < N° impianti


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Stima degli Impianti <strong>di</strong> riferimento per categoria<br />

GENNAIO 2005<br />

CATEGORIA IPPC<br />

1 Attività energetiche<br />

2 Produzione e trasformazione metalli<br />

3 Industria dei prodotti minerali<br />

4 Industria chimica<br />

5 Gestione dei rifiuti<br />

6 Altre categorie<br />

6.6 Allevamenti intensivi<br />

Totale complessivo<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

N° AZIENDE TOTALE PER<br />

PC PR RE MO BO FE RA FC RN CATEGORIA<br />

4 3 2 1 0 2 3 0 0 15<br />

5 8 25 20 33 5 4 13 6 119<br />

5 7 51 78 16 2 9 2 5 175<br />

1 1 2 6 4 5 15 0 1 35<br />

7 16 18 31 12 14 23 18 4 143<br />

17 29 21 27 17 10 18 24 1 164<br />

39 22 63 67 21 16 82 160 16 486<br />

78 86 182 230 103 54 154 217 33 1137<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

La Commissione ha un messaggio<br />

chiaro per gli Stati membri e i paesi<br />

can<strong>di</strong>dati:<br />

è possibile raggiungere un livello<br />

elevato <strong>di</strong> tutela dell'ambiente<br />

(obiettivo essenziale <strong>della</strong> <strong>di</strong>rettiva)<br />

soltanto se le autorità responsabili<br />

compiono gli sforzi necessari per<br />

attuare correttamente la<br />

legislazione e si impegnano a<br />

interagire in maniera costruttiva con<br />

i gestori degli impianti e con gli altri<br />

soggetti interessati.<br />

Per la <strong>attuazione</strong> operativa <strong>della</strong> LR 21/04 si è seguito il metodo del<br />

confronto continuo con i soggetti principali coinvolti: Associazioni<br />

Impren<strong>di</strong>toriali, Autorità Competenti, Impianti pilota, ARPA<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


<strong>Ferrara</strong> 26 Aprile 2006<br />

UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Valutazione ambientale integrata<br />

Risposta all’inosservanza<br />

degli accor<strong>di</strong><br />

Applicazione e<br />

monitoraggio<br />

Implementazione<br />

delle con<strong>di</strong>zioni<br />

<strong>della</strong><br />

autorizzazione<br />

Il ciclo<br />

Discussione negoziazione per<br />

autorizzatorio •rilascio<br />

Consegna <strong>della</strong> autorizzazione<br />

Accordo sulle con<strong>di</strong>zioni<br />

<strong>della</strong> autorizzazione<br />

•rinnovo<br />

•riesame<br />

autorizzazioni<br />

Iter autorizzativo<br />

Partecipazione del<br />

pubblico e stima<br />

degli esperti<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Si confronta<br />

Controlla<br />

Azienda<br />

Dati<br />

ARPA<br />

Pone in atto<br />

Richi<strong>ed</strong>e AIA<br />

Invia commenti<br />

Autorizzazione<br />

Integrata<br />

Ambientale<br />

Informa<br />

Supporta tecnicamente<br />

Provincia<br />

Emana<br />

Commenta<br />

Pubblico e<br />

Pubblico<br />

interessato<br />

Informa<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Delibera GR 29 Novembre 2004 n. 2411 “Approvazione delle guide e delle relative modulistiche per la<br />

r<strong>ed</strong>azione <strong>della</strong> domanda <strong>di</strong> AIA”;<br />

Delibera GR 6 Dicembre 2004 n. 2523 “Approvazione <strong>della</strong> sesta mo<strong>di</strong>fica calendario scadenza<br />

presentazione domande autorizzazione integrata ambientale. Abrogazione delibere 1240/02, 38/03,<br />

1859/03, 1658/04, 1946/04 (D.lgs 372/99, art. 4, comma 3)”;<br />

Delibera GR 11 Aprile 2005 n. 667 “Modalità per la determinazione da parte delle Province degli<br />

anticipi delle spese istruttorie per il rilascio <strong>della</strong> Autorizzazione Integrata Ambientale (AIA)”.<br />

Due circolari regionali che hanno affrontato gli aspetti relativi a:<br />

– Campo <strong>di</strong> applicazione <strong>della</strong> <strong>normativa</strong><br />

– Ruolo del SUAP per il rilascio dell’AIA<br />

– Presentazione <strong>della</strong> domanda <strong>di</strong> AIA<br />

– Proc<strong>ed</strong>imento <strong>di</strong> rilascio dell’AIA<br />

– Schema dell’AIA e sua entrata in efficacia<br />

– Assetto autorizzatorio - Mo<strong>di</strong>fiche degli impianti - Proc<strong>ed</strong>ura <strong>di</strong> riesame.<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Dal D.lgs 59/05: due novità su cui lavorare<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

