CCM shall leverage projects currently underway that are planning a NOAANet-DoD enterprise<br />

network capability. [NUOPC related]<br />

Priority: (M)<br />

Advocate: JAG/CCM – [Craig Hegemann]<br />

Suspense: <strong>Spring</strong> <strong>20</strong>09 CSAB meeting or (April 1, <strong>20</strong>09).<br />

Status <strong>as</strong> <strong>of</strong> <strong>20</strong> <strong>August</strong> <strong>20</strong>09: Open.<br />

• CSAB 18 December <strong>20</strong>08. CCM h<strong>as</strong> invited Craig Hegemann to brief the current effort<br />

<strong>of</strong> a NOAAnet to DOD enterprise solution, at the next CCM telcon. The goal is to<br />

widen the scope <strong>of</strong> this project to also consider Navy and NESDIS. Review and update<br />

the status at the next CSAB telcon.<br />

• CSAB 22 January <strong>20</strong>09. Luis Cano – CCM h<strong>as</strong> a meeting scheduled for 11 Feb <strong>20</strong>09<br />

with AFWA TD, CNMOC N6, Navy TDs, NESDIS Deputy CIO, and TOC Director.<br />

Review and update the status at the next CSAB telcon.<br />

• CSAB 26 February <strong>20</strong>09. Luis Cano – CCM held the meeting and produced the Next<br />

Steps, which includes a data requirements gathering effort.<br />

• CSAB 19 March <strong>20</strong>09. Luis Cano – need to hear back from Craig Hegemann to see if<br />

he h<strong>as</strong> been in contact with the appropriate level at DISA. Review and update the status<br />

at the next CSAB meeting.<br />

• CSAB 16 April <strong>20</strong>09. JAG/CCM recommends keeping this action open. This action<br />

item is being actively worked and an enterprise solution timeline will be presented at the<br />

<strong>Spring</strong> <strong>COPC</strong>.<br />

• CSAB 18 June <strong>20</strong>09. Ken Barnett – held a successful meeting with DISA and CCM at<br />

DISA HQ. Working a short-term solution for DATMS-U bandwidth constraints that will<br />

connect with the long-term <strong>COPC</strong> Enterprise solution.<br />

• CSAB 16 July <strong>20</strong>09. Luis Cano – DISA working a short-term solution for DATMS-U<br />

bandwidth constraints. The technical approach h<strong>as</strong> been approved and now this effort is<br />

waiting for higher level DISA approval.<br />

• CSAB <strong>20</strong> <strong>August</strong> <strong>20</strong>09. Luis Cano – working hard with DISA for the short-term<br />

solution for DATMS-U bandwidth constraints. The JAG/CCM is waiting for CNMOC to<br />

approve submitting the TSRs.<br />

<strong>COPC</strong> <strong>Action</strong> Item <strong>20</strong>08-2.12: JAG CCM will provide an ongoing process to capture and<br />

coordinate telecommunication requirements across <strong>COPC</strong> partners. These requirements would<br />

include the size <strong>of</strong> the data, when the data needs to be transmitted, when the data needs to be<br />

received, which <strong>COPC</strong> partner will send the data, which <strong>COPC</strong> partner will receive the data, the<br />

schedule <strong>of</strong> when new data will or needs to be enabled, encryption requirements, other data<br />

restrictions, and related <strong>COPC</strong> business functions. As a follow-on action item, this process would<br />

be used to validate technical designs and resource estimates for new network infr<strong>as</strong>tructure<br />

initiatives. This process would provide <strong>COPC</strong> continuing value by supporting network capacity<br />

management for existing infr<strong>as</strong>tructure and help justify funding requests for future network<br />

upgrades. [add nuopc-specific language: capture rqmts against proposed NUOPC data rqmts]<br />

[NUOPC related]<br />

Priority: (M)<br />

Advocate: JAG/CCM – [Luis Cano (Chair)]<br />

Suspense: <strong>Spring</strong> <strong>20</strong>09 CSAB meeting or (April 1, <strong>20</strong>09).<br />

Status <strong>as</strong> <strong>of</strong> <strong>20</strong> <strong>August</strong> <strong>20</strong>09: Open.<br />

• CSAB 18 December <strong>20</strong>08. The CCM plan is to develop a template to gather<br />

requirements to allow for technical analysis on the capacity that is needed for the future<br />

and to <strong>as</strong>sist with budgetary decisions.