Scenario: Outages and LMPs (continued)<br />
G1 QSE offers 100 MW @ $30/MWh<br />
50 MW dispatched<br />
@ $ $30/MWh<br />
100 MW dispatched<br />
@ @$ $10/MWh<br />
100 100 MW Li Limit it<br />
G2 QSE offers 200 MW @ $10/MWh<br />
L1<br />
150 MW<br />
Load<br />
LMP = $30 / MWh<br />
Paid to Generators (G2)<br />
G1 ( 50 MW * $30/MWh ) = $1500<br />
G2 ( 100 MW * $10/MWh ) = $1000<br />
Charged g to Loads (L1) ( )<br />
( 150 MW * $30/MWh) = $4500<br />
<strong>Module</strong> 1 : Slide 41