ALLEGATO VI –<br />

FINALITà DELL'OSSERVATORIO IPPC<br />

c) scambio <strong>di</strong> informazione a livello<br />

nazionale <strong>di</strong> cui all'art. 14, comma 4;<br />

d) adempimenti in materia <strong>di</strong><br />

comunicazione previsti dall'art. 12, comma<br />

3, dall'art. 14, commi 1 e 2 e dall'art. 15,<br />

commi 1 e 2;<br />

e) aggiornare il quadro dello stato <strong>di</strong><br />

<strong>attuazione</strong> nazionale e comunitario <strong>della</strong><br />

<strong>di</strong>sciplina in materia <strong>di</strong> prevenzione e<br />

riduzione integrata dell'inquinamento<br />

anche al fine <strong>di</strong> renderlo accessibile al<br />

pubblico.<br />

Art. 14. - Scambio <strong>di</strong> informazioni<br />

3. Il Ministero dell'ambiente e <strong>della</strong> tutela del<br />

territorio, <strong>di</strong> intesa con il Ministero delle<br />

attività produttive, con il Ministero <strong>della</strong><br />

salute e con la Conferenza permanente per<br />

i rapporti tra lo Stato, le regioni e le<br />

province autonome <strong>di</strong> Trento e <strong>di</strong> Bolzano,<br />

provv<strong>ed</strong>e ad assicurare la partecipazione<br />

dell'Italia allo scambio <strong>di</strong> informazioni<br />

organizzato dalla Commissione europea<br />

relativamente alle migliori tecniche<br />

<strong>di</strong>sponibili e al loro sviluppo, nonché alle<br />

relative prescrizioni in materia <strong>di</strong> controllo,<br />

e a rendere accessibili i risultati <strong>di</strong> tale<br />

scambio <strong>di</strong> informazioni. Le modalità <strong>di</strong> tale<br />

partecipazione, in particolare, dovranno<br />

consentire il coinvolgimento delle autorità<br />

competenti in tutte le fasi ascendenti dello<br />

scambio <strong>di</strong> informazioni.<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Dal D.lgs 152/06: un rinvio …………..<br />

ARTICOLO 51<br />

Regolamenti e norme tecniche<br />

integrative – Autorizzazione unica<br />

ambientale per le piccole imprese<br />

5. Con successivo decreto,<br />

adottato dal Ministro dell’ambiente e<br />

<strong>della</strong> tutela del territorio, <strong>di</strong> concerto<br />

con il Ministro dell’economia e delle<br />

finanze e con il Ministro delle attività<br />

produttive, si provv<strong>ed</strong>erà ad accorpare<br />

in un unico provv<strong>ed</strong>imento le <strong>di</strong>verse<br />

autorizzazioni ambientali nel caso <strong>di</strong><br />

impianti non rientranti nel campo <strong>di</strong><br />

applicazione del decreto legislativo 18<br />

febbraio 2005, n. 59, ma sottoposti a più<br />

<strong>di</strong> una autorizzazione ambientale <strong>di</strong><br />

settore.<br />

Tipologia degli<br />

impianti<br />

Impianti che ricadono<br />

nell’ambito <strong>di</strong> applicazione<br />

<strong>della</strong> <strong>normativa</strong> IPPC<br />

Impianti esclusi dall’ambito<br />

<strong>di</strong> applicazione <strong>della</strong><br />

<strong>normativa</strong> IPPC che per il<br />

loro esercizio necessitano <strong>di</strong><br />

più <strong>di</strong> una autorizzazione<br />

settoriale<br />

Impianti esclusi dall’ambito<br />

<strong>di</strong> applicazione <strong>della</strong><br />

<strong>normativa</strong> IPPC che per il<br />

loro esercizio necessitano <strong>di</strong><br />

una sola autorizzazione<br />

settoriale<br />

Regime autorizzatorio<br />

Autorizzazione Integrata<br />

Ambientale<br />

Autorizzazione Unica<br />

Autorizzazione Settoriale<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

Conclusione<br />

?La revisione <strong>della</strong> <strong>di</strong>rettiva IPPC lascia immutata la scadenza<br />

<strong>di</strong> Ottobre 2007 per gli impianti esistenti e prefigura un<br />

rafforzamento dell’approccio integrato <strong>ed</strong> un ampliamento del<br />

suo campo <strong>di</strong> applicazione;<br />

?Il quadro normativo italiano presenta novità ma anche ritar<strong>di</strong><br />

e <strong>di</strong>fficoltà nel superamento dell’approccio settoriale e nel<br />

rinnovamento del sistema regolatore;<br />

?L’<strong>attuazione</strong> <strong>di</strong> IPPC in Italia richi<strong>ed</strong>e <strong>di</strong> costruire rapidamente<br />

un quadro conoscitivo aggiornato sul quale sviluppare i<br />

necessari confronti e riflessioni finalizzati a fare contare <strong>di</strong><br />

più il nostro paese;<br />

?Dall’Emilia-Romagna e dai suoi oltre mille impianti IPPC può<br />

venire un contributo importante.<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi


UNIVERSITA’ DI FERRARA<br />

“NORMATIVA IPPC:Autorizzazioni Integrate Ambientali”<br />

ATTUAZIONE ED EVOLUZIONE DELLA<br />

NORMATIVA IPPC: INDICAZIONI<br />

DALLA ESPERIENZA DELLA REGIONE<br />

EMILIA-ROMAGNA<br />

Eugenio Lanzi - Regione Emilia-Romagna<br />

(elanzi@regione.emilia-romagna.it)<br />

Grazie per l’attenzione<br />

Domande?<br />

<strong>Ferrara</strong> 26 Aprile 2006<br />

Eugenio Lanzi