SOLICITATION NUMBER N00173-12-R-CB02<br />

PAGE 22<br />

(11) List of Government furnished material and the estimated value thereof for each order.<br />

(f) The ceiling amount for each task order will be the ceiling price stated therein and may not be<br />

exceeded except when authorized by a modification to the task order.<br />

G-11 INFORMATION REQUIRED FOR SUBMISSION OF EACH ORDER<br />

(a) The COR or TM assigned in Section G will provide the contractor with a Statement of Work<br />

(SOW) for each order. The Contractor shall provide the COR or TM with a proposal in response<br />

to the SOW. The COR or TM will prepare an acquisition package and forward to the NRL<br />

Contracting Division for issuance of an order.<br />

(b) Direct Labor Hours, travel and material costs are subject to negotiation prior to award. In order to<br />

fully evaluate each order proposal, the contractor shall provide the following as applicable:<br />

(1) A time phased (e.g., monthly, quarterly, etc.) breakdown of direct labor by labor category.<br />

(2) A complete breakdown for travel identifying each cost mode of travel and the reason for<br />

the travel proposed.<br />

(3) A complete list of all material including quantity and cost. The contractor shall provide<br />

specific documentation to serve as the basis for price verification (i.e., vendor quotations,<br />

invoices, published price lists, GSA schedule lists, etc.).