143<br />
Location: Bridge B-839S, I-15 at California Wash<br />
Bridge Phone #: 702-720-3037<br />
B-839S SCOUR MONITORING DEVICE DATA<br />
Sonar installed on upstream nose of easternmost pier (pier 4).<br />
One channel 1 float-out installed 3 feet deep in 6 foot riprap layer at upstream nose of easternmost pier (pier 4).<br />
One channel 2 float-out installed 3 feet deep in 6 foot riprap layer at each upstream nose of center pier (pier 3)<br />
and westernmost pier (pier 2).<br />
Elevation data from contract 1108 and field measurements during installations:<br />
Piers<br />
bottom of bridge: 1818.7±<br />
top of pier walls (upstream nose): 1818.3 (pier 2), 1817.9 (pier 3), 1817.6 (pier 4)<br />
top of spread footings: 1806.3 (piers 2 & 4), 1806.7 (pier 3)<br />
bottom of spread footings: 1805.0<br />
Sonar (This data is programmed in the monitoring equipment)<br />
sonar transducer elevation: 1812.0<br />
ground elevation (riprap) referenced by sonar at time of installation: 1810.0±<br />
elevation readings that trigger successive pager/computer calls: 1808.0, 1805.0<br />
Float-Outs<br />
ground (riprap) elevation at float-out locations at time of installation: 1810.0±<br />
float-out elevation: 1807.0±<br />
Location: Bridge B-839S, I-15 at California Wash<br />
B-839S SCOUR RESPONSE PLAN<br />
<strong>Scour</strong> Event Pager Message: "839, California Wash” [false alarm if 839 is missing or different]<br />
Pager Group Members: Phone # Cell Phone #<br />
Maintenance Supervisor 1<br />
Maintenance Supervisor 2<br />
Maintenance Superintendent<br />
District Maintenance Engineer<br />
Principal Bridge Maintenance Engineer<br />
Responses to Sonar Calls:<br />
First call at elevation reading of 1808.0<br />
<strong>Scour</strong> Location: 2.0' into 6.0' riprap layer (scour depth = 2.0')<br />
Response:<br />
Mobilize to monitor and potentially close bridge<br />
Second call at elevation reading of 1805.0<br />
<strong>Scour</strong> Location: Bottom of spread footing (scour depth = 5.0')<br />
Response:<br />
Close bridge<br />
Responses to Float-Out Calls:<br />
First call from channel 1 float-out<br />
<strong>Scour</strong> Location: Nose of east pier at midpoint of 6.0' riprap layer (scour depth = 3.0')<br />
Response:<br />
Mobilize to monitor and potentially close bridge<br />
First call from channel 2 float-out<br />
<strong>Scour</strong> Location: Nose of center or west pier at midpoint of 6.0' riprap layer (scour depth = 3.0')<br />
Response:<br />
Mobilize to monitor and potentially close bridge