identified in relation to IPC <strong>and</strong> EC, risk assessments are currently<br />
being reviewed <strong>and</strong> updated to populate the risk register.<br />
The summary provided was updated in January 2011 however the<br />
review of this summary indicated that not all risks have been updated<br />
on a regular basis. The trust needs to ensure that risk registers which<br />
include key information on infection, prevention <strong>and</strong> control have<br />
identified timescales, are kept up to date <strong>and</strong> clearly outline the current<br />
position in relation to the identified risk.<br />
Recommendations<br />
1. The trust should ensure that all staff have <strong>and</strong> are competent<br />
to access the policies <strong>and</strong> procedures on the trust's intranet.<br />
2. The trust should develop an Environmental Cleanliness <strong>and</strong><br />
Infection Prevention <strong>and</strong> Control Strategy.<br />
3. The trust should ensure IPC controls assurance<br />
documentation clearly outlines actions required to address<br />
the outst<strong>and</strong>ing issues. New templates which reflect<br />
amendments made to the st<strong>and</strong>ards by the DHSSPSNI should<br />
be implemented in the agreed timeframe.<br />
4. The trust needs to ensure that risk registers <strong>and</strong> key<br />
information on infection, prevention <strong>and</strong> control <strong>and</strong><br />
environmental cleanliness have identified timescales, are<br />
kept up to date <strong>and</strong> clearly outline the current position in<br />
relation to the identified risk.<br />