ID Task Name Duration Start Finish<br />
1 Projektforløb 84 days Wed 01-09-10 Mon 03-01-11<br />
2 Dagbog 84 days Wed 01-09-10 Mon 03-01-11<br />
3 Forberedelse på projektforløb 3 days Wed 01-09-10 Fri 03-09-10<br />
4 Dispositionsforslag 10 days Fri 03-09-10 Fri 17-09-10<br />
5 <strong>Statisk</strong>projekteringsrapport 3 days Fri 03-09-10 Tue 07-09-10<br />
6<br />
7 AFP workshop 3 4 hrs Tue 07-09-10 Tue 07-09-10<br />
8 Aflevering fordeling af fagområde 0 days Thu 09-09-10 Thu 09-09-10<br />
9 Endelig godkendelse af projektformular 0 days Wed 15-09-10 Wed 15-09-10<br />
10 Delaflevering: Dispositionsforslag 0 days Fri 17-09-10 Fri 17-09-10<br />
11 Projektforslag 46 days Fri 17-09-10 Fri 26-11-10<br />
12 <strong>Statisk</strong>projekteringsrapport 43,88 days Fri 17-09-10 Wed 24-11-10<br />
13 Lastfastsættelse 3 days Fri 17-09-10 Tue 21-09-10<br />
14 Overslag af dæk,væg, søjle og bjælke 8 days Wed 22-09-10 Mon 04-10-10<br />
15 Stabilitet 1 day Mon 04-10-10 Tue 05-10-10<br />
16 Robusthed 1 day Tue 05-10-10 Wed 06-10-10<br />
17 Medierampe 23 days Fri 15-10-10 Wed 24-11-10<br />
18 Tagkonstruktion 27 days Wed 06-10-10 Fri 19-11-10<br />
19 Rapport 43 days Fri 17-09-10 Tue 23-11-10<br />
20<br />
21 Ventilationsrapport 17 days Fri 17-09-10 Mon 11-10-10<br />
22 Overslag af luftskifter 7 days Fri 17-09-10 Mon 27-09-10<br />
23 Overslag af aggregat 10 days Tue 28-09-10 Mon 11-10-10<br />
24 Rapport 17 days Fri 17-09-10 Mon 11-10-10<br />
25 Tegning 15 days Mon 08-11-10 Fri 26-11-10<br />
26<br />
27 AFP workshop 4 4 hrs Fri 24-09-10 Fri 24-09-10<br />
28 Statusmøde 1 2 hrs Tue 12-10-10 Tue 12-10-10<br />
29 Delaflevering: Projektforslag 0 days Fri 26-11-10 Fri 26-11-10<br />
30 Hovedprojekt 24 days Mon 29-11-10 Thu 30-12-10<br />
31 <strong>Statisk</strong>projekteringrapport 24 days Mon 29-11-10 Thu 30-12-10<br />
32 Kerne 24 days Mon 29-11-10 Thu 30-12-10<br />
33 Tagkonstruktion 24 days Mon 29-11-10 Thu 30-12-10<br />
34 Stringerbjælke 24 days Mon 29-11-10 Thu 30-12-10<br />
35 Tegning 16 days Thu 09-12-10 Thu 30-12-10<br />
36<br />
37 Statusmøde 2 2 hrs Wed 01-12-10 Wed 01-12-10<br />
38 AFP workshop 5 4 hrs Fri 03-12-10 Fri 03-12-10<br />
39<br />
40 Delaflevering: Hovedprojekt 0 days Thu 30-12-10 Thu 30-12-10<br />
41<br />
42 Aflevering 0 days Mon 03-01-11 Mon 03-01-11<br />
43 Ophængning 1 day Tue 04-01-11 Tue 04-01-11<br />
44 Eksamen 0 days Fri 14-01-11 Fri 14-01-11<br />
Qtr 4, 2010 Qtr 1, 2<br />
September 2010 October 2010 November 2010 December 2010 January<br />
31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04<br />
09-09<br />
15-09<br />
17-09<br />
Afgangsprojekt<br />
Multimediehuset i Århus<br />
26-11<br />
Afleveret den 3. januar 2011<br />
Bilag 2<br />
w w w.easyco m puting.co m<br />
30-12<br />
Nu kopen!<br />
0<br />
Project: Tidsplan<br />
Date: Wed 29-12-10<br />
Task<br />
Split<br />
Progress<br />
Milestone<br />
Summary<br />
Project Summary<br />
External Tasks<br />
External Milestone<br />
Deadline<br />
Rammetidsplan<br />
Ingeniørhøjskolen i KBH