W474<br />

Restoration - Citrus County - Kings Bay Park Lagoon<br />

Critical Project Milestones<br />

Projected<br />

1. CFI Agreement<br />

Execute agreement 10/01/2012<br />

2. Design and permitting<br />

Advertise RFQ for design and permitting services 01/31/2013<br />

Select contractor 05/31/2013<br />

Complete design and permitting 09/30/2013<br />

3. Restoration<br />

Advertise RFP for sediment removal/replanting 01/31/2014<br />

Select contractor 05/30/2014<br />

Complete restoration 09/30/2015<br />

4. Manatee exclusion and restoration monitoring<br />

Begin exclusion and monitoring 09/30/2012<br />

Complete exclusion and monitoring 09/30/2017<br />

5. Project closeout<br />

Closeout 10/31/2017<br />

Status As Of<br />

Amended<br />

Actual<br />