<strong>Honolulu</strong> <strong>Rail</strong> <strong>Transit</strong> <strong>Project</strong> Programmatic Agreement Expanded Schedule<br />
as of October 30, 2012<br />
Deliverable<br />
Start<br />
Date<br />
VI. National Register of Historic Places<br />
A. Multiple Property Documentation July 2013 December 2014<br />
B. NHL Nominations<br />
United States Naval Base, Pearl Harbor NHL May 2013 December 2015 Coordinated with NAVY completion of ICRMP<br />
CINCPAC Headquarters Building NHL August 2012 July 2013<br />
C. NRHP Nominations<br />
Honouliuli Stream Bridge March 2012 December 2013<br />
Waikele Stream Bridge and Span over OR&L August 2012 February 2013<br />
1932 Waiawa Stream Bridge August 2012 February 2013<br />
Waimalu Stream Bridge August 2012 February 2013<br />
Kalauao Spring Bridge August 2012 February 2013<br />
Kalauao Stream Bridge August 2012 February 2013<br />
Makalapa Navy Housing Historic District November 2012 August 2013<br />
Ossipoff’s Aloha Chapel, SMART Clinic, and Navy- November 2012 August 2013<br />
Marine Corps Relief Society<br />
Little Makalapa Navy Housing Historic District November 2012 August 2013<br />
Hawai‘i Employers Council January 2013 August 2013<br />
Kapālama Canal Bridge January 2013 August 2013<br />
Nu‘uanu Stream Bridge January 2013 August 2013<br />
Lava Rock Curbs May 2013 December 2013<br />
Six Quonset Huts May 2013 December 2013<br />
True Kamani Trees May 2013 December 2013<br />
Institute for Human Services/Tamura Building May 2013 December 2013<br />
Wood Tenement Buildings May 2013 December 2013<br />
Oahu <strong>Rail</strong> & Land Co. Office and Document Storage May 2013 December 2013<br />
Building<br />
Oahu <strong>Rail</strong> & Land Co. Terminal Building May 2013 December 2013<br />
Chinatown Historic District August 2012 February 2013<br />
Merchant Street Historic District August 2012 February 2013<br />
HDOT Harbors Division Offices August 2012 February 2013<br />
Pier 10/11 Building August 2012 February 2013<br />
Aloha Tower November 2012 August 2013<br />
Irwin Park November 2012 August 2013<br />
Walker Park November 2012 August 2013<br />
HECO Downtown Plant November 2012 August 2013<br />
Dillingham Transportation Building November 2012 August 2013<br />
Mother Waldron Playground November 2012 August 2013<br />
D. Clarification on MPS No activity, clarification text<br />
E. Also follow HRS 6E No activity, clarification text<br />
F. Develop searchable database April 2012 December 2015 Active on project website, to be updated as information<br />
accepted by SHPD and NPS<br />
G. Coordination with SHPD on database continuity December 2015 EOC<br />
VII. Educational and Interpretive Programs, Materials, and Signage<br />
A. Interpretive Plan July 2011 December 2015 Stations are being designed to include interpretive<br />
placards. Content to be finalized prior to opening.<br />
B. History Brochure July 2015 December 2015 Will contain information from Interpretive Plan<br />
C. Children's Materials December 2015 December 2016 Materials need to be available prior to operation.<br />
D. Humanities Program May 2012 December 2014<br />
E. Public Workshop January 2013 January 2014<br />
F. Educational Field Guides May 2012 December 2014 Field guide will be based on content developed in<br />
Stipulations V and VI.<br />
G. Planning Kickoff May 2011 May 2011 Held two meetings, discussion options for Humanities<br />
and Interpretive Programs.<br />
H. Review of Materials Process stipulation tied to A-F above.<br />
VIII. Mitigation for Specific Historic Properties (all in City Center)<br />
End<br />
Date<br />
A. Lava Rock Curbstones January 2015 April 2018<br />
B. Kapalama Canal Bridge <strong>Rail</strong> November 2014 February 2018<br />
C. True Kamani Trees November 2014 February 2018<br />
D. Park Improvement Plan December 2014 12/1/2016 Will follow CLRs.<br />
IX. Measures to Address Reasonably Foreseeable Indirect and Cumulative Effects<br />
A. Hire Architectural Historian See I.G.<br />
B. Historic Preservation Committee July 2011 December 2014<br />
C. Demolition Monitoring January 2012 EOC Baseline for monitoring established 29 properties. First<br />
annual report produced January 2012.<br />
D. Unanticipated Adverse Effects Identification EOC Process<br />
E. Chinatown and Merchant Street Additional<br />
requirements<br />
February 2013 EOC + 6 months<br />
Notes<br />
Green = Activity Complete<br />
EOC = End of Construction 3