Restoration - Citrus County - Kings Bay Park Lagoon<br />
Critical Project Milestones<br />
Projected<br />
1. CFI Agreement<br />
Execute agreement 10/01/2012<br />
2. Design and permitting<br />
Advertise RFQ for design and permitting services 01/31/2013<br />
Select contractor 05/31/2013<br />
Complete design and permitting 09/30/2013<br />
3. Restoration<br />
Advertise RFP for sediment removal/replanting 01/31/2014<br />
Select contractor 05/30/2014<br />
Complete restoration 09/30/2015<br />
4. Manatee exclusion and restoration monitoring<br />
Begin exclusion and monitoring 09/30/2012<br />
Complete exclusion and monitoring 09/30/2017<br />
5. Project closeout<br />
Closeout 10/31/2017<br />
Status As Of<br />
Amended<br />
Actual<br />