PISD 2004 <strong>School</strong> Bond Program<br />

Program Manager: Terry Page<br />

Project Manager: Nick Martin<br />

Project Architect: PDG<br />

General Contractor: Division One<br />

Project Summary<br />

Phase 3B<br />

Bid Package 18<br />

New <strong>School</strong>s and Renovations<br />

Cost Description<br />

Original<br />

Budget<br />

Budget<br />

Adjustments<br />

Current<br />

Budget<br />

Committed<br />

Costs<br />

Cost to Date<br />

Future<br />

Commitment<br />

Estimate at<br />

Completion<br />

Construction $3,900,665 ($2,080,000) $1,820,665 $1,650,409 $1,650,409 $170,256 $1,820,665<br />

Design A/E $321,229 ($34,451) $286,778 $285,057 $279,876 $1,721 $286,778<br />

FF&E $0 $0 $0 $0 $0 $0 $0<br />

Asbestos $0 $5,192 $5,192 $5,192 $5,192 $0 $5,192<br />

Construction-Other $14,797 $63,747 $78,544 $71,118 $50,731 $7,426 $78,544<br />

Project Contingency $400,465 ($255,434) $145,031 $0 $0 $145,031 $145,031<br />

Professional Services-Other $51,171 $33,185 $84,356 $81,318 $64,543 $3,038 $84,356<br />

Miscellaneous $0 $0 $0 $0 $0 $0 $0<br />

Budget<br />

Balance<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

Totals: $4,688,327 ($2,267,762) $2,420,565 $2,093,094 $2,050,751 $327,471 $2,420,565 $0<br />

Project Notes<br />

1. Major Activities:<br />

Project close out is complete.<br />

2. Key Issues and Concerns:<br />

None at this time.<br />

$2,700,000<br />

$2,430,000<br />

$2,160,000<br />

$1,890,000<br />

$1,620,000<br />

$1,350,000<br />

$1,080,000<br />

$810,000<br />

$540,000<br />

$270,000<br />

$0<br />

Current<br />

Budget<br />

Committed<br />

Costs<br />

Cost to<br />

Date<br />

Estimate at<br />

Completion<br />

Phase 3B<br />

Status Date: 10-Mar-<strong>2008</strong><br />

Page 41 of 48