Scenario: Outages and LMPs (continued)<br />

G1 QSE offers 100 MW @ $30/MWh<br />

50 MW dispatched<br />

@ $ $30/MWh<br />

100 MW dispatched<br />

@ @$ $10/MWh<br />

100 100 MW Li Limit it<br />

G2 QSE offers 200 MW @ $10/MWh<br />

L1<br />

150 MW<br />

Load<br />

LMP = $30 / MWh<br />

Paid to Generators (G2)<br />

G1 ( 50 MW * $30/MWh ) = $1500<br />

G2 ( 100 MW * $10/MWh ) = $1000<br />

Charged g to Loads (L1) ( )<br />

( 150 MW * $30/MWh) = $4500<br />

<strong>Module</strong> 1 : Slide 41