CONTACTS:<br />
Chief <strong>of</strong> Police Keith Atkinson - <strong>729</strong>-2305<br />
Inspector Shane Corley – <strong>729</strong>-2302<br />
Inspector Ian Grant - <strong>729</strong>-2304<br />
______________________________________________________________________________________________<br />
Inspector Ian Grant<br />
Effective Monday, November 21 st , 2011 Inspector Ian Grant will be seconded to work with the Provincial<br />
Government, Department <strong>of</strong> Justice for a ten month period. This secondment will conclude on Friday,<br />
September 28 th , 2012.<br />
Inspector Grant has been seconded as a Policing Services Consultant with Policing Services Branch,<br />
Criminal Justice Division, Manitoba Justice and will report directly to Mr. Glen Lewis, Executive Director <strong>of</strong><br />
Public Safety and Strategic Initiatives, Criminal Justice Division.<br />
Change <strong>of</strong> Command 26 th Field Regiment<br />
Chief Atkinson attended the Change <strong>of</strong> Command Ceremony in Shilo on October 29 th , 2011. Lieutenant<br />
Colonel Dave Dalal has taken over command <strong>of</strong> the 26 th Field Regiment.<br />
Building Update<br />
Construction Progress: Week Ending November 4 th , 2011<br />
Exterior:<br />
- The masonry has been installed along the south elevation, gridline 7a-13.<br />
- The masonry has been installed along the east elevation, gridline A-K.<br />
- The masonry has been installed along the north elevation, gridline 1-3.<br />
- The electrical trenching and conduit installation has been executed in the parking lot area.<br />
- The ro<strong>of</strong> decking for the Operations garage has been installed.<br />
- The light standard bases have been formed and poured.<br />
- The front entrance slab has been poured.<br />
- The installation <strong>of</strong> the gypsum for the exterior walls is on-going on all elevations.<br />
Interior:<br />
- The holding cell ro<strong>of</strong> slabs have been formed and poured.<br />
- The electrical wall rough ins are on-going in the steel stud locations.<br />
- The plumbers have continued with the installation <strong>of</strong> the water mains for the building.<br />
- The plumbers have also been roughing in the bathroom walls.<br />
- The HVAC installation <strong>of</strong> the laboratory ventilation is on-going.<br />
- The HVAC runs and VAV installation is continuing.<br />
- The structural steel channels required in the East Corridor is on-going.<br />
- The temp heat preparations are underway.<br />
- The temp water meter is being installed this week.