q<br />

Inspection report format of State Level Monitors notified<br />

7. Beneficiary selection<br />

q Preparing transparent criteria for prioritizing 7,972 beneficiaries from the<br />

12,548 fully/severely damaged houses based on the principle of prioritization<br />

based on degree of damage to house and economic status. Prioritization<br />

done in special gram sabha using these criteria.<br />

q<br />

5,800 beneficiaries prioritized of the total target of 7,972 in 140 Gram Sabhas.<br />

Beneficiary List has been placed in public domain and is also available at<br />

www.sikkimrmdd.gov.in web portal. Remaining to be completed shortly.<br />

Capacity building and IEC<br />

q Training of technical staff: The AE/JEs have been trained in the technical<br />

aspects of house construction and management of block level stores<br />

in various training workshops. Also the “Mason Training Handbook” has been<br />

prepared in both English and Nepali to simplify the technical aspects<br />

of house construction.<br />

q<br />

q<br />

Training of accounts staff to maintain accounts and management of block<br />

level stores by the store keepers has also been conducted.<br />

Record keeping: Record keeping at District, Block and Block Level Stores has<br />

been simplified by providing pre-printed registers and training has also been<br />

conducted<br />

8. Why progress appears slow<br />

q Finalizing the technical house design took time: Consultation with experts from<br />

NDMA, People’s Science Institute and others<br />

q<br />

q<br />

Finalizing the strategy for stock material purchase and management which<br />

is transparent and fair. 23 lakh bags of cement and 2 lakh quintals of TMT bars<br />

need to be not only purchased transparently, but also provided to 7,972<br />

destinations as per requirement without leakage.<br />

Establishment of Block Level Stores for the first time<br />

q Prioritization of beneficiaries: Prioritization 7,972 of the total 12,548<br />

beneficiaries following a transparent criteria in special gram Sabhas<br />

q<br />

q<br />

Inadequate staff at Block level: Existing technical staff at the Block level<br />

(1AE and 3 JEs) are already constructing 6,000 houses under Rural Housing<br />

Mission and implementing flagship programs like MGNREGA, IAY,<br />

NRDWP, TSC, BRGF, NSAP and various other state programmes<br />

Shortage of masons and labour: Already 6,000 houses under Rural Housing<br />

Mission are under various stages of construction. There is an acute shortage of<br />

masons and labour to build the houses<br />

SOUTH SIKKIM EARTHQUAKE REPORT<br />