Building on the Promise<br />
Ready, set, build!<br />
View from the top<br />
The new critical care tower will be connected to the new parking deck and main hospital building by skywalks accessed on the third floor.<br />
Last summer, <strong>Akron</strong> Children’s announced<br />
a $200 million expansion of its <strong>Akron</strong> campus,<br />
which includes a new critical care tower. The<br />
design phase of the tower is complete, and<br />
the timeline for construction has been set.<br />
The renderings above and at right will give<br />
you a sneak peek inside the new building,<br />
which is set to open in 2015. For more<br />
information about the building project, visit<br />
http://building.akronchildrens.org/.<br />
Construction Timeline<br />
March 2013<br />
Demolition of existing buildings begins<br />
March-April 2013<br />
Preparation of site for construction<br />
May 2013<br />
Foundation construction begins<br />
June 2013<br />
Structural frame construction begins<br />
September 2013<br />
Parking garage is complete<br />
October 2013<br />
Building enclosure begins<br />
First Quarter 2014<br />
Interior finishes begin<br